Possession date of Kalpataru Advay (MahaRERA P51800077381): 30 October 2030. It has 776 homes (1 BHK, 2 BHK and 3 BHK, 480–2435 sq ft carpet), 70% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800077381, and currently active. Its completion date is now October 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800077381, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kalpataru Advay?

2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kalpataru Advay has moved

  1. 30 June 2030

    Completion date given when the project was registered

  2. 30 October 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Kalpataru Advay’s extension records on MahaRERA (P51800077381), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kalpataru Advay

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the October 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800077381
Status
Registered and active
Builder
Kalpataru Limited
Location
Vajira Naka Borivali, Mumbai · 400091
Project type
Residential / Group Housing
Registered on
12 Aug 2024
Completion date at registration
June 2030
Latest completion date
October 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
776
Sold or booked
70%
Towers
3
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
9

Construction progress of Kalpataru Advay, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing A100%50%21%0%
Wing B100%46%14%0%
Wing C100%53%19%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing A: covers 34 floors
  • Wing B: covers 47 floors
  • Wing C: covers 34 floors

Latest CC order on MahaRERA: dated 08/05/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kalpataru Advay every 1–2 months.

Kalpataru Advay: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK505 – 780415
3 BHK1,138 – 1,258174
Other685 – 735100
4 BHK1,70478
1 BHK4807
5 BHK2,4352
  • Buildings: Wing A (39 floors, 261 units) · Wing B (49 floors, 254 units) · Wing C (39 floors, 261 units)
  • Car parking: 1,201 covered
  • Land: 23,829 sq m (about 5.9 acres) · sanctioned built-up 73,892 sq m · recreational space 5,463 sq m
  • Land, as filed: C.T.S. No.2 (Pt) of Eksar-S village & 258/B of Borivali Village, Borivali (W), Mumbai.
  • Map: Get directions

The builder’s record and reviews

Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 61 finished, 57 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 392 complaints on MahaRERA across 60 projects.

Read Google reviews of Kalpataru Advay →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kalpataru Advay: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kalpataru Advay

What is the possession date of Kalpataru Advay?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kalpataru Advay in Vajira Naka Borivali, Mumbai is 30 October 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Kalpataru Advay?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kalpataru Advay's builder has filed on MahaRERA, the official one, is 30 October 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kalpataru Advay?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kalpataru Advay in Vajira Naka Borivali, Mumbai is P51800077381.

Is Kalpataru Advay registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay is registered as P51800077381 and its status is "Registered and active".

What is the current construction status of Kalpataru Advay? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 46% to 53% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Kalpataru Advay have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kalpataru Advay safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay is registered on MahaRERA as P51800077381, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kalpataru Advay?

Kalpataru Advay is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Kalpataru Advay are 480 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kalpataru Advay?

For a flat in Kalpataru Advay (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Kalpataru Advay received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay is still under construction, with 30 October 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Kalpataru Advay a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay is a redevelopment: 445 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Kalpataru Advay uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kalpataru Advay was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kalpataru Advay's possession date changes?

The latest dates are on Kalpataru Advay's MahaRERA page (P51800077381). GharKundli's Kundli Watch sends a free WhatsApp update on Kalpataru Advay every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kalpataru Advay have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay has 3 buildings filed: Wing A with 39 floors and 261 units; Wing B with 49 floors and 254 units; Wing C with 39 floors and 261 units.

What are the flat sizes (carpet area) in Kalpataru Advay?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kalpataru Advay: 2 BHK: 505 to 780 sq ft carpet (415 homes); 3 BHK: 1138 to 1258 sq ft carpet (174 homes); Other: 685 to 735 sq ft carpet (100 homes); 4 BHK: 1704 sq ft carpet (78 homes); 1 BHK: 480 sq ft carpet (7 homes); 5 BHK: 2435 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Kalpataru Advay have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1,201 covered car parking spaces for Kalpataru Advay.

How big is the land of Kalpataru Advay?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay stands on 23,829 sq m of land (about 5.9 acres), with 73,892 sq m of sanctioned built-up area and 5,463 sq m of recreational open space.

What is the track record of Kalpataru Advay's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru (a group of 21 linked companies) has 96 projects on MahaRERA since 2017, this one included. Of the 96 GharKundli has checked: 61 finished, 57 within the promised date and 4 needed more time (typically 5 months); 33 still being built, 2 past the promised date (typically 5 months late); 2 lapsed. 392 complaints on MahaRERA across 60 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kalpataru Advay?

Google Maps has reviews of Kalpataru Advay written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kalpataru Advay?

Kalpataru Advay by Kalpataru Limited (Agile) is in Vajira Naka Borivali, Mumbai, pincode 400091 (near Borivali West, Mandapeshwar, Kandivali West), Maharashtra, and is registered on MahaRERA as P51800077381, per GharKundli's check of MahaRERA records. Its land is filed as C.T.S. No.2 (Pt) of Eksar-S village & 258/B of Borivali Village, Borivali (W), Mumbai.. GharKundli lists all 69 MahaRERA projects in Borivali West (400091).

How many flats are in Kalpataru Advay, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay has 776 homes in 3 towers registered on MahaRERA, and 70% of them are sold or booked.

When was Kalpataru Advay registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kalpataru Advay was registered on MahaRERA on 12 August 2024. GharKundli did not find a title report on the land on file there.

Does Kalpataru Advay have any legal issues or court cases?

2 court cases are listed for Kalpataru Advay on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Kalpataru Advay?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kalpataru Limited, the company Agile files this project under, which has 9 other projects registered on MahaRERA.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Borivali West (400091)

All 69 projects in Borivali West (400091) →

Other projects by Kalpataru Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.