Ruparel Palacio Ph I

by Shree Siddhivinayak Infrastructure & Realty (Ruparel) · Kandivali, MumbaiAlso near Malad West, Bandra, Iraniwadi

Possession date of Ruparel Palacio Ph I: 31 December 2025, moved from 30 December 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800013681. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Ruparel Palacio Ph I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ruparel Palacio Ph I has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800018866)

    Reason the builder gave MahaRERA:
    “Subject: Application for Extension of Project "Ruparel Palacio" – RERA Regn. No.: P51800013681 Respected Authority Members, We, M/s. Shree Siddhivinayak Infra & Realty, promoters of the project Ruparel Palacio (RERA Regn. No. P51800013681),…” Read the full reason“Subject: Application for Extension of Project "Ruparel Palacio" – RERA Regn. No.: P51800013681 Respected Authority Members, We, M/s. Shree Siddhivinayak Infra & Realty, promoters of the project Ruparel Palacio (RERA Regn. No. P51800013681), request an extension of the project completion date to 31st December 2025 due to unavoidable delays. Project Overview: Ruparel Palacio is a high-rise residential project with a ground floor and 43 upper floors. The project has received a No Objection Certificate from the Airports Authority of India (issued on 31st January 2018, valid until 30th January 2…”

Source: Ruparel Palacio Ph I’s extension records on MahaRERA (P51800013681), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ruparel Palacio Ph I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800013681
Status
Lapsed (registration period ended)
Builder
Shree Siddhivinayak Infrastructure & Realty
Location
Kandivali, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
23 Oct 2017
Completion date at registration
December 2023
Latest completion date
December 2025
Delay so far
24 months
Homes
84
Sold or booked
74%
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Ruparel Palacio Ph I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Ruparel Palacio100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ruparel Palacio Ph I every month.

Ruparel Palacio Ph I: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK856 – 95673
2 BHK632 – 71111
Shops472 – 1,4416

The builder’s record and reviews

Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects.

Read Google reviews of Ruparel Palacio Ph I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ruparel Palacio Ph I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ruparel Palacio Ph I

What is the possession date of Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ruparel Palacio Ph I in Kandivali, Mumbai is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Ruparel Palacio Ph I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ruparel Palacio Ph I's builder has filed on MahaRERA, the official one, is 31 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ruparel Palacio Ph I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "Subject: Application for Extension of Project "Ruparel Palacio" – RERA Regn. No.: P51800013681 Respected Authority Members, We, M/s. Shree Siddhivinayak Infra & Realty, promoters of the project Ruparel Palacio (RERA Regn. No. P51800013681), request an extension of the project completion date to 31st December 2025 due to unavoidable delays. Project Overview: Ruparel Palacio is a high-rise residential project with a ground floor and 43 upper floors. The project has received a No Objection Certificate from the Airports Authority of India (issued on 31st January 2018, valid until 30th January 2…".

What is the RERA number of Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ruparel Palacio Ph I in Kandivali, Mumbai is P51800013681.

Is Ruparel Palacio Ph I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I is registered as P51800013681 and its status is "Lapsed (registration period ended)".

What is the construction status of Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Ruparel Palacio is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Ruparel Palacio Ph I have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Ruparel Palacio Ph I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I is registered on MahaRERA as P51800013681, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ruparel Palacio Ph I's possession date changes?

The latest dates are on Ruparel Palacio Ph I's MahaRERA page (P51800013681). GharKundli's Kundli Watch sends a free WhatsApp update on Ruparel Palacio Ph I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ruparel Palacio Ph I have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I has one building filed: Ruparel Palacio with 43 floors.

What are the flat sizes (carpet area) in Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ruparel Palacio Ph I: 3 BHK: 856 to 956 sq ft carpet (73 homes); 2 BHK: 632 to 711 sq ft carpet (11 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I stands on 2,065 sq m of land (about 0.5 acres), with 4,178 sq m of sanctioned built-up area and 165 sq m of recreational open space.

What is the track record of Ruparel Palacio Ph I's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Infra & Realty (a group of 12 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 47 months); 13 still being built, 7 past the promised date (typically 28 months late); 10 lapsed. 856 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ruparel Palacio Ph I?

Google Maps has reviews of Ruparel Palacio Ph I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ruparel Palacio Ph I?

Ruparel Palacio Ph I by Shree Siddhivinayak Infrastructure & Realty (Ruparel) is in Kandivali, Mumbai (pincode 400067), near Malad West, Bandra, Iraniwadi, Maharashtra, and is registered on MahaRERA as P51800013681, per GharKundli's check of MahaRERA records.

How many homes are in Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I has 84 homes in 1 tower registered on MahaRERA, and 74% of them are sold or booked.

When was Ruparel Palacio Ph I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ruparel Palacio Ph I was registered on MahaRERA on 23 October 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Ruparel Palacio Ph I?

No court cases are listed for Ruparel Palacio Ph I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Ruparel Palacio Ph I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shree Siddhivinayak Infrastructure & Realty, the company Ruparel files this project under, which has 2 other projects registered on MahaRERA.

Other projects in pincode 400067

All 318 projects in Kandivali West (400067) →

Other projects by Shree Siddhivinayak Infrastructure & Realty

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.