Aryavarta Indraprastha CHSL
by Aryavarta Indraprastha Co operative Housing Society Limited · Mulund East, Mumbai 400081Also near Mulund West
What’s in the report? →Possession: Aryavarta Indraprastha CHSL (MahaRERA P51800047416) is marked completed on MahaRERA. It has 37 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800047416. Status: Completed.
Source: MahaRERA website — records for P51800047416, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Aryavarta Indraprastha CHSL?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Aryavarta Indraprastha CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the November 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800047416
- Status
- Completed
- Builder
- Aryavarta Indraprastha Co operative Housing Society Limited
- Location
- Mulund East, Mumbai · 400081
- Project type
- Residential / Group Housing
- Registered on
- 27 Oct 2022
- Completion date at registration
- November 2025
- Homes
- 37
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Aryavarta Indraprastha CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Aryavarta Indraprastha CHSL | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aryavarta Indraprastha CHSL every 1–2 months.
Aryavarta Indraprastha CHSL: buildings, flats and land, as filed on MahaRERA
- Buildings: Aryavarta Indraprastha CHSL (14 floors)
- Land: 812 sq m (about 0.2 acres) · sanctioned built-up 2,193 sq m
- Boundaries filed include: Layout Road
- Land, as filed: 1071/1 ,1071/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Aryavarta Indraprastha CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Aryavarta Indraprastha CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Aryavarta Indraprastha CHSL
What is the possession date of Aryavarta Indraprastha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aryavarta Indraprastha CHSL in Mulund East, Mumbai is 25 November 2025.
Is the builder's possession date different from the MahaRERA date for Aryavarta Indraprastha CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Aryavarta Indraprastha CHSL's builder has filed on MahaRERA, the official one, is 25 November 2025, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Aryavarta Indraprastha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aryavarta Indraprastha CHSL in Mulund East, Mumbai is P51800047416.
Is Aryavarta Indraprastha CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL is registered as P51800047416 and its status is "Completed".
What is the current construction status of Aryavarta Indraprastha CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL's status on MahaRERA is "Completed". As filed by the builder, slab work on Aryavarta Indraprastha CHSL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Aryavarta Indraprastha CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Aryavarta Indraprastha CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL is registered on MahaRERA as P51800047416, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Aryavarta Indraprastha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Aryavarta Indraprastha CHSL?
For a flat in Aryavarta Indraprastha CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Aryavarta Indraprastha CHSL received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Aryavarta Indraprastha CHSL completed?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL is marked completed on MahaRERA, and the completion date filed there is 25 November 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Is Aryavarta Indraprastha CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Aryavarta Indraprastha CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aryavarta Indraprastha CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Aryavarta Indraprastha CHSL's possession date changes?
The latest dates are on Aryavarta Indraprastha CHSL's MahaRERA page (P51800047416). GharKundli's Kundli Watch sends a free WhatsApp update on Aryavarta Indraprastha CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Aryavarta Indraprastha CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL has one building filed: Aryavarta Indraprastha CHSL with 14 floors.
How big is the land of Aryavarta Indraprastha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL stands on 812 sq m of land (about 0.2 acres), with 2,193 sq m of sanctioned built-up area.
What are the reviews of Aryavarta Indraprastha CHSL?
Google Maps has reviews of Aryavarta Indraprastha CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Aryavarta Indraprastha CHSL?
Aryavarta Indraprastha CHSL by Aryavarta Indraprastha Co operative Housing Society Limited is in Mulund East, Mumbai, pincode 400081 (near Mulund West), Maharashtra, and is registered on MahaRERA as P51800047416, per GharKundli's check of MahaRERA records. Its boundaries filed there include Layout Road. Its land is filed as 1071/1 ,1071/2. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).
How many flats are in Aryavarta Indraprastha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL has 37 homes in 1 tower registered on MahaRERA.
When was Aryavarta Indraprastha CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Aryavarta Indraprastha CHSL was registered on MahaRERA on 27 October 2022. GharKundli did not find a title report on the land on file there.
Does Aryavarta Indraprastha CHSL have any legal issues or court cases?
1 court case is listed for Aryavarta Indraprastha CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Aryavarta Indraprastha CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aryavarta Indraprastha Co operative Housing Society Limited.
Check it yourself on MahaRERA
- How to check the possession date of Aryavarta Indraprastha CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund East (400081)
- Kam Ganesh Co-operative Housing Society Ltd and Nav Amardeep Co-operative Housing Society Limited
- Satre Elite
- Govind Prakash Sra CHS LTD
- Pearl
- Rbi Employees Shree Sahawas Co Op HSG Soc LTD
- New Usha Vihar Chsl
- Bimal Apartment CHSL
- Guru Ashish
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.