SHEETAL VAIBHAV
by D.G.S TOWNSHIP PRIVATE LIMITED · Khar West, Mumbai
Registered on MahaRERA under P51800019010. Status: Completed. Its completion date has moved from May 2022 to December 2025, 43 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on SHEETAL VAIBHAV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800019010
- Status
- Completed
- Builder
- D.G.S TOWNSHIP PRIVATE LIMITED
- Location
- Khar West, Mumbai · 400052
- Project type
- Residential / Group Housing
- Registered on
- 28 Dec 2018
- Completion date at registration
- May 2022
- Latest completion date
- December 2025
- Delay so far
- 43 months
- Homes
- 11
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
SHEETAL VAIBHAV: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about SHEETAL VAIBHAV
Is SHEETAL VAIBHAV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL VAIBHAV is registered as P51800019010 and its status is "Completed".
Where is SHEETAL VAIBHAV?
SHEETAL VAIBHAV by D.G.S TOWNSHIP PRIVATE LIMITED is in Khar West, Mumbai (pincode 400052), Maharashtra, and is registered on MahaRERA as P51800019010, per GharKundli's check of MahaRERA records.
When is possession of SHEETAL VAIBHAV due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHEETAL VAIBHAV in Khar West, Mumbai is 31 December 2025 — 43 months later than 1 May 2022, the date given at registration.
Does SHEETAL VAIBHAV have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of SHEETAL VAIBHAV?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is D.G.S TOWNSHIP PRIVATE LIMITED, which has 1 other project registered on MahaRERA.
Other projects in pincode 400052
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.