by LAKSHMI BUILDERS DEVELOPER LLP · Vile Parle (E), Mumbai

Registered on MahaRERA under PR1180002600675, and currently active. Its completion date has moved from May 2029 to September 2029, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
PR1180002600675
Status
Registered and active
Builder
LAKSHMI BUILDERS DEVELOPER LLP
Location
Vile Parle (E), Mumbai · 400057
Project type
Residential / Group Housing
Registered on
5 Jun 2026
Completion date at registration
May 2029
Latest completion date
September 2029
Delay so far
4 months
Homes
21
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

GharKundli’s full report on 64 CREST

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

64 CREST: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about 64 CREST

Is 64 CREST registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), 64 CREST is registered as PR1180002600675 and its status is "Registered and active".

Where is 64 CREST?

64 CREST by LAKSHMI BUILDERS DEVELOPER LLP is in Vile Parle (E), Mumbai (pincode 400057), Maharashtra, and is registered on MahaRERA as PR1180002600675, per GharKundli's check of MahaRERA records.

When is possession of 64 CREST due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 64 CREST in Vile Parle (E), Mumbai is 1 September 2029 — 4 months later than 1 May 2029, the date given at registration.

Does 64 CREST have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of 64 CREST?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAKSHMI BUILDERS DEVELOPER LLP, which has 1 other project registered on MahaRERA.

Other projects in pincode 400057

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.