Skip to content
GharKundli

Lakshmi Eternia

by LAKSHMI BUILDERS DEVELOPER LLP · Vile Parle, Mumbai 400057Also near Vileeparle East, Vileparle West, Andheri East

What’s in the report? →

Possession date of Lakshmi Eternia (MahaRERA P51800078237): 15 September 2027. It has 10 homes (2 BHK, 3 BHK and 4 BHK, 697–3210 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800078237, and currently active.

Source: MahaRERA website — records for P51800078237, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Lakshmi Eternia?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Lakshmi Eternia

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800078237
Status
Registered and active
Builder
LAKSHMI BUILDERS DEVELOPER LLP
Location
Vile Parle, Mumbai · 400057
Project type
Residential / Group Housing
Registered on
29 Nov 2024
Completion date at registration
September 2027
Homes
10
Sold or booked
100%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Lakshmi Eternia, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LAKSHMI ETERNIA100%100%95%80%

Commencement certificate (CC), as filed on MahaRERA

  • LAKSHMI ETERNIA: covers CC for work up to top of stilt slab level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lakshmi Eternia every 1–2 months.

Lakshmi Eternia: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK697 – 1,2477
4 BHK2,0111
Duplex3,2101
3 BHK1,0701
  • Buildings: LAKSHMI ETERNIA (9 floors, 10 units)
  • Car parking: 21 covered
  • Land: 477 sq m (about 0.1 acres) · sanctioned built-up 1,285 sq m
  • Land, as filed: 330
  • Map: Get directions

The builder’s record and reviews

Lakshmi Builders AND Developers (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 6 finished, all within the promised date; 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Lakshmi Eternia →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lakshmi Eternia: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Lakshmi Eternia

What is the possession date of Lakshmi Eternia?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Lakshmi Eternia in Vile Parle, Mumbai is 15 September 2027.

Is the builder's possession date different from the MahaRERA date for Lakshmi Eternia?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lakshmi Eternia's builder has filed on MahaRERA, the official one, is 15 September 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Lakshmi Eternia?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Lakshmi Eternia in Vile Parle, Mumbai is P51800078237.

Is Lakshmi Eternia registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia is registered as P51800078237 and its status is "Registered and active".

What is the current construction status of Lakshmi Eternia? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia's status on MahaRERA is "Registered and active". As filed by the builder, slab work on LAKSHMI ETERNIA is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Lakshmi Eternia have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Lakshmi Eternia safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia is registered on MahaRERA as P51800078237, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Lakshmi Eternia?

Lakshmi Eternia is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Lakshmi Eternia start at 697 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Lakshmi Eternia?

For a flat in Lakshmi Eternia (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Lakshmi Eternia received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia is still under construction, with 15 September 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Lakshmi Eternia a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia is a redevelopment: 4 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Lakshmi Eternia uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Lakshmi Eternia was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Lakshmi Eternia's possession date changes?

The latest dates are on Lakshmi Eternia's MahaRERA page (P51800078237). GharKundli's Kundli Watch sends a free WhatsApp update on Lakshmi Eternia every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lakshmi Eternia have?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia has one building filed: LAKSHMI ETERNIA with 9 floors and 10 units.

What are the flat sizes (carpet area) in Lakshmi Eternia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Lakshmi Eternia: 2 BHK: 697 to 1247 sq ft carpet (7 homes); 4 BHK: 2011 sq ft carpet (1 homes); Duplex: 3210 sq ft carpet (1 homes); 3 BHK: 1070 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Lakshmi Eternia have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 21 covered car parking spaces for Lakshmi Eternia.

How big is the land of Lakshmi Eternia?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia stands on 477 sq m of land (about 0.1 acres), with 1,285 sq m of sanctioned built-up area.

What is the track record of Lakshmi Eternia's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Builders AND Developers (a group of 2 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 6 finished, all within the promised date; 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Lakshmi Eternia?

Google Maps has reviews of Lakshmi Eternia written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Lakshmi Eternia?

Lakshmi Eternia by LAKSHMI BUILDERS DEVELOPER LLP is in Vile Parle, Mumbai, pincode 400057 (near Vileeparle East, Vileparle West, Andheri East), Maharashtra, and is registered on MahaRERA as P51800078237, per GharKundli's check of MahaRERA records. Its land is filed as 330. GharKundli lists all 251 MahaRERA projects in Vile Parle East (400057).

How many flats are in Lakshmi Eternia, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia has 10 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Lakshmi Eternia registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Lakshmi Eternia was registered on MahaRERA on 29 November 2024. GharKundli did not find a title report on the land on file there.

Does Lakshmi Eternia have any legal issues or court cases?

No court cases are listed for Lakshmi Eternia on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Lakshmi Eternia?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAKSHMI BUILDERS DEVELOPER LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Vile Parle East (400057)

All 251 projects in Vile Parle East (400057) →

Other projects by LAKSHMI BUILDERS DEVELOPER LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.