Pratap Oasis
by JPV Realtors Private Limited · Malad West, MumbaiAlso near Orlem, Valnai, Malad North
Possession date of Pratap Oasis: 31 December 2026, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800023003, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Pratap Oasis?
How the possession date of Pratap Oasis has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800017427)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51800025239)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 80% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. We…”31 December 2026
Extended at the builder's request (MahaRERA application EA08012619353)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we ar”
Source: Pratap Oasis’s extension records on MahaRERA (P51800023003), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pratap Oasis
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800023003
- Status
- Registered and active
- Builder
- JPV Realtors Private Limited
- Location
- Malad West, Mumbai · 400064
- Project type
- Residential / Group Housing
- Registered on
- 13 Nov 2019
- Completion date at registration
- December 2023
- Latest completion date
- December 2026
- Delay so far
- 36 months
- Homes
- 56
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of Pratap Oasis, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Pratap Oasis | 100% | 100% | 100% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- Pratap Oasis: covers 16 (G + 15)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pratap Oasis every month.
Pratap Oasis: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 399 – 438 | 30 |
| 2 BHK | 543 – 614 | 18 |
| Shops | 276 – 469 | 4 |
| 3 BHK | 761 – 827 | 3 |
| 4 BHK | 1,147 | 1 |
- Buildings: Pratap Oasis (17 floors, 56 units)
- Land: 981 sq m (about 0.2 acres) · sanctioned built-up 2,182 sq m
- Boundaries filed include: Municipal Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
JPV Realtors (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 7 still being built, 4 past the promised date (typically 8 months late). 4 complaints on MahaRERA across 3 projects.
Read Google reviews of Pratap Oasis →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pratap Oasis: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Pratap Oasis
What is the possession date of Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pratap Oasis in Malad West, Mumbai is 31 December 2026 — 36 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Pratap Oasis?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pratap Oasis's builder has filed on MahaRERA, the official one, is 31 December 2026, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pratap Oasis extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 80% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. We…"; to 31 December 2026, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we ar".
What is the RERA number of Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pratap Oasis in Malad West, Mumbai is P51800023003.
Is Pratap Oasis registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis is registered as P51800023003 and its status is "Registered and active".
What is the construction status of Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Pratap Oasis is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Pratap Oasis have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Pratap Oasis safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis is registered on MahaRERA as P51800023003, its completion date has moved 36 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Pratap Oasis's possession date changes?
The latest dates are on Pratap Oasis's MahaRERA page (P51800023003). GharKundli's Kundli Watch sends a free WhatsApp update on Pratap Oasis every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pratap Oasis have?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis has one building filed: Pratap Oasis with 17 floors and 56 units.
What are the flat sizes (carpet area) in Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Pratap Oasis: 1 BHK: 399 to 438 sq ft carpet (30 homes); 2 BHK: 543 to 614 sq ft carpet (18 homes); Shops: 276 to 469 sq ft carpet (4 homes); 3 BHK: 761 to 827 sq ft carpet (3 homes); 4 BHK: 1147 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis stands on 981 sq m of land (about 0.2 acres), with 2,182 sq m of sanctioned built-up area.
What is the track record of Pratap Oasis's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), JPV Realtors (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 7 still being built, 4 past the promised date (typically 8 months late). 4 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Pratap Oasis?
Google Maps has reviews of Pratap Oasis written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Pratap Oasis?
Pratap Oasis by JPV Realtors Private Limited is in Malad West, Mumbai (pincode 400064), near Orlem, Valnai, Malad North, Maharashtra, and is registered on MahaRERA as P51800023003, per GharKundli's check of MahaRERA records. Its boundaries filed there include Municipal Road.
How many homes are in Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis has 56 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Pratap Oasis registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Oasis was registered on MahaRERA on 13 November 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Pratap Oasis?
No court cases are listed for Pratap Oasis on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Pratap Oasis?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JPV Realtors Private Limited, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Pratap Oasis
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400064
- AABIEL AVENUE
- Lotus Sky Garden
- Bhagat Grandeur
- AVIRAHI ELEGANCE
- Rite Amor
- RASHMI ICON
- MARU MANSION
- Florence Residency
Other projects by JPV Realtors Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.