by NITAI GAUR ENTERPRISES (Chaitanya) · Borivali West, Mumbai 400092Also near Borivali East, Mandapeshwar
What’s in the report? →Possession date of Ganapati Baug CHSL (MahaRERA P51800055078): 31 May 2028. It has 70 homes (1 BHK, 2 BHK and 3 BHK, 413–3862 sq ft carpet), 51% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800055078, and currently active. Its completion date is now May 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800055078, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ganapati Baug CHSL?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ganapati Baug CHSL has moved
31 January 2028
Completion date given when the project was registered
31 May 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ganapati Baug CHSL’s extension records on MahaRERA (P51800055078), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ganapati Baug CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800055078
- Status
- Registered and active
- Builder
- NITAI GAUR ENTERPRISES
- Location
- Borivali West, Mumbai · 400092
- Project type
- Others
- Registered on
- 29 Feb 2024
- Completion date at registration
- January 2028
- Latest completion date
- May 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 70
- Sold or booked
- 51%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Ganapati Baug CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GANAPATI BAUG CHSL / wing A | 100% | 27% | 0% | 0% |
| GANAPATI BAUG CHSL / wing B | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GANAPATI BAUG CHSL: covers Wing ‘A’ comprising of Gr. (for comm.)+1st (pt.) (for comm.) + 1st (pt.) podium (for parking) + 2nd to 6th podium (for parking) + 1st to 13th upper residential
- GANAPATI BAUG CHSL: covers Wing ‘B’ comprising of. Gr. (for comm.), 1st (pt.) (for comm.) + 1st (pt.) podium (for parking) + Service Floor + 2nd to 6th podium (for parking) + 1st to 11th
Latest CC order on MahaRERA: dated 27/02/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ganapati Baug CHSL every 1–2 months.
Ganapati Baug CHSL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 676 – 805 | 46 |
| Shops | 132 – 1,688 | 32 |
| 3 BHK | 1,036 – 1,231 | 20 |
| 1 BHK | 413 | 2 |
| 4 BHK | 1,787 | 1 |
| 6 BHK | 3,862 | 1 |
- Buildings: GANAPATI BAUG CHSL (21 floors, 88 units) · GANAPATI BAUG CHSL (20 floors, 14 units)
- Land: 2,339 sq m (about 0.6 acres) · sanctioned built-up 7,579 sq m
- Boundaries filed include: LOKMANYA TILAK ROAD
- Land, as filed: 215 ,216
- Map: Get directions
The builder’s record and reviews
Ethics Infra Development (a group of 10 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 13 finished, 5 within the promised date and 8 needed more time (typically 10 months); 5 still being built, 1 past the promised date (typically 39 months late). 3 complaints on MahaRERA across 2 projects.
Read Google reviews of Ganapati Baug CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ganapati Baug CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ganapati Baug CHSL
What is the possession date of Ganapati Baug CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ganapati Baug CHSL in Borivali West, Mumbai is 31 May 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Ganapati Baug CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ganapati Baug CHSL's builder has filed on MahaRERA, the official one, is 31 May 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Ganapati Baug CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ganapati Baug CHSL in Borivali West, Mumbai is P51800055078.
Is Ganapati Baug CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL is registered as P51800055078 and its status is "Registered and active".
What is the current construction status of Ganapati Baug CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 27% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Ganapati Baug CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ganapati Baug CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL is registered on MahaRERA as P51800055078, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ganapati Baug CHSL?
Ganapati Baug CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ganapati Baug CHSL are 413 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ganapati Baug CHSL?
For a flat in Ganapati Baug CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ganapati Baug CHSL received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL is still under construction, with 31 May 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Ganapati Baug CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL is a redevelopment: 63 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Ganapati Baug CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ganapati Baug CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ganapati Baug CHSL's possession date changes?
The latest dates are on Ganapati Baug CHSL's MahaRERA page (P51800055078). GharKundli's Kundli Watch sends a free WhatsApp update on Ganapati Baug CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ganapati Baug CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL has 2 buildings filed: GANAPATI BAUG CHSL with 21 floors and 88 units; GANAPATI BAUG CHSL with 20 floors and 14 units.
What are the flat sizes (carpet area) in Ganapati Baug CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ganapati Baug CHSL: 2 BHK: 676 to 805 sq ft carpet (46 homes); 3 BHK: 1036 to 1231 sq ft carpet (20 homes); 1 BHK: 413 sq ft carpet (2 homes); 4 BHK: 1787 sq ft carpet (1 homes); 6 BHK: 3862 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Ganapati Baug CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL stands on 2,339 sq m of land (about 0.6 acres), with 7,579 sq m of sanctioned built-up area.
What is the track record of Ganapati Baug CHSL's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ethics Infra Development (a group of 10 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 13 finished, 5 within the promised date and 8 needed more time (typically 10 months); 5 still being built, 1 past the promised date (typically 39 months late). 3 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ganapati Baug CHSL?
Google Maps has reviews of Ganapati Baug CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ganapati Baug CHSL?
Ganapati Baug CHSL by NITAI GAUR ENTERPRISES (Chaitanya) is in Borivali West, Mumbai, pincode 400092 (near Borivali East, Mandapeshwar), Maharashtra, and is registered on MahaRERA as P51800055078, per GharKundli's check of MahaRERA records. Its boundaries filed there include LOKMANYA TILAK ROAD. Its land is filed as 215 ,216. GharKundli lists all 362 MahaRERA projects in Borivali West (400092).
How many flats are in Ganapati Baug CHSL, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL has 70 homes in 2 towers registered on MahaRERA, and 51% of them are sold or booked.
When was Ganapati Baug CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ganapati Baug CHSL was registered on MahaRERA on 29 February 2024. GharKundli did not find a title report on the land on file there.
Does Ganapati Baug CHSL have any legal issues or court cases?
No court cases are listed for Ganapati Baug CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ganapati Baug CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NITAI GAUR ENTERPRISES, the company Chaitanya files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Ganapati Baug CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Borivali West (400092)
- Skylark Heights
- Gaurav Galaxy
- Soni Arcade, Building No 2
- Fortune Avirahi Wing A
- Shraddha Skyline
- Sparkle Umadarshan
- I Space Urban Vista
- Hiranandani Bluecrest
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.