by Lodha Developers Limited · Vikhroli, MumbaiAlso near Tagore Nagar

Possession date of Vikhroli ASPI Project 2: 30 May 2029, moved from 31 January 2028 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800054375, and currently active. Its completion date has moved from January 2028 to May 2029: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Vikhroli ASPI Project 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vikhroli ASPI Project 2 has moved

  1. 31 January 2028

    Completion date given when the project was registered

  2. 30 January 2029

    Extended at the builder's request (MahaRERA application EA04052620827)

    Reason the builder gave MahaRERA:
    “We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 2” bearing MahaRERA Registration No. P51800054375. The applicant promoter respectfully submits that…” Read the full reason“We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 2” bearing MahaRERA Registration No. P51800054375. The applicant promoter respectfully submits that the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance. The project site falls within a 5-kilometre radius of Thane Creek Flamingo Sanctuary”
  3. 30 May 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Vikhroli ASPI Project 2’s extension records on MahaRERA (P51800054375), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vikhroli ASPI Project 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the May 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800054375
Status
Registered and active
Builder
Lodha Developers Limited
Location
Vikhroli, Mumbai · 400079
Project type
Residential / Group Housing
Registered on
18 Jan 2024
Completion date at registration
January 2028
Latest completion date
May 2029
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
81
Sold or booked
91%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Vikhroli ASPI Project 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sale building 3-Sale Wing A4100%78%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Sale building 3-Sale Wing A4: covers 23 floors

Latest CC order on MahaRERA: dated 09/12/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vikhroli ASPI Project 2 every month.

Vikhroli ASPI Project 2: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Other663 – 1,62281
  • Buildings: Sale building 3-Sale Wing A4 (23 floors, 81 units)
  • Car parking: 97 covered
  • Land: 1,482 sq m (about 0.4 acres) · sanctioned built-up 8,029 sq m · recreational space 119 sq m
  • Boundaries filed include: LBS Rd

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.

Read Google reviews of Vikhroli ASPI Project 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vikhroli ASPI Project 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vikhroli ASPI Project 2

What is the possession date of Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vikhroli ASPI Project 2 in Vikhroli, Mumbai is 30 May 2029 — 12 months later than 31 January 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Vikhroli ASPI Project 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vikhroli ASPI Project 2's builder has filed on MahaRERA, the official one, is 30 May 2029, already 12 months later than the 31 January 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vikhroli ASPI Project 2 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2's builder applied to MahaRERA to extend the completion date once: to 30 January 2029, giving the reason "We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 2” bearing MahaRERA Registration No. P51800054375. The applicant promoter respectfully submits that the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance. The project site falls within a 5-kilometre radius of Thane Creek Flamingo Sanctuary". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vikhroli ASPI Project 2 in Vikhroli, Mumbai is P51800054375.

Is Vikhroli ASPI Project 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2 is registered as P51800054375 and its status is "Registered and active".

What is the construction status of Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sale building 3-Sale Wing A4 is 78% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Vikhroli ASPI Project 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vikhroli ASPI Project 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2 is registered on MahaRERA as P51800054375, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Vikhroli ASPI Project 2 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Vikhroli ASPI Project 1 (P51800053072, possession 30 Sep 2029); Vikhroli ASPI Project 3 (P51800053253, possession 29 Sep 2029); Vikhroli ASPI Project 4 (P51800078490, possession 31 Dec 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Vikhroli ASPI Project 2's possession date changes?

The latest dates are on Vikhroli ASPI Project 2's MahaRERA page (P51800054375). GharKundli's Kundli Watch sends a free WhatsApp update on Vikhroli ASPI Project 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vikhroli ASPI Project 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2 has one building filed: Sale building 3-Sale Wing A4 with 23 floors and 81 units.

What are the flat sizes (carpet area) in Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vikhroli ASPI Project 2: Other: 663 to 1622 sq ft carpet (81 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Vikhroli ASPI Project 2 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 97 covered car parking spaces for Vikhroli ASPI Project 2.

How big is the land of Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2 stands on 1,482 sq m of land (about 0.4 acres), with 8,029 sq m of sanctioned built-up area and 119 sq m of recreational open space.

What is the track record of Vikhroli ASPI Project 2's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Vikhroli ASPI Project 2?

Google Maps has reviews of Vikhroli ASPI Project 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vikhroli ASPI Project 2?

Vikhroli ASPI Project 2 by Lodha Developers Limited is in Vikhroli, Mumbai (pincode 400079), near Tagore Nagar, Maharashtra, and is registered on MahaRERA as P51800054375, per GharKundli's check of MahaRERA records. Its boundaries filed there include LBS Rd.

How many homes are in Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2 has 81 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.

When was Vikhroli ASPI Project 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 2 was registered on MahaRERA on 18 January 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on Vikhroli ASPI Project 2?

1 court case is listed for Vikhroli ASPI Project 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Vikhroli ASPI Project 2?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in pincode 400079

All 24 projects in Vikhroli (400079) →

Other projects by Lodha Developers Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.