SUPERBIA
by K V DEVCON LIMITED LIABILITY PARTNERSHIP · Mulund East, MumbaiAlso near Mulund West, Vile Parle East, Kopri
Possession date of SUPERBIA: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800047715, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SUPERBIA?
How the possession date of SUPERBIA has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SUPERBIA’s extension records on MahaRERA (P51800047715), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SUPERBIA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800047715
- Status
- Registered and active
- Builder
- K V DEVCON LIMITED LIABILITY PARTNERSHIP
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 21 Nov 2022
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 38
- Sold or booked
- 5%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of SUPERBIA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SUPERBIA | 10% | 19.53% | 33% | 33% |
Commencement certificate (CC), as filed on MahaRERA
- SUPERBIA: covers Full C.C. is granted Wing–A: Stilt floors only; Wing–B: Stilt + 9 upper floors and Wing–C: Stilt + 10 upper floors
Latest CC order on MahaRERA: dated 12/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUPERBIA every month.
SUPERBIA: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 716 – 726 | 38 |
- Buildings: SUPERBIA (11 floors, 38 units)
- Car parking: 66 covered, 31 open
- Land: 3,200 sq m (about 0.8 acres) · sanctioned built-up 3,128 sq m · recreational space 480 sq m
- Boundaries filed include: SANSKAR SOCIETY, VEER SAVARKAR ROAD, NEELAM NAGAR PHASE II, PRATAPRAO GUJAR ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Neelam Finance Bombay (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 30 months late). 13 complaints on MahaRERA across 5 projects.
Read Google reviews of SUPERBIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SUPERBIA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SUPERBIA
What is the possession date of SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUPERBIA in Mulund East, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SUPERBIA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SUPERBIA's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SUPERBIA in Mulund East, Mumbai is P51800047715.
Is SUPERBIA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA is registered as P51800047715 and its status is "Registered and active".
What is the construction status of SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SUPERBIA is 19.53% done and internal work 33%. GharKundli's full report compares construction progress with the deadline.
Does SUPERBIA have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SUPERBIA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA is registered on MahaRERA as P51800047715, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SUPERBIA's possession date changes?
The latest dates are on SUPERBIA's MahaRERA page (P51800047715). GharKundli's Kundli Watch sends a free WhatsApp update on SUPERBIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SUPERBIA have?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA has one building filed: SUPERBIA with 11 floors and 38 units.
What are the flat sizes (carpet area) in SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SUPERBIA: 2 BHK: 716 to 726 sq ft carpet (38 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SUPERBIA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 66 covered and 31 open car parking spaces for SUPERBIA.
How big is the land of SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA stands on 3,200 sq m of land (about 0.8 acres), with 3,128 sq m of sanctioned built-up area and 480 sq m of recreational open space.
What is the track record of SUPERBIA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelam Finance Bombay (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 30 months late). 13 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SUPERBIA?
Google Maps has reviews of SUPERBIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SUPERBIA?
SUPERBIA by K V DEVCON LIMITED LIABILITY PARTNERSHIP is in Mulund East, Mumbai (pincode 400081), near Mulund West, Vile Parle East, Kopri, Maharashtra, and is registered on MahaRERA as P51800047715, per GharKundli's check of MahaRERA records. Its boundaries filed there include SANSKAR SOCIETY, VEER SAVARKAR ROAD, NEELAM NAGAR PHASE II, PRATAPRAO GUJAR ROAD.
How many homes are in SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA has 38 homes in 1 tower registered on MahaRERA, and 5% of them are sold or booked.
When was SUPERBIA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUPERBIA was registered on MahaRERA on 21 November 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on SUPERBIA?
1 court case is listed for SUPERBIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SUPERBIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K V DEVCON LIMITED LIABILITY PARTNERSHIP.
Check it yourself on MahaRERA
- How to check the possession date of SUPERBIA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400081
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- RBI EMPLOYEES SHREE SAHAWAS CO OP HSG SOC LTD
- GOVIND PRAKASH SRA CHS LTD
- BIMAL APARTMENT CHSL
- GURU ASHISH
- SATRE ELITE
- PEARL
- New Usha Vihar Chsl
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.