TRIENITY 1 PHASE II
by TRIENITY PRIME PROPERTY PROJECTS LLP · Borivali West, MumbaiAlso near Vile Parle East, Eksar Village, Kandivali
Possession date of TRIENITY 1 PHASE II: 31 July 2027, moved from 31 January 2025 (26 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800030871, and currently active. Its completion date has moved from January 2025 to July 2027: 26 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about TRIENITY 1 PHASE II?
How the possession date of TRIENITY 1 PHASE II has moved
31 January 2025
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EXT51800025456)
Reason the builder gave MahaRERA: “Due to shortage of material and labor we are not able to complete project please grant us extension till 31/03/2027”
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: TRIENITY 1 PHASE II’s extension records on MahaRERA (P51800030871), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TRIENITY 1 PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800030871
- Status
- Registered and active
- Builder
- TRIENITY PRIME PROPERTY PROJECTS LLP
- Location
- Borivali West, Mumbai · 400092
- Project type
- Commercial
- Registered on
- 20 Sep 2021
- Completion date at registration
- January 2025
- Latest completion date
- July 2027
- Delay so far
- 26 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of TRIENITY 1 PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TRIENITY 1 PHASE II | 100% | 90% | 65% | 35% |
Commencement certificate (CC), as filed on MahaRERA
- TRIENITY 1 PHASE II: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TRIENITY 1 PHASE II every month.
TRIENITY 1 PHASE II: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 474 – 1,381 | 40 |
- Buildings: TRIENITY 1 PHASE II (11 floors, 40 units)
- Land: 1,129 sq m (about 0.3 acres) · sanctioned built-up 2,604 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of TRIENITY 1 PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TRIENITY 1 PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TRIENITY 1 PHASE II
What is the possession date of TRIENITY 1 PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TRIENITY 1 PHASE II in Borivali West, Mumbai is 31 July 2027 — 26 months later than 31 January 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for TRIENITY 1 PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TRIENITY 1 PHASE II's builder has filed on MahaRERA, the official one, is 31 July 2027, already 26 months later than the 31 January 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TRIENITY 1 PHASE II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Due to shortage of material and labor we are not able to complete project please grant us extension till 31/03/2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of TRIENITY 1 PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TRIENITY 1 PHASE II in Borivali West, Mumbai is P51800030871.
Is TRIENITY 1 PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II is registered as P51800030871 and its status is "Registered and active".
What is the construction status of TRIENITY 1 PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TRIENITY 1 PHASE II is 90% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does TRIENITY 1 PHASE II have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is TRIENITY 1 PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II is registered on MahaRERA as P51800030871, its completion date has moved 26 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TRIENITY 1 PHASE II's possession date changes?
The latest dates are on TRIENITY 1 PHASE II's MahaRERA page (P51800030871). GharKundli's Kundli Watch sends a free WhatsApp update on TRIENITY 1 PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TRIENITY 1 PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II has one building filed: TRIENITY 1 PHASE II with 11 floors and 40 units.
How big is the land of TRIENITY 1 PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II stands on 1,129 sq m of land (about 0.3 acres), with 2,604 sq m of sanctioned built-up area.
Where can I read reviews of TRIENITY 1 PHASE II?
Google Maps has reviews of TRIENITY 1 PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TRIENITY 1 PHASE II?
TRIENITY 1 PHASE II by TRIENITY PRIME PROPERTY PROJECTS LLP is in Borivali West, Mumbai (pincode 400092), near Vile Parle East, Eksar Village, Kandivali, Maharashtra, and is registered on MahaRERA as P51800030871, per GharKundli's check of MahaRERA records.
How many homes are in TRIENITY 1 PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II has 0 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was TRIENITY 1 PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), TRIENITY 1 PHASE II was registered on MahaRERA on 20 September 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on TRIENITY 1 PHASE II?
1 court case is listed for TRIENITY 1 PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of TRIENITY 1 PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TRIENITY PRIME PROPERTY PROJECTS LLP.
Check it yourself on MahaRERA
- How to check the possession date of TRIENITY 1 PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400092
- FORTUNE AVIRAHI WING A
- SONI ARCADE, BUILDING NO 2
- Sparkle Umadarshan
- SHRADDHA SKYLINE
- I SPACE URBAN VISTA
- GAURAV GALAXY
- SKYLARK HEIGHTS
- Hiranandani Bluecrest
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.