Vikhroli ASPI Project 4
by Lodha Developers Limited · Vikhroli, MumbaiAlso near Tagore Nagar
Possession date of Vikhroli ASPI Project 4: 31 December 2030, moved from 31 December 2029 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800078490, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vikhroli ASPI Project 4?
How the possession date of Vikhroli ASPI Project 4 has moved
31 December 2029
Completion date given when the project was registered
31 December 2030
Extended at the builder's request (MahaRERA application EA11052620899)
Reason the builder gave MahaRERA:
“We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 4” bearing MahaRERA Registration No. P51800078490. The applicant promoter respectfully submits that…” Read the full reason
“We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 4” bearing MahaRERA Registration No. P51800078490. The applicant promoter respectfully submits that the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance. The project site falls within a 5-kilometre radius of Thane Creek Flamingo Sanctuary”
Source: Vikhroli ASPI Project 4’s extension records on MahaRERA (P51800078490), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vikhroli ASPI Project 4
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Vikhroli ASPI Project 1P51800053072 · possession 30 Sep 2029
- Vikhroli ASPI Project 2P51800054375 · possession 30 May 2029
- Vikhroli ASPI Project 3P51800053253 · possession 29 Sep 2029
- MahaRERA registration
- P51800078490
- Status
- Registered and active
- Builder
- Lodha Developers Limited
- Location
- Vikhroli, Mumbai · 400079
- Project type
- Residential / Group Housing
- Registered on
- 17 Dec 2024
- Completion date at registration
- December 2029
- Latest completion date
- December 2030
- Delay so far
- 12 months
- Homes
- 135
- Sold or booked
- 48%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 180
Construction progress of Vikhroli ASPI Project 4, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A5 | 0% | 14% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A5: covers 35 floors
Latest CC order on MahaRERA: dated 23/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vikhroli ASPI Project 4 every month.
Vikhroli ASPI Project 4: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 932 – 2,605 | 135 |
- Buildings: A5 (35 floors, 135 units)
- Land: 1,162 sq m (about 0.3 acres) · sanctioned built-up 7,203 sq m · recreational space 86 sq m
The builder’s record and reviews
Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects.
Read Google reviews of Vikhroli ASPI Project 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vikhroli ASPI Project 4: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vikhroli ASPI Project 4
What is the possession date of Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vikhroli ASPI Project 4 in Vikhroli, Mumbai is 31 December 2030 — 12 months later than 31 December 2029, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Vikhroli ASPI Project 4?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vikhroli ASPI Project 4's builder has filed on MahaRERA, the official one, is 31 December 2030, already 12 months later than the 31 December 2029 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vikhroli ASPI Project 4 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "We hereby submit this application seeking an extension us 6 of the project completion date for our registered project “Vikhroli ASPI Project 4” bearing MahaRERA Registration No. P51800078490. The applicant promoter respectfully submits that the project has been delayed due to circumstances beyond the control of the promoter, primarily relating to issues concerning the requirement of Environmental Clearance (EC) and jurisdictional ambiguity between the Central and State authorities for granting such clearance. The project site falls within a 5-kilometre radius of Thane Creek Flamingo Sanctuary".
What is the RERA number of Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vikhroli ASPI Project 4 in Vikhroli, Mumbai is P51800078490.
Is Vikhroli ASPI Project 4 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4 is registered as P51800078490 and its status is "Registered and active".
What is the construction status of Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A5 is 14% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Vikhroli ASPI Project 4 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vikhroli ASPI Project 4 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4 is registered on MahaRERA as P51800078490, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Vikhroli ASPI Project 4 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: Vikhroli ASPI Project 1 (P51800053072, possession 30 Sep 2029); Vikhroli ASPI Project 2 (P51800054375, possession 30 May 2029); Vikhroli ASPI Project 3 (P51800053253, possession 29 Sep 2029). Check that your agreement names the registration of your own wing.
How can I get updates if Vikhroli ASPI Project 4's possession date changes?
The latest dates are on Vikhroli ASPI Project 4's MahaRERA page (P51800078490). GharKundli's Kundli Watch sends a free WhatsApp update on Vikhroli ASPI Project 4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vikhroli ASPI Project 4 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4 has one building filed: A5 with 35 floors and 135 units.
What are the flat sizes (carpet area) in Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vikhroli ASPI Project 4: Other: 932 to 2605 sq ft carpet (135 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4 stands on 1,162 sq m of land (about 0.3 acres), with 7,203 sq m of sanctioned built-up area and 86 sq m of recreational open space.
What is the track record of Vikhroli ASPI Project 4's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Lodha (Macrotech) (a group of 4 linked companies) has 387 projects on MahaRERA since 2017, this one included. Of the 375 GharKundli has checked: 208 finished, 190 within the promised date and 18 needed more time (typically 11 months); 167 still being built, 13 past the promised date (typically 3 months late). 584 complaints on MahaRERA across 155 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vikhroli ASPI Project 4?
Google Maps has reviews of Vikhroli ASPI Project 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vikhroli ASPI Project 4?
Vikhroli ASPI Project 4 by Lodha Developers Limited is in Vikhroli, Mumbai (pincode 400079), near Tagore Nagar, Maharashtra, and is registered on MahaRERA as P51800078490, per GharKundli's check of MahaRERA records.
How many homes are in Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4 has 135 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.
When was Vikhroli ASPI Project 4 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vikhroli ASPI Project 4 was registered on MahaRERA on 17 December 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Vikhroli ASPI Project 4?
No court cases are listed for Vikhroli ASPI Project 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Vikhroli ASPI Project 4?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lodha Developers Limited, which has 180 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vikhroli ASPI Project 4
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in pincode 400079
- MANTHAN ACROPOLIS
- Lodha Vikhroli - Tower C1
- Lodha Vikhroli-Signet
- Vikhroli ASPI Project 1
- Vikhroli ASPI Project 3
- Vikhroli ASPI Project 2
- Vikhroli Tower C3
- Vikhroli Premium Tower A1
Other projects by Lodha Developers Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.