SHEETAL SONA
by D.G.S TOWNSHIP PRIVATE LIMITED (Land) · Virar East, Palghar
Possession date of SHEETAL SONA: 31 May 2025, moved from 30 March 2023 (26 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000020654. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (May 2025) has passed.
What do you want to know about SHEETAL SONA?
How the possession date of SHEETAL SONA has moved
30 March 2023
Completion date given when the project was registered
1 March 2024
Extended at the builder's request (MahaRERA application EXT99000016681)
Reason the builder gave MahaRERA: “Due to Covid -19 Pandemic the constrction work was stopped for more than 10 months caused delaying in the project.”
31 May 2025
Extended at the builder's request (MahaRERA application EXT99000019590)
Reason the builder gave MahaRERA: “We have completed our project and we are under Process of getting Occupancy Certificate so we need extension till 31 st may 2025”
Source: SHEETAL SONA’s extension records on MahaRERA (P99000020654), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHEETAL SONA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the May 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000020654
- Status
- Lapsed (registration period ended)
- Builder
- D.G.S TOWNSHIP PRIVATE LIMITED
- Location
- Virar East, Palghar · 401305
- Project type
- Residential / Group Housing
- Registered on
- 30 Apr 2019
- Completion date at registration
- March 2023
- Latest completion date
- May 2025
- Delay so far
- 26 months
- Homes
- 193
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SHEETAL SONA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHEETAL SONA A AND B WING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHEETAL SONA every month.
SHEETAL SONA: buildings, flats and land, as filed on MahaRERA
- Buildings: SHEETAL SONA A AND B WING (21 floors)
- Land: 1,803 sq m (about 0.4 acres) · sanctioned built-up 1,803 sq m · recreational space 1,211 sq m
The builder’s record and reviews
D G Land Developers (a group of 8 linked companies) has 46 projects on MahaRERA since 2017, this one included. Of the 40 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 24 months); 25 still being built, 4 past the promised date (typically 28 months late); 10 lapsed. 42 complaints on MahaRERA across 17 projects.
Read Google reviews of SHEETAL SONA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHEETAL SONA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHEETAL SONA
What is the possession date of SHEETAL SONA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHEETAL SONA in Virar East, Palghar is 31 May 2025 — 26 months later than 30 March 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SHEETAL SONA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHEETAL SONA's builder has filed on MahaRERA, the official one, is 31 May 2025, already 26 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHEETAL SONA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA's builder applied to MahaRERA to extend the completion date 2 times: to 1 March 2024, giving the reason "Due to Covid -19 Pandemic the constrction work was stopped for more than 10 months caused delaying in the project."; to 31 May 2025, giving the reason "We have completed our project and we are under Process of getting Occupancy Certificate so we need extension till 31 st may 2025".
What is the RERA number of SHEETAL SONA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHEETAL SONA in Virar East, Palghar is P99000020654.
Is SHEETAL SONA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA is registered as P99000020654 and its status is "Lapsed (registration period ended)".
What is the construction status of SHEETAL SONA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHEETAL SONA A AND B WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHEETAL SONA have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SHEETAL SONA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA is registered on MahaRERA as P99000020654, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 26 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHEETAL SONA's possession date changes?
The latest dates are on SHEETAL SONA's MahaRERA page (P99000020654). GharKundli's Kundli Watch sends a free WhatsApp update on SHEETAL SONA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHEETAL SONA have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA has one building filed: SHEETAL SONA A AND B WING with 21 floors.
How big is the land of SHEETAL SONA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA stands on 1,803 sq m of land (about 0.4 acres), with 1,803 sq m of sanctioned built-up area and 1,211 sq m of recreational open space.
What is the track record of SHEETAL SONA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), D G Land Developers (a group of 8 linked companies) has 46 projects on MahaRERA since 2017, this one included. Of the 40 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 24 months); 25 still being built, 4 past the promised date (typically 28 months late); 10 lapsed. 42 complaints on MahaRERA across 17 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SHEETAL SONA?
Google Maps has reviews of SHEETAL SONA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHEETAL SONA?
SHEETAL SONA by D.G.S TOWNSHIP PRIVATE LIMITED (Land) is in Virar East, Palghar (pincode 401305), Maharashtra, and is registered on MahaRERA as P99000020654, per GharKundli's check of MahaRERA records.
How many homes are in SHEETAL SONA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA has 193 homes in 1 tower registered on MahaRERA.
When was SHEETAL SONA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHEETAL SONA was registered on MahaRERA on 30 April 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SHEETAL SONA?
No court cases are listed for SHEETAL SONA on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SHEETAL SONA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is D.G.S TOWNSHIP PRIVATE LIMITED, the company Land files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SHEETAL SONA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401305
- Swastik Epitome Building 2 Phase I Ground to 7 floors
- Swastik Epitome Building 2 Phase II 8 to 14 floors
- SIDDHIVINAYAK CROWN
- GIRDHARI HEIGHTS
- VIRAT CO-OP HOUSING SOCIETY
- NANA HEIGHTS
- SHREE SWAMI SAMARTH NX
- SHIVNERI
Other projects by D.G.S TOWNSHIP PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.