Navaghar Purvrang Coop HS
by NAVGHAR PURVARANG CHS LIMITED · Mulund East, Mumbai 400081Also near Mulund West
What’s in the report? →Possession date of Navaghar Purvrang Coop HS (MahaRERA P51800026043): 30 October 2026, moved from 30 June 2025 (12 months later), and it has already passed. It has 118 homes (1 BHK, 2 BHK and 3 BHK, 266–1017 sq ft carpet), 88% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800026043, and currently active. Its completion date has moved from June 2025 to October 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800026043, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Navaghar Purvrang Coop HS?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Navaghar Purvrang Coop HS has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA10102518075)
Reason the builder gave MahaRERA:
“We, Navghar Purvarang Co-op housing society ltd, are the promoters of the real estate project known as “Navghar Purvarang” bearing MahaRERA Registration No. P51800026043. We would like to respectfully bring to your attention that our projec…” Read the full reason
“We, Navghar Purvarang Co-op housing society ltd, are the promoters of the real estate project known as “Navghar Purvarang” bearing MahaRERA Registration No. P51800026043. We would like to respectfully bring to your attention that our project stands 100% completed; however, the Occupancy Certificate is pending with MHADA due to certain compliance requirements. Now the compliances has been complied and submitted for obtaining OC . We would like to assure the Authority that we remain fully committed to obtaining the Occupancy Certificate and to ensuring completion of the project strictly in li…”30 October 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Navaghar Purvrang Coop HS’s extension records on MahaRERA (P51800026043), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Navaghar Purvrang Coop HS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800026043
- Status
- Registered and active
- Builder
- NAVGHAR PURVARANG CHS LIMITED
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2020
- Completion date at registration
- June 2025
- Latest completion date
- October 2026
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 118
- Sold or booked
- 88%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Navaghar Purvrang Coop HS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 100% | 100% | 95% | 95% |
| WING B | 100% | 100% | 95% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers plinth level
- WING B: covers plinth level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Navaghar Purvrang Coop HS every 1–2 months.
Navaghar Purvrang Coop HS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 266 – 756 | 58 |
| 3 BHK | 1,016 – 1,017 | 40 |
| 1 BHK | 470 | 20 |
- Buildings: WING A (28 floors, 60 units) · WING B (28 floors, 58 units)
- Land: 1,502 sq m (about 0.4 acres)
- Boundaries filed include: LAYOUT ROAD
- Land, as filed: CTS NO 1287 P
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Navaghar Purvrang Coop HS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Navaghar Purvrang Coop HS: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Navaghar Purvrang Coop HS
What is the possession date of Navaghar Purvrang Coop HS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Navaghar Purvrang Coop HS in Mulund East, Mumbai is 30 October 2026 — 12 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Navaghar Purvrang Coop HS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Navaghar Purvrang Coop HS's builder has filed on MahaRERA, the official one, is 30 October 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Navaghar Purvrang Coop HS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "We, Navghar Purvarang Co-op housing society ltd, are the promoters of the real estate project known as “Navghar Purvarang” bearing MahaRERA Registration No. P51800026043. We would like to respectfully bring to your attention that our project stands 100% completed; however, the Occupancy Certificate is pending with MHADA due to certain compliance requirements. Now the compliances has been complied and submitted for obtaining OC . We would like to assure the Authority that we remain fully committed to obtaining the Occupancy Certificate and to ensuring completion of the project strictly in li…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Navaghar Purvrang Coop HS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Navaghar Purvrang Coop HS in Mulund East, Mumbai is P51800026043.
Is Navaghar Purvrang Coop HS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS is registered as P51800026043 and its status is "Registered and active".
What is the current construction status of Navaghar Purvrang Coop HS? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Navaghar Purvrang Coop HS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Navaghar Purvrang Coop HS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS is registered on MahaRERA as P51800026043, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Navaghar Purvrang Coop HS?
Navaghar Purvrang Coop HS is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Navaghar Purvrang Coop HS are 266 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Navaghar Purvrang Coop HS?
For a flat in Navaghar Purvrang Coop HS (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Navaghar Purvrang Coop HS received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Navaghar Purvrang Coop HS a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS is a redevelopment: 76 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Navaghar Purvrang Coop HS uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Navaghar Purvrang Coop HS was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Navaghar Purvrang Coop HS's possession date changes?
The latest dates are on Navaghar Purvrang Coop HS's MahaRERA page (P51800026043). GharKundli's Kundli Watch sends a free WhatsApp update on Navaghar Purvrang Coop HS every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Navaghar Purvrang Coop HS have?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS has 2 buildings filed: WING A with 28 floors and 60 units; WING B with 28 floors and 58 units.
What are the flat sizes (carpet area) in Navaghar Purvrang Coop HS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Navaghar Purvrang Coop HS: 2 BHK: 266 to 756 sq ft carpet (58 homes); 3 BHK: 1016 to 1017 sq ft carpet (40 homes); 1 BHK: 470 sq ft carpet (20 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Navaghar Purvrang Coop HS?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS stands on 1,502 sq m of land (about 0.4 acres).
What are the reviews of Navaghar Purvrang Coop HS?
Google Maps has reviews of Navaghar Purvrang Coop HS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Navaghar Purvrang Coop HS?
Navaghar Purvrang Coop HS by NAVGHAR PURVARANG CHS LIMITED is in Mulund East, Mumbai, pincode 400081 (near Mulund West), Maharashtra, and is registered on MahaRERA as P51800026043, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAYOUT ROAD. Its land is filed as CTS NO 1287 P. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).
How many flats are in Navaghar Purvrang Coop HS, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS has 118 homes in 2 towers registered on MahaRERA, and 88% of them are sold or booked.
When was Navaghar Purvrang Coop HS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Navaghar Purvrang Coop HS was registered on MahaRERA on 11 August 2020. GharKundli did not find a title report on the land on file there.
Does Navaghar Purvrang Coop HS have any legal issues or court cases?
No court cases are listed for Navaghar Purvrang Coop HS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Navaghar Purvrang Coop HS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAVGHAR PURVARANG CHS LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Navaghar Purvrang Coop HS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Mulund East (400081)
- Satre Elite
- Govind Prakash Sra CHS LTD
- Pearl
- Rbi Employees Shree Sahawas Co Op HSG Soc LTD
- New Usha Vihar Chsl
- Bimal Apartment CHSL
- Guru Ashish
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.