Vikhroli ASPI Project 3

by Lodha Developers Limited · Vikhroli, MumbaiAlso near Tagore Nagar

Possession date of Vikhroli ASPI Project 3: 29 September 2029, moved from 30 September 2028 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800053253, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Vikhroli ASPI Project 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vikhroli ASPI Project 3 has moved

  1. 30 September 2028

    Completion date given when the project was registered

  2. 29 September 2029

    Extended at the builder's request (MahaRERA application EA11052620897)

    Reason the builder gave MahaRERA:
    “We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 3” bearing MahaRERA Registration No. P51800053253. The applicant promoter respectfully submits that…” Read the full reason“We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 3” bearing MahaRERA Registration No. P51800053253. The applicant promoter respectfully submits that the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance. The project site falls within a 5-kilometre radius of Thane Creek Flamingo Sanctuary”

Source: Vikhroli ASPI Project 3’s extension records on MahaRERA (P51800053253), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vikhroli ASPI Project 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the September 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800053253
Status
Registered and active
Builder
Lodha Developers Limited
Location
Vikhroli, Mumbai · 400079
Project type
Residential / Group Housing
Registered on
23 Oct 2023
Completion date at registration
September 2028
Latest completion date
September 2029
Delay so far
12 months
Homes
137
Sold or booked
63%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
180

Construction progress of Vikhroli ASPI Project 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A3100%66%18%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A3: covers 38 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vikhroli ASPI Project 3 every month.

Vikhroli ASPI Project 3: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK975 – 2,005132
Other847 – 2,3645
  • Buildings: Wing A3 (38 floors, 137 units)
  • Land: 3,242 sq m (about 0.8 acres) · sanctioned built-up 13,681 sq m · recreational space 553 sq m
  • Boundaries filed include: LBS Road

The builder’s record and reviews

Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.

Read Google reviews of Vikhroli ASPI Project 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vikhroli ASPI Project 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vikhroli ASPI Project 3

What is the possession date of Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vikhroli ASPI Project 3 in Vikhroli, Mumbai is 29 September 2029 — 12 months later than 30 September 2028, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Vikhroli ASPI Project 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vikhroli ASPI Project 3's builder has filed on MahaRERA, the official one, is 29 September 2029, already 12 months later than the 30 September 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vikhroli ASPI Project 3 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3's builder applied to MahaRERA to extend the completion date once: to 29 September 2029, giving the reason "We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 3” bearing MahaRERA Registration No. P51800053253. The applicant promoter respectfully submits that the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance. The project site falls within a 5-kilometre radius of Thane Creek Flamingo Sanctuary".

What is the RERA number of Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vikhroli ASPI Project 3 in Vikhroli, Mumbai is P51800053253.

Is Vikhroli ASPI Project 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3 is registered as P51800053253 and its status is "Registered and active".

What is the construction status of Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A3 is 66% done and internal work 18%. GharKundli's full report compares construction progress with the deadline.

Does Vikhroli ASPI Project 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Vikhroli ASPI Project 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3 is registered on MahaRERA as P51800053253, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Vikhroli ASPI Project 3 have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Vikhroli ASPI Project 1 (P51800053072, possession 30 Sep 2029); Vikhroli ASPI Project 2 (P51800054375, possession 30 May 2029); Vikhroli ASPI Project 4 (P51800078490, possession 31 Dec 2030). Check that your agreement names the registration of your own wing.

How can I get updates if Vikhroli ASPI Project 3's possession date changes?

The latest dates are on Vikhroli ASPI Project 3's MahaRERA page (P51800053253). GharKundli's Kundli Watch sends a free WhatsApp update on Vikhroli ASPI Project 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vikhroli ASPI Project 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3 has one building filed: Wing A3 with 38 floors and 137 units.

What are the flat sizes (carpet area) in Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vikhroli ASPI Project 3: 3 BHK: 975 to 2005 sq ft carpet (132 homes); Other: 847 to 2364 sq ft carpet (5 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3 stands on 3,242 sq m of land (about 0.8 acres), with 13,681 sq m of sanctioned built-up area and 553 sq m of recreational open space.

What is the track record of Vikhroli ASPI Project 3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Vikhroli ASPI Project 3?

Google Maps has reviews of Vikhroli ASPI Project 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vikhroli ASPI Project 3?

Vikhroli ASPI Project 3 by Lodha Developers Limited is in Vikhroli, Mumbai (pincode 400079), near Tagore Nagar, Maharashtra, and is registered on MahaRERA as P51800053253, per GharKundli's check of MahaRERA records. Its boundaries filed there include LBS Road.

How many homes are in Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3 has 137 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.

When was Vikhroli ASPI Project 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 3 was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Vikhroli ASPI Project 3?

1 court case is listed for Vikhroli ASPI Project 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Vikhroli ASPI Project 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in pincode 400079

All 24 projects in Vikhroli (400079) →

Other projects by Lodha Developers Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.