Sanghvi Infenia
by Sanghvi Spaces LLP · Vidyanagari, MumbaiAlso near Kurla West, Sion
Possession date of Sanghvi Infenia: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800033811, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Sanghvi Infenia?
How the possession date of Sanghvi Infenia has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sanghvi Infenia’s extension records on MahaRERA (P51800033811), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sanghvi Infenia
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800033811
- Status
- Registered and active
- Builder
- Sanghvi Spaces LLP
- Location
- Vidyanagari, Mumbai · 400098
- Project type
- Residential / Group Housing
- Registered on
- 8 Mar 2022
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 46
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sanghvi Infenia, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sanghvi Infenia | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sanghvi Infenia every month.
Sanghvi Infenia: buildings, flats and land, as filed on MahaRERA
- Buildings: Sanghvi Infenia (15 floors)
- Land: 2,061 sq m (about 0.5 acres) · sanctioned built-up 4,900 sq m · recreational space 273 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sanghvi Infenia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sanghvi Infenia: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Sanghvi Infenia
What is the possession date of Sanghvi Infenia?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sanghvi Infenia in Vidyanagari, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sanghvi Infenia?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sanghvi Infenia's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sanghvi Infenia?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sanghvi Infenia in Vidyanagari, Mumbai is P51800033811.
Is Sanghvi Infenia registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia is registered as P51800033811 and its status is "Registered and active".
What is the construction status of Sanghvi Infenia?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sanghvi Infenia is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Sanghvi Infenia have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Sanghvi Infenia safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia is registered on MahaRERA as P51800033811, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Sanghvi Infenia's possession date changes?
The latest dates are on Sanghvi Infenia's MahaRERA page (P51800033811). GharKundli's Kundli Watch sends a free WhatsApp update on Sanghvi Infenia every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sanghvi Infenia have?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia has one building filed: Sanghvi Infenia with 15 floors.
How big is the land of Sanghvi Infenia?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia stands on 2,061 sq m of land (about 0.5 acres), with 4,900 sq m of sanctioned built-up area and 273 sq m of recreational open space.
Where can I read reviews of Sanghvi Infenia?
Google Maps has reviews of Sanghvi Infenia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Sanghvi Infenia?
Sanghvi Infenia by Sanghvi Spaces LLP is in Vidyanagari, Mumbai (pincode 400098), near Kurla West, Sion, Maharashtra, and is registered on MahaRERA as P51800033811, per GharKundli's check of MahaRERA records.
How many homes are in Sanghvi Infenia?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia has 46 homes in 1 tower registered on MahaRERA.
When was Sanghvi Infenia registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Sanghvi Infenia was registered on MahaRERA on 8 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Sanghvi Infenia?
No court cases are listed for Sanghvi Infenia on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Sanghvi Infenia?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanghvi Spaces LLP.
Check it yourself on MahaRERA
- How to check the possession date of Sanghvi Infenia
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400098
All 30 projects in Santacruz East (400098) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.