by Sun Sumit Venture · Andheri West, Mumbai 400058Also near Ambivali West, Jogeshwari East, Jogeshwari WEst
What’s in the report? →Possession date of Sun Sumit Yashodhan (MahaRERA P51800079912): 30 April 2028. It has 38 homes (1 BHK, 2 BHK and 3 BHK, 414–1198 sq ft carpet), 18% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800079912, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800079912, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sun Sumit Yashodhan?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sun Sumit Yashodhan has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sun Sumit Yashodhan’s extension records on MahaRERA (P51800079912), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sun Sumit Yashodhan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800079912
- Status
- Registered and active
- Builder
- Sun Sumit Venture
- Location
- Andheri West, Mumbai · 400058
- Project type
- Residential / Group Housing
- Registered on
- 29 Mar 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 38
- Sold or booked
- 18%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Sun Sumit Yashodhan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sun Sumit Yashodhan | 100% | 84% | 80% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sun Sumit Yashodhan: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sun Sumit Yashodhan every 1–2 months.
Sun Sumit Yashodhan: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 414 – 421 | 20 |
| 2 BHK | 693 – 743 | 17 |
| 3 BHK | 1,198 | 1 |
- Buildings: Sun Sumit Yashodhan (11 floors, 38 units)
- Car parking: 46 covered
- Land: 966 sq m (about 0.2 acres) · sanctioned built-up 2,218 sq m
- Land, as filed: 264C & 275(Pt.)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sun Sumit Venture has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 11 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Sun Sumit Yashodhan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sun Sumit Yashodhan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sun Sumit Yashodhan
What is the possession date of Sun Sumit Yashodhan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sun Sumit Yashodhan in Andheri West, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Sun Sumit Yashodhan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sun Sumit Yashodhan's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Sun Sumit Yashodhan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sun Sumit Yashodhan in Andheri West, Mumbai is P51800079912.
Is Sun Sumit Yashodhan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan is registered as P51800079912 and its status is "Registered and active".
What is the current construction status of Sun Sumit Yashodhan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sun Sumit Yashodhan is 84% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does Sun Sumit Yashodhan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sun Sumit Yashodhan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan is registered on MahaRERA as P51800079912, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sun Sumit Yashodhan?
Sun Sumit Yashodhan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sun Sumit Yashodhan are 414 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sun Sumit Yashodhan?
For a flat in Sun Sumit Yashodhan (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sun Sumit Yashodhan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Sun Sumit Yashodhan a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Sun Sumit Yashodhan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sun Sumit Yashodhan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sun Sumit Yashodhan's possession date changes?
The latest dates are on Sun Sumit Yashodhan's MahaRERA page (P51800079912). GharKundli's Kundli Watch sends a free WhatsApp update on Sun Sumit Yashodhan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sun Sumit Yashodhan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan has one building filed: Sun Sumit Yashodhan with 11 floors and 38 units.
What are the flat sizes (carpet area) in Sun Sumit Yashodhan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sun Sumit Yashodhan: 1 BHK: 414 to 421 sq ft carpet (20 homes); 2 BHK: 693 to 743 sq ft carpet (17 homes); 3 BHK: 1198 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Sun Sumit Yashodhan have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 46 covered car parking spaces for Sun Sumit Yashodhan.
How big is the land of Sun Sumit Yashodhan?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan stands on 966 sq m of land (about 0.2 acres), with 2,218 sq m of sanctioned built-up area.
What is the track record of Sun Sumit Yashodhan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Venture has 4 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 11 months); 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sun Sumit Yashodhan?
Google Maps has reviews of Sun Sumit Yashodhan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sun Sumit Yashodhan?
Sun Sumit Yashodhan by Sun Sumit Venture is in Andheri West, Mumbai, pincode 400058 (near Ambivali West, Jogeshwari East, Jogeshwari WEst), Maharashtra, and is registered on MahaRERA as P51800079912, per GharKundli's check of MahaRERA records. Its land is filed as 264C & 275(Pt.). GharKundli lists all 148 MahaRERA projects in Andheri West (400058).
How many flats are in Sun Sumit Yashodhan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan has 38 homes in 1 tower registered on MahaRERA, and 18% of them are sold or booked.
When was Sun Sumit Yashodhan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sun Sumit Yashodhan was registered on MahaRERA on 29 March 2025. GharKundli did not find a title report on the land on file there.
Does Sun Sumit Yashodhan have any legal issues or court cases?
No court cases are listed for Sun Sumit Yashodhan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sun Sumit Yashodhan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sun Sumit Venture, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sun Sumit Yashodhan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Andheri West (400058)
- Naman Habitat
- Mesacon Harmony
- Shradha Residency
- Matruchaya CHS Ltd
- Rachanaa Aaravya
- Shepherd Horizon
- Priya Co-operative Housing Society LTD.
- Mobin Heights
Other projects by Sun Sumit Venture
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.