Sidhivinayak Flora
by SIDHIVINAYAK CONSTRUCTIONS · Chembur Naka, MumbaiAlso near Chembur east, Chembur West, Wadhavali
Possession date of Sidhivinayak Flora: 30 April 2027, moved from 19 August 2024 (28 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800033003, and currently active. Its completion date has moved from August 2024 to April 2027: 28 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Sidhivinayak Flora?
How the possession date of Sidhivinayak Flora has moved
19 August 2024
Completion date given when the project was registered
19 August 2025
Extended at the builder's request (MahaRERA application EXT51800024437)
Reason the builder gave MahaRERA: “We are making the application to extend the completion date of our project u/s 6 of Real Estate Act,2016”
31 December 2026
Extended at the builder's request (MahaRERA application EA24112518413)
Reason the builder gave MahaRERA:
“The main reason for extension is due to change in BMC scheme for construction of the upper floors above 10th Floor . The revised approval process is underway. After that, the Promoter will obtain all requisite NOCs required for the grant of…” Read the full reason
“The main reason for extension is due to change in BMC scheme for construction of the upper floors above 10th Floor . The revised approval process is underway. After that, the Promoter will obtain all requisite NOCs required for the grant of the final Occupation Certificate, which is expected well before 31/12/2026.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sidhivinayak Flora’s extension records on MahaRERA (P51800033003), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sidhivinayak Flora
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800033003
- Status
- Registered and active
- Builder
- SIDHIVINAYAK CONSTRUCTIONS
- Location
- Chembur Naka, Mumbai · 400071
- Project type
- Residential / Group Housing
- Registered on
- 3 Feb 2022
- Completion date at registration
- August 2024
- Latest completion date
- April 2027
- Delay so far
- 28 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Sidhivinayak Flora, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Flora Wing A | 100% | 95% | 98% | 97% |
| Flora Wing B | 100% | 95% | 98% | 97% |
Commencement certificate (CC), as filed on MahaRERA
- Flora Wing A: covers 11 floors
- Flora Wing B: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sidhivinayak Flora every month.
Sidhivinayak Flora: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 850 | 20 |
| 1 BHK | 268 – 402 | 19 |
| 2 BHK | 645 – 650 | 16 |
| 1 Room Kitchen | 268 | 1 |
- Buildings: Flora Wing A (12 floors, 28 units) · Flora Wing B (12 floors, 28 units)
- Land: 1,212 sq m (about 0.3 acres) · sanctioned built-up 3,599 sq m · recreational space 182 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sidhivinayak Constructions (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 6 finished, 1 within the promised date and 5 needed more time (typically 23 months); 3 still being built, 1 past the promised date (typically 22 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Sidhivinayak Flora →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sidhivinayak Flora: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sidhivinayak Flora
What is the possession date of Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sidhivinayak Flora in Chembur Naka, Mumbai is 30 April 2027 — 28 months later than 19 August 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sidhivinayak Flora?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sidhivinayak Flora's builder has filed on MahaRERA, the official one, is 30 April 2027, already 28 months later than the 19 August 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sidhivinayak Flora extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora's builder applied to MahaRERA to extend the completion date 2 times: to 19 August 2025, giving the reason "We are making the application to extend the completion date of our project u/s 6 of Real Estate Act,2016"; to 31 December 2026, giving the reason "The main reason for extension is due to change in BMC scheme for construction of the upper floors above 10th Floor . The revised approval process is underway. After that, the Promoter will obtain all requisite NOCs required for the grant of the final Occupation Certificate, which is expected well before 31/12/2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sidhivinayak Flora in Chembur Naka, Mumbai is P51800033003.
Is Sidhivinayak Flora registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora is registered as P51800033003 and its status is "Registered and active".
What is the construction status of Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 95% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Sidhivinayak Flora have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sidhivinayak Flora safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora is registered on MahaRERA as P51800033003, its completion date has moved 28 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sidhivinayak Flora's possession date changes?
The latest dates are on Sidhivinayak Flora's MahaRERA page (P51800033003). GharKundli's Kundli Watch sends a free WhatsApp update on Sidhivinayak Flora every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sidhivinayak Flora have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora has 2 buildings filed: Flora Wing A with 12 floors and 28 units; Flora Wing B with 12 floors and 28 units.
What are the flat sizes (carpet area) in Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sidhivinayak Flora: 3 BHK: 850 sq ft carpet (20 homes); 1 BHK: 268 to 402 sq ft carpet (19 homes); 2 BHK: 645 to 650 sq ft carpet (16 homes); 1 Room Kitchen: 268 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora stands on 1,212 sq m of land (about 0.3 acres), with 3,599 sq m of sanctioned built-up area and 182 sq m of recreational open space.
What is the track record of Sidhivinayak Flora's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Constructions (a group of 4 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 6 finished, 1 within the promised date and 5 needed more time (typically 23 months); 3 still being built, 1 past the promised date (typically 22 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Sidhivinayak Flora?
Google Maps has reviews of Sidhivinayak Flora written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sidhivinayak Flora?
Sidhivinayak Flora by SIDHIVINAYAK CONSTRUCTIONS is in Chembur Naka, Mumbai (pincode 400071), near Chembur east, Chembur West, Wadhavali, Maharashtra, and is registered on MahaRERA as P51800033003, per GharKundli's check of MahaRERA records.
How many homes are in Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora has 56 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Sidhivinayak Flora registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sidhivinayak Flora was registered on MahaRERA on 3 February 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Sidhivinayak Flora?
No court cases are listed for Sidhivinayak Flora on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Sidhivinayak Flora?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDHIVINAYAK CONSTRUCTIONS, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sidhivinayak Flora
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400071
- SHREE SARASWATI CHS LTD PLOT 8B
- TULSI CHAMBER PHASE II
- SAMPOORNA
- QUEENS PARK
- ARHAM MOURYA
- 71 Pardis
- ICONS 71
- Viera Golf Greens
Other projects by SIDHIVINAYAK CONSTRUCTIONS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.