JPV Pratap Palace

by JPV Realtors Private Limited · Kandivali West, Mumbai 400067Also near BorivaliRegistered on MahaRERA as “Pratap Palace”

What’s in the report? →

Possession date of JPV Pratap Palace (MahaRERA P51800025101): 30 July 2029, moved from 30 March 2025 (48 months later). It has 77 homes (2 BHK, 3 BHK and 4 BHK, 452–2150 sq ft carpet), 95% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800025101, and currently active. Its completion date has moved from March 2025 to July 2029: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800025101, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about JPV Pratap Palace?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of JPV Pratap Palace has moved

  1. 30 March 2025

    Completion date given when the project was registered

  2. 30 March 2029

    Extended at the builder's request (MahaRERA application EXT51800025460)

    Reason the builder gave MahaRERA:
    “We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 84% of the project is completed. we kindly request an extension until 30-03-2029 to complete the project and fulfil all regulatory requirements.”
  3. 30 July 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: JPV Pratap Palace’s extension records on MahaRERA (P51800025101), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on JPV Pratap Palace

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800025101
Status
Registered and active
Builder
JPV Realtors Private Limited
Location
Kandivali West, Mumbai · 400067
Project type
Others
Registered on
18 Mar 2020
Completion date at registration
March 2025
Latest completion date
July 2029
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
77
Sold or booked
95%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of JPV Pratap Palace, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%0%0%0%
Wing B100%20%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A: covers 21 floors
  • Wing B: covers 21 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on JPV Pratap Palace every 1–2 months.

JPV Pratap Palace: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK842 – 1,23337
2 BHK452 – 74737
Shops439 – 5265
4 BHK1,306 – 2,1503
Other2,1961
  • Buildings: Wing A (21 floors, 43 units) · Wing B (21 floors, 40 units)
  • Land: 2,325 sq m (about 0.6 acres) · sanctioned built-up 2,309 sq m · recreational space 338 sq m
  • Boundaries filed include: Municipal Road
  • Land, as filed: CTS NO 15, CTS No 15/1 to 15/8
  • Map: Get directions

The builder’s record and reviews

JPV Realtors (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 7 still being built, 4 past the promised date (typically 8 months late). 4 complaints on MahaRERA across 3 projects.

Read Google reviews of JPV Pratap Palace →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

JPV Pratap Palace: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about JPV Pratap Palace

What is the possession date of JPV Pratap Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for JPV Pratap Palace in Kandivali West, Mumbai is 30 July 2029 — 48 months later than 30 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for JPV Pratap Palace?

Builders and listing sites often quote an earlier "target" date for handover. The completion date JPV Pratap Palace's builder has filed on MahaRERA, the official one, is 30 July 2029, already 48 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of JPV Pratap Palace extended?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace's builder applied to MahaRERA to extend the completion date once: to 30 March 2029, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 84% of the project is completed. we kindly request an extension until 30-03-2029 to complete the project and fulfil all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of JPV Pratap Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of JPV Pratap Palace in Kandivali West, Mumbai is P51800025101.

Is JPV Pratap Palace registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace is registered as P51800025101 and its status is "Registered and active".

What is the current construction status of JPV Pratap Palace? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 20% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does JPV Pratap Palace have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is JPV Pratap Palace safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace is registered on MahaRERA as P51800025101, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in JPV Pratap Palace?

JPV Pratap Palace is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in JPV Pratap Palace are 452 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in JPV Pratap Palace?

For a flat in JPV Pratap Palace (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has JPV Pratap Palace received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace is still under construction, with 30 July 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is JPV Pratap Palace a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace is a redevelopment: 40 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has JPV Pratap Palace uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for JPV Pratap Palace was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if JPV Pratap Palace's possession date changes?

The latest dates are on JPV Pratap Palace's MahaRERA page (P51800025101). GharKundli's Kundli Watch sends a free WhatsApp update on JPV Pratap Palace every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does JPV Pratap Palace have?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace has 2 buildings filed: Wing A with 21 floors and 43 units; Wing B with 21 floors and 40 units.

What are the flat sizes (carpet area) in JPV Pratap Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for JPV Pratap Palace: 3 BHK: 842 to 1233 sq ft carpet (37 homes); 2 BHK: 452 to 747 sq ft carpet (37 homes); 4 BHK: 1306 to 2150 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of JPV Pratap Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace stands on 2,325 sq m of land (about 0.6 acres), with 2,309 sq m of sanctioned built-up area and 338 sq m of recreational open space.

What is the track record of JPV Pratap Palace's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Realtors (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 7 still being built, 4 past the promised date (typically 8 months late). 4 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of JPV Pratap Palace?

Google Maps has reviews of JPV Pratap Palace written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of JPV Pratap Palace?

JPV Pratap Palace by JPV Realtors Private Limited is in Kandivali West, Mumbai, pincode 400067 (near Borivali), Maharashtra, and is registered on MahaRERA as P51800025101, per GharKundli's check of MahaRERA records. Its boundaries filed there include Municipal Road. Its land is filed as CTS NO 15, CTS No 15/1 to 15/8. GharKundli lists all 318 MahaRERA projects in Kandivali West (400067).

How many flats are in JPV Pratap Palace, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace has 77 homes in 2 towers registered on MahaRERA, and 95% of them are sold or booked.

When was JPV Pratap Palace registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), JPV Pratap Palace was registered on MahaRERA on 18 March 2020. GharKundli did not find a title report on the land on file there.

Does JPV Pratap Palace have any legal issues or court cases?

No court cases are listed for JPV Pratap Palace on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of JPV Pratap Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JPV Realtors Private Limited, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Kandivali West (400067)

All 318 projects in Kandivali West (400067) →

Other projects by JPV Realtors Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.