Possession: Borivali Yashodhan CHSL (MahaRERA P51800048607) is marked completed on MahaRERA. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800048607. Status: Completed.

Source: MahaRERA website — records for P51800048607, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Borivali Yashodhan CHSL?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Borivali Yashodhan CHSL has moved

  1. 30 June 2024

    Completion date given when the project was registered

  2. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024488)

    Reason the builder gave MahaRERA: “Due to the site situation and a delay in the parking tower, we would like to request an extension for another year to complete the project and obtain a full occupancy certificate.”

Source: Borivali Yashodhan CHSL’s extension records on MahaRERA (P51800048607), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Borivali Yashodhan CHSL

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800048607
Status
Completed
Builder
TGN REALTOR LLP
Location
Borivali West, Mumbai · 400092
Project type
Commercial
Registered on
10 Jan 2023
Completion date at registration
June 2024
Latest completion date
June 2025
Delay so far
12 months
Homes
0
Sold or booked
58%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Borivali Yashodhan CHSL, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BORIVALI YASHODHAN CHSL100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BORIVALI YASHODHAN CHSL: covers FULL CC

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Borivali Yashodhan CHSL every 1–2 months.

Borivali Yashodhan CHSL: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space158 – 1,70427
Shops165 – 4615

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Borivali Yashodhan CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Borivali Yashodhan CHSL: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Borivali Yashodhan CHSL

What is the possession date of Borivali Yashodhan CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Borivali Yashodhan CHSL in Borivali West, Mumbai is 30 June 2025 — 12 months later than 30 June 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Borivali Yashodhan CHSL?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Borivali Yashodhan CHSL's builder has filed on MahaRERA, the official one, is 30 June 2025, already 12 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Borivali Yashodhan CHSL extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL's builder applied to MahaRERA to extend the completion date once: to 30 June 2025, giving the reason "Due to the site situation and a delay in the parking tower, we would like to request an extension for another year to complete the project and obtain a full occupancy certificate.".

What is the RERA number of Borivali Yashodhan CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Borivali Yashodhan CHSL in Borivali West, Mumbai is P51800048607.

Is Borivali Yashodhan CHSL registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL is registered as P51800048607 and its status is "Completed".

What is the current construction status of Borivali Yashodhan CHSL? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL's status on MahaRERA is "Completed". As filed by the builder, slab work on BORIVALI YASHODHAN CHSL is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Borivali Yashodhan CHSL have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Borivali Yashodhan CHSL safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL is registered on MahaRERA as P51800048607, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Borivali Yashodhan CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Borivali Yashodhan CHSL?

For a flat in Borivali Yashodhan CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Borivali Yashodhan CHSL received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Borivali Yashodhan CHSL completed?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL is marked completed on MahaRERA, and the completion date filed there is 30 June 2025. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Is Borivali Yashodhan CHSL a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Borivali Yashodhan CHSL uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Borivali Yashodhan CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Borivali Yashodhan CHSL's possession date changes?

The latest dates are on Borivali Yashodhan CHSL's MahaRERA page (P51800048607). GharKundli's Kundli Watch sends a free WhatsApp update on Borivali Yashodhan CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Borivali Yashodhan CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL has one building filed: BORIVALI YASHODHAN CHSL with 12 floors and 32 units.

How much parking does Borivali Yashodhan CHSL have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 44 covered car parking spaces for Borivali Yashodhan CHSL.

How big is the land of Borivali Yashodhan CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL stands on 458 sq m of land (about 0.1 acres), with 1,819 sq m of sanctioned built-up area.

What are the reviews of Borivali Yashodhan CHSL?

Google Maps has reviews of Borivali Yashodhan CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Borivali Yashodhan CHSL?

Borivali Yashodhan CHSL by TGN REALTOR LLP is in Borivali West, Mumbai, pincode 400092 (near Borivali East, Eksar, Daulat Nagar), Maharashtra, and is registered on MahaRERA as P51800048607, per GharKundli's check of MahaRERA records. Its boundaries filed there include ROSHAN NAGAR ROAD, CHANDAVARKAR ROAD. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).

How many flats are in Borivali Yashodhan CHSL, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL has 0 homes in 1 tower registered on MahaRERA, and 58% of them are sold or booked.

When was Borivali Yashodhan CHSL registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Borivali Yashodhan CHSL was registered on MahaRERA on 10 January 2023. GharKundli did not find a title report on the land on file there.

Does Borivali Yashodhan CHSL have any legal issues or court cases?

No court cases are listed for Borivali Yashodhan CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Borivali Yashodhan CHSL?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TGN REALTOR LLP.

Other projects in Borivali West (400092)

All 362 projects in Borivali West (400092) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.