Alpine Primo

by ALPINE INFRAHEIGHTS LLP · Andheri West, MumbaiAlso near Andheri Railway Station, Andheri East, Vesava

Possession date of Alpine Primo: 30 April 2027, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800030851. Status: In abeyance (on hold by MahaRERA). Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Alpine Primo?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Alpine Primo has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800023040)

    Reason the builder gave MahaRERA:
    “We understand the importance of adhering to project timelines as per MahaRERA regulations, and we assure you that our team is working diligently to mitigate these challenges. However, in the interest of transparency and to ensure the succes…” Read the full reason“We understand the importance of adhering to project timelines as per MahaRERA regulations, and we assure you that our team is working diligently to mitigate these challenges. However, in the interest of transparency and to ensure the successful completion of the project in accordance with the quality standards set by MahaRERA, we kindly request an extension of 12 months to the original project completion date.”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA26122519033)

    Reason the builder gave MahaRERA:
    “due to delay in sanctioned plans from concerned authority, therefore there was delay in completing the project, hence we request you to kindly grant us extension for further period of 12 months, so shall we complete and comply with MahaRERA…” Read the full reason“due to delay in sanctioned plans from concerned authority, therefore there was delay in completing the project, hence we request you to kindly grant us extension for further period of 12 months, so shall we complete and comply with MahaRERA norms.”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Alpine Primo’s extension records on MahaRERA (P51800030851), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Alpine Primo

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800030851
Status
In abeyance (on hold by MahaRERA)
Builder
ALPINE INFRAHEIGHTS LLP
Location
Andheri West, Mumbai · 400058
Project type
Others
Registered on
20 Sep 2021
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
145
Sold or booked
72%
Towers
3
Complaints on MahaRERA
5
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of Alpine Primo, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Alpine Primo -A Wing100%82%50%100%
Alpine Primo -B Wing100%82%50%100%
Alpine Primo - C Wing100%82%50%100%

Commencement certificate (CC), as filed on MahaRERA

  • Alpine Primo -A Wing: covers 14 upper floor
  • Alpine Primo -B Wing: covers 14 upper floors
  • Alpine Primo - C Wing: covers Top of 15th (part) upper Floor LMR+OHT

Latest CC order on MahaRERA: dated 17/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Alpine Primo every month.

Alpine Primo: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK565 – 79878
Shops45 – 73347
3 BHK425 – 1,08745
1 BHK422 – 59722
Office Space115 – 1,02622
Other380 – 7135
  • Buildings: Alpine Primo -A Wing (17 floors, 82 units) · Alpine Primo -B Wing (17 floors, 57 units) · Alpine Primo - C Wing (18 floors, 80 units)
  • Land: 3,625 sq m (about 0.9 acres) · sanctioned built-up 12,649 sq m · recreational space 683 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Alpine Primo →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Alpine Primo: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Alpine Primo

What is the possession date of Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Alpine Primo in Andheri West, Mumbai is 30 April 2027 — 24 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Alpine Primo?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Alpine Primo's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Alpine Primo extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "We understand the importance of adhering to project timelines as per MahaRERA regulations, and we assure you that our team is working diligently to mitigate these challenges. However, in the interest of transparency and to ensure the successful completion of the project in accordance with the quality standards set by MahaRERA, we kindly request an extension of 12 months to the original project completion date."; to 31 December 2026, giving the reason "due to delay in sanctioned plans from concerned authority, therefore there was delay in completing the project, hence we request you to kindly grant us extension for further period of 12 months, so shall we complete and comply with MahaRERA norms.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Alpine Primo in Andheri West, Mumbai is P51800030851.

Is Alpine Primo registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo is registered as P51800030851 and its status is "In abeyance (on hold by MahaRERA)". On MahaRERA's own list: Suspended, in abeyance or deregistered by MahaRERA order. MahaRERA has acted on this project by an order -- suspended, in abeyance or deregistered. Read the order to see which before paying anything.

What is the construction status of Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work is 82% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Alpine Primo have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Alpine Primo safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo is registered on MahaRERA as P51800030851, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has moved 24 months since registration, 5 complaints are listed against it and it is on MahaRERA's list "Suspended, in abeyance or deregistered by MahaRERA order". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Alpine Primo's possession date changes?

The latest dates are on Alpine Primo's MahaRERA page (P51800030851). GharKundli's Kundli Watch sends a free WhatsApp update on Alpine Primo every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Alpine Primo have?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo has 3 buildings filed: Alpine Primo -A Wing with 17 floors and 82 units; Alpine Primo -B Wing with 17 floors and 57 units; Alpine Primo - C Wing with 18 floors and 80 units.

What are the flat sizes (carpet area) in Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Alpine Primo: 2 BHK: 565 to 798 sq ft carpet (78 homes); 3 BHK: 425 to 1087 sq ft carpet (45 homes); 1 BHK: 422 to 597 sq ft carpet (22 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo stands on 3,625 sq m of land (about 0.9 acres), with 12,649 sq m of sanctioned built-up area and 683 sq m of recreational open space.

Where can I read reviews of Alpine Primo?

Google Maps has reviews of Alpine Primo written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Alpine Primo?

Alpine Primo by ALPINE INFRAHEIGHTS LLP is in Andheri West, Mumbai (pincode 400058), near Andheri Railway Station, Andheri East, Vesava, Maharashtra, and is registered on MahaRERA as P51800030851, per GharKundli's check of MahaRERA records.

How many homes are in Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo has 145 homes in 3 towers registered on MahaRERA, and 72% of them are sold or booked.

When was Alpine Primo registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Alpine Primo was registered on MahaRERA on 20 September 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on Alpine Primo?

No court cases are listed for Alpine Primo on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Alpine Primo?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALPINE INFRAHEIGHTS LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400058

All 148 projects in Andheri West (400058) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.