Mayfair Breeze

by MAYFAIR HOUSING PRIVATE LIMITED · Andheri, Mumbai 400058Also near Jogeshwari East, Ambivali West, Mogra

What’s in the report? →

Possession: Mayfair Breeze (MahaRERA P51800054512) is marked completed on MahaRERA. It has 108 homes (2 BHK and 3 BHK, 555–914 sq ft carpet), 62% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800054512. Status: Completed.

Source: MahaRERA website — records for P51800054512, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Mayfair Breeze?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Mayfair Breeze

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800054512
Status
Completed
Builder
MAYFAIR HOUSING PRIVATE LIMITED
Location
Andheri, Mumbai · 400058
Project type
Residential / Group Housing
Registered on
25 Jan 2024
Completion date at registration
November 2027
Homes
108
Sold or booked
62%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Mayfair Breeze, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%100%
WING B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 15 floors
  • WING B: covers 15 floors

Latest CC order on MahaRERA: dated 29/01/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mayfair Breeze every 1–2 months.

Mayfair Breeze: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK702 – 91480
2 BHK555 – 86528
Shops6491
  • Buildings: WING A (15 floors, 56 units) · WING B (15 floors, 53 units)
  • Car parking: 128 covered
  • Land: 2,539 sq m (about 0.6 acres) · sanctioned built-up 8,509 sq m · recreational space 543 sq m
  • Boundaries filed include: DAWOOD BAUG ROAD
  • Land, as filed: 63 ,59
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Mayfair Housing (a group of 4 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 6 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 30 months late). 14 complaints on MahaRERA across 4 projects.

Read Google reviews of Mayfair Breeze →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mayfair Breeze: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Mayfair Breeze

What is the possession date of Mayfair Breeze?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mayfair Breeze in Andheri, Mumbai is 30 November 2027.

Is the builder's possession date different from the MahaRERA date for Mayfair Breeze?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mayfair Breeze's builder has filed on MahaRERA, the official one, is 30 November 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Mayfair Breeze?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mayfair Breeze in Andheri, Mumbai is P51800054512.

Is Mayfair Breeze registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze is registered as P51800054512 and its status is "Completed".

What is the current construction status of Mayfair Breeze? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Mayfair Breeze have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Mayfair Breeze safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze is registered on MahaRERA as P51800054512, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Mayfair Breeze?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Mayfair Breeze?

For a flat in Mayfair Breeze (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Mayfair Breeze received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Mayfair Breeze completed?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze is marked completed on MahaRERA, and the completion date filed there is 30 November 2027. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Is Mayfair Breeze a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Mayfair Breeze uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mayfair Breeze was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Mayfair Breeze's possession date changes?

The latest dates are on Mayfair Breeze's MahaRERA page (P51800054512). GharKundli's Kundli Watch sends a free WhatsApp update on Mayfair Breeze every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mayfair Breeze have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze has 2 buildings filed: WING A with 15 floors and 56 units; WING B with 15 floors and 53 units.

What are the flat sizes (carpet area) in Mayfair Breeze?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Mayfair Breeze: 3 BHK: 702 to 914 sq ft carpet (80 homes); 2 BHK: 555 to 865 sq ft carpet (28 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Mayfair Breeze have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 128 covered car parking spaces for Mayfair Breeze.

How big is the land of Mayfair Breeze?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze stands on 2,539 sq m of land (about 0.6 acres), with 8,509 sq m of sanctioned built-up area and 543 sq m of recreational open space.

What is the track record of Mayfair Breeze's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Housing (a group of 4 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 6 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 30 months late). 14 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Mayfair Breeze?

Google Maps has reviews of Mayfair Breeze written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Mayfair Breeze?

Mayfair Breeze by MAYFAIR HOUSING PRIVATE LIMITED is in Andheri, Mumbai, pincode 400058 (near Jogeshwari East, Ambivali West, Mogra), Maharashtra, and is registered on MahaRERA as P51800054512, per GharKundli's check of MahaRERA records. Its boundaries filed there include DAWOOD BAUG ROAD. Its land is filed as 63 ,59. GharKundli lists all 148 MahaRERA projects in Andheri West (400058).

How many flats are in Mayfair Breeze, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze has 108 homes in 2 towers registered on MahaRERA, and 62% of them are sold or booked.

When was Mayfair Breeze registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Breeze was registered on MahaRERA on 25 January 2024. GharKundli did not find a title report on the land on file there.

Does Mayfair Breeze have any legal issues or court cases?

No court cases are listed for Mayfair Breeze on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Mayfair Breeze?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MAYFAIR HOUSING PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

Other projects in Andheri West (400058)

All 148 projects in Andheri West (400058) →

Other projects by MAYFAIR HOUSING PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.