PIER 23
by HOOR CONSTRUCTIONS · Mazgaon, MumbaiAlso near Dongri, Chinchbunder, Tank Road
Possession date of PIER 23: 30 April 2031, moved from 30 June 2024 (78 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900009360, and currently active. Its completion date has moved from June 2024 to April 2031: 78 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about PIER 23?
How the possession date of PIER 23 has moved
30 June 2024
Completion date given when the project was registered
31 December 2030
Extended at the builder's request (MahaRERA application EA20072621803)
Reason the builder gave MahaRERA:
“"Due to delays in obtaining the necessary approvals from the concerned Government authorities, arising from regulatory restrictions beyond our control, the project could not be completed within the stipulated timeline. We are therefore seek…” Read the full reason
“"Due to delays in obtaining the necessary approvals from the concerned Government authorities, arising from regulatory restrictions beyond our control, the project could not be completed within the stipulated timeline. We are therefore seeking an extension of the project registration period to enable us to complete the remaining work and obtain the Occupancy Certificate (OC) in compliance with all applicable regulations."”30 April 2031
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: PIER 23’s extension records on MahaRERA (P51900009360), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PIER 23
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2031 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900009360
- Status
- Registered and active
- Builder
- HOOR CONSTRUCTIONS
- Location
- Mazgaon, Mumbai · 400010
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- June 2024
- Latest completion date
- April 2031
- Delay so far
- 78 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of PIER 23, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 0% | 0% | 0% | 0% |
| WING B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers 0 floors
- WING B: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PIER 23 every month.
PIER 23: buildings, flats and land, as filed on MahaRERA
- Buildings: WING A (17 floors) · WING B (23 floors)
- Land: 2,253 sq m (about 0.6 acres) · sanctioned built-up 4,791 sq m · recreational space 231 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Castle Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 12 months late); 1 lapsed. 3 complaints on MahaRERA across 2 projects.
Read Google reviews of PIER 23 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PIER 23: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PIER 23
What is the possession date of PIER 23?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PIER 23 in Mazgaon, Mumbai is 30 April 2031 — 78 months later than 30 June 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for PIER 23?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PIER 23's builder has filed on MahaRERA, the official one, is 30 April 2031, already 78 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PIER 23 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason ""Due to delays in obtaining the necessary approvals from the concerned Government authorities, arising from regulatory restrictions beyond our control, the project could not be completed within the stipulated timeline. We are therefore seeking an extension of the project registration period to enable us to complete the remaining work and obtain the Occupancy Certificate (OC) in compliance with all applicable regulations."". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of PIER 23?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PIER 23 in Mazgaon, Mumbai is P51900009360.
Is PIER 23 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23 is registered as P51900009360 and its status is "Registered and active".
What is the construction status of PIER 23?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does PIER 23 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PIER 23 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23 is registered on MahaRERA as P51900009360, its completion date has moved 78 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PIER 23's possession date changes?
The latest dates are on PIER 23's MahaRERA page (P51900009360). GharKundli's Kundli Watch sends a free WhatsApp update on PIER 23 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PIER 23 have?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23 has 2 buildings filed: WING A with 17 floors; WING B with 23 floors.
How big is the land of PIER 23?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23 stands on 2,253 sq m of land (about 0.6 acres), with 4,791 sq m of sanctioned built-up area and 231 sq m of recreational open space.
What is the track record of PIER 23's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Castle Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 12 months late); 1 lapsed. 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PIER 23?
Google Maps has reviews of PIER 23 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PIER 23?
PIER 23 by HOOR CONSTRUCTIONS is in Mazgaon, Mumbai (pincode 400010), near Dongri, Chinchbunder, Tank Road, Maharashtra, and is registered on MahaRERA as P51900009360, per GharKundli's check of MahaRERA records.
When was PIER 23 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), PIER 23 was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PIER 23?
1 court case is listed for PIER 23 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of PIER 23?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HOOR CONSTRUCTIONS.
Check it yourself on MahaRERA
- How to check the possession date of PIER 23
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2031 in Mumbai Suburban →
Other projects in pincode 400010
- A. M. Residency
- One India Tower
- TARABAUG
- The Aga Hall Estate
- HUSSAINI PARK
- Aqeeq Tower
- 52 Avenue
- Presidence Eternia
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.