Skip to content
GharKundli

MANTHAN ACROPOLIS

by MANTHAN DEVELOPMENT CORPORATION · Parksite Vikhroli West, MumbaiAlso near Vikhroli East

Possession date of MANTHAN ACROPOLIS: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800015626, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MANTHAN ACROPOLIS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MANTHAN ACROPOLIS has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800013329)

    Reason the builder gave MahaRERA:
    “As per the revised Market Redevelopment Policy vide Govt. notification u/no. TPB-4320/120/C.R.79/2020/UD-11 dated 01/04/2021, we are awaiting the revised approvals from the BMC for consumption of permissible FSI on the plot of land bearing…” Read the full reason“As per the revised Market Redevelopment Policy vide Govt. notification u/no. TPB-4320/120/C.R.79/2020/UD-11 dated 01/04/2021, we are awaiting the revised approvals from the BMC for consumption of permissible FSI on the plot of land bearing CTS No. 38 B of village Vikhroli (W), Mumbai – 400 079 of the proposed building known as Manthan Acropolis.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT51800018244)

    Reason the builder gave MahaRERA:
    “As per the revised Market Redevelopment Policy vide Govt. notification u/no. TPB-4320/120/C.R.79/2020/UD-11 dated 01/04/2021, the BMC has issued the revised LOI u/no. AC/Market/012794/AE(Mkt.)-1 dt. 29/08/2023 for the proposed project known…” Read the full reason“As per the revised Market Redevelopment Policy vide Govt. notification u/no. TPB-4320/120/C.R.79/2020/UD-11 dated 01/04/2021, the BMC has issued the revised LOI u/no. AC/Market/012794/AE(Mkt.)-1 dt. 29/08/2023 for the proposed project known as Manthan Acropolis after the sanctions of Improvement Committee vide their Resolution dt. 17/02/2023 and Corporation Resolution dt. 01/03/2023 respectively of BMC for consumption of additional FSI on the said plot bearing CTS No. 38 B of village Vikhroli (W), Mumbai – 400 079. Now we are awaiting the further revised / amended IOD & further CC from the…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MANTHAN ACROPOLIS’s extension records on MahaRERA (P51800015626), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MANTHAN ACROPOLIS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800015626
Status
Registered and active
Builder
MANTHAN DEVELOPMENT CORPORATION
Location
Parksite Vikhroli West, Mumbai · 400079
Project type
Mixed
Registered on
15 Mar 2018
Completion date at registration
December 2022
Latest completion date
April 2027
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
34
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of MANTHAN ACROPOLIS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MANTHAN ACROPOLIS100%60%30%0%

Commencement certificate (CC), as filed on MahaRERA

  • MANTHAN ACROPOLIS: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANTHAN ACROPOLIS every month.

MANTHAN ACROPOLIS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK436 – 45727
1 Room Kitchen2197

The builder’s record and reviews

Manthan Development Corporation has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 20 months late). 5 complaints on MahaRERA across 2 projects.

Read Google reviews of MANTHAN ACROPOLIS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MANTHAN ACROPOLIS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MANTHAN ACROPOLIS

What is the possession date of MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MANTHAN ACROPOLIS in Parksite Vikhroli West, Mumbai is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MANTHAN ACROPOLIS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MANTHAN ACROPOLIS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MANTHAN ACROPOLIS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2023, giving the reason "As per the revised Market Redevelopment Policy vide Govt. notification u/no. TPB-4320/120/C.R.79/2020/UD-11 dated 01/04/2021, we are awaiting the revised approvals from the BMC for consumption of permissible FSI on the plot of land bearing CTS No. 38 B of village Vikhroli (W), Mumbai – 400 079 of the proposed building known as Manthan Acropolis."; to 31 December 2026, giving the reason "As per the revised Market Redevelopment Policy vide Govt. notification u/no. TPB-4320/120/C.R.79/2020/UD-11 dated 01/04/2021, the BMC has issued the revised LOI u/no. AC/Market/012794/AE(Mkt.)-1 dt. 29/08/2023 for the proposed project known as Manthan Acropolis after the sanctions of Improvement Committee vide their Resolution dt. 17/02/2023 and Corporation Resolution dt. 01/03/2023 respectively of BMC for consumption of additional FSI on the said plot bearing CTS No. 38 B of village Vikhroli (W), Mumbai – 400 079. Now we are awaiting the further revised / amended IOD & further CC from the…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MANTHAN ACROPOLIS in Parksite Vikhroli West, Mumbai is P51800015626.

Is MANTHAN ACROPOLIS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS is registered as P51800015626 and its status is "Registered and active".

What is the construction status of MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MANTHAN ACROPOLIS is 60% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.

Does MANTHAN ACROPOLIS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MANTHAN ACROPOLIS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS is registered on MahaRERA as P51800015626, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MANTHAN ACROPOLIS's possession date changes?

The latest dates are on MANTHAN ACROPOLIS's MahaRERA page (P51800015626). GharKundli's Kundli Watch sends a free WhatsApp update on MANTHAN ACROPOLIS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MANTHAN ACROPOLIS have?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS has one building filed: MANTHAN ACROPOLIS with 9 floors and 34 units.

What are the flat sizes (carpet area) in MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MANTHAN ACROPOLIS: 1 BHK: 436 to 457 sq ft carpet (27 homes); 1 Room Kitchen: 219 sq ft carpet (7 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS stands on 1,040 sq m of land (about 0.3 acres), with 2,158 sq m of sanctioned built-up area and 168 sq m of recreational open space.

What is the track record of MANTHAN ACROPOLIS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Manthan Development Corporation has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 20 months late). 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MANTHAN ACROPOLIS?

Google Maps has reviews of MANTHAN ACROPOLIS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MANTHAN ACROPOLIS?

MANTHAN ACROPOLIS by MANTHAN DEVELOPMENT CORPORATION is in Parksite Vikhroli West, Mumbai (pincode 400079), near Vikhroli East, Maharashtra, and is registered on MahaRERA as P51800015626, per GharKundli's check of MahaRERA records.

How many homes are in MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS has 34 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was MANTHAN ACROPOLIS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MANTHAN ACROPOLIS was registered on MahaRERA on 15 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on MANTHAN ACROPOLIS?

No court cases are listed for MANTHAN ACROPOLIS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MANTHAN ACROPOLIS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANTHAN DEVELOPMENT CORPORATION, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400079

All 24 projects in Vikhroli (400079) →

Other projects by MANTHAN DEVELOPMENT CORPORATION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.