Possession date of Shraddha Palm (MahaRERA P51800055034): 31 March 2027, moved from 31 March 2026 (12 months later). It has 45 homes (1 BHK, 2 BHK and 3 BHK, 389–1554 sq ft carpet), 21% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800055034, and currently active.

Source: MahaRERA website — records for P51800055034, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Shraddha Palm?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Shraddha Palm has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA30032620445)

    Reason the builder gave MahaRERA:
    “The completion of the project was adversely affected due to unforeseen circumstances including delays in procurement of materials, financial constraints, and site-related challenges, which collectively impacted the construction schedule. Fu…” Read the full reason“The completion of the project was adversely affected due to unforeseen circumstances including delays in procurement of materials, financial constraints, and site-related challenges, which collectively impacted the construction schedule. Further, the delay in responding to the queries raised by MahaRERA occurred primarily due to the time taken to obtain consents from allottees. This involved extensive coordination, communication, and repeated follow-ups with multiple allottees. Additionally, time was required to compile and verify supporting documents, prepare the PERT Chart, and ensure com…”

Source: Shraddha Palm’s extension records on MahaRERA (P51800055034), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Shraddha Palm

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800055034
Status
Registered and active
Builder
Dharmadi Enterprises
Location
Mulund East, Mumbai · 400081
Project type
Others
Registered on
26 Feb 2024
Completion date at registration
March 2026
Latest completion date
March 2027
Delay so far
12 months
Homes
45
Sold or booked
21%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Shraddha Palm, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shraddha Palm100%95.65%77.5%0%

Commencement certificate (CC), as filed on MahaRERA

  • Shraddha Palm: covers 22 (Ground + 21 Upper Floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shraddha Palm every 1–2 months.

Shraddha Palm: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK389 – 42723
2 BHK628 – 69018
3 BHK768 – 8233
Shops251 – 4062
4 BHK1,5541

The builder’s record and reviews

Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects.

Read Google reviews of Shraddha Palm →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shraddha Palm: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Shraddha Palm

What is the possession date of Shraddha Palm?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shraddha Palm in Mulund East, Mumbai is 31 March 2027 — 12 months later than 31 March 2026, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Shraddha Palm?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shraddha Palm's builder has filed on MahaRERA, the official one, is 31 March 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Shraddha Palm extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The completion of the project was adversely affected due to unforeseen circumstances including delays in procurement of materials, financial constraints, and site-related challenges, which collectively impacted the construction schedule. Further, the delay in responding to the queries raised by MahaRERA occurred primarily due to the time taken to obtain consents from allottees. This involved extensive coordination, communication, and repeated follow-ups with multiple allottees. Additionally, time was required to compile and verify supporting documents, prepare the PERT Chart, and ensure com…".

What is the RERA number of Shraddha Palm?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shraddha Palm in Mulund East, Mumbai is P51800055034.

Is Shraddha Palm registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm is registered as P51800055034 and its status is "Registered and active".

What is the current construction status of Shraddha Palm? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shraddha Palm is 95.65% done and internal work 77.5%. GharKundli's full report compares construction progress with the deadline.

Does Shraddha Palm have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Shraddha Palm safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm is registered on MahaRERA as P51800055034, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Shraddha Palm?

Shraddha Palm is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Shraddha Palm are 389 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Shraddha Palm?

For a flat in Shraddha Palm (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Shraddha Palm received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm is still under construction, with 31 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Shraddha Palm a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm is a redevelopment: 13 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Shraddha Palm uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shraddha Palm was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Shraddha Palm's possession date changes?

The latest dates are on Shraddha Palm's MahaRERA page (P51800055034). GharKundli's Kundli Watch sends a free WhatsApp update on Shraddha Palm every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shraddha Palm have?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm has one building filed: Shraddha Palm with 20 floors and 47 units.

What are the flat sizes (carpet area) in Shraddha Palm?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Shraddha Palm: 1 BHK: 389 to 427 sq ft carpet (23 homes); 2 BHK: 628 to 690 sq ft carpet (18 homes); 3 BHK: 768 to 823 sq ft carpet (3 homes); 4 BHK: 1554 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Shraddha Palm?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm stands on 603 sq m of land (about 0.1 acres), with 2,595 sq m of sanctioned built-up area.

What is the track record of Shraddha Palm's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Landmark (a group of 8 linked companies) has 35 projects on MahaRERA since 2017, this one included. Of the 35 GharKundli has checked: 12 finished, 8 within the promised date and 4 needed more time (typically 8 months); 22 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 7 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Shraddha Palm?

Google Maps has reviews of Shraddha Palm written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Shraddha Palm?

Shraddha Palm by Dharmadi Enterprises (Shraddha) is in Mulund East, Mumbai, pincode 400081 (near Naupada, Thane West, Panchpakhadi), Maharashtra, and is registered on MahaRERA as P51800055034, per GharKundli's check of MahaRERA records. Its land is filed as C. T. S. No. 882. GharKundli lists all 124 MahaRERA projects in Mulund East (400081).

How many flats are in Shraddha Palm, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm has 45 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.

When was Shraddha Palm registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Shraddha Palm was registered on MahaRERA on 26 February 2024. GharKundli did not find a title report on the land on file there.

Does Shraddha Palm have any legal issues or court cases?

No court cases are listed for Shraddha Palm on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Shraddha Palm?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Dharmadi Enterprises, the company Shraddha files this project under.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Mulund East (400081)

All 124 projects in Mulund East (400081) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.