Shreeji Shraddha
by Shreeji Realtech · Ghatkopar East, Mumbai 400075Also near Ghatkopar West, Sanghani Estate, Barve Nagar
What’s in the report? →Possession date of Shreeji Shraddha (MahaRERA PR1180002500451): 30 October 2028. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002500451, and currently active. Its completion date is now October 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002500451, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shreeji Shraddha?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shreeji Shraddha has moved
30 June 2028
Completion date given when the project was registered
30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shreeji Shraddha’s extension records on MahaRERA (PR1180002500451), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shreeji Shraddha
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002500451
- Status
- Registered and active
- Builder
- Shreeji Realtech
- Location
- Ghatkopar East, Mumbai · 400075
- Project type
- Residential / Group Housing
- Registered on
- 1 Aug 2025
- Completion date at registration
- June 2028
- Latest completion date
- October 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shreeji Shraddha, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C.C. issued upto Plinth level | 100% | 13% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- C.C. issued upto Plinth level: covers Plinth
Latest CC order on MahaRERA: dated 24/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shreeji Shraddha every 1–2 months.
Shreeji Shraddha: buildings, flats and land, as filed on MahaRERA
- Buildings: C.C. issued upto Plinth level (1 floors)
- Land: 807 sq m (about 0.2 acres)
- Boundaries filed include: Recreation Ground
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shreeji Shraddha →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shreeji Shraddha: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shreeji Shraddha
What is the possession date of Shreeji Shraddha?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shreeji Shraddha in Ghatkopar East, Mumbai is 30 October 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shreeji Shraddha?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shreeji Shraddha's builder has filed on MahaRERA, the official one, is 30 October 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shreeji Shraddha?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shreeji Shraddha in Ghatkopar East, Mumbai is PR1180002500451.
Is Shreeji Shraddha registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha is registered as PR1180002500451 and its status is "Registered and active".
What is the current construction status of Shreeji Shraddha? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha's status on MahaRERA is "Registered and active". As filed by the builder, slab work on C.C. issued upto Plinth level is 13% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Shreeji Shraddha have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shreeji Shraddha safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha is registered on MahaRERA as PR1180002500451, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shreeji Shraddha?
Shreeji Shraddha is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shreeji Shraddha?
For a flat in Shreeji Shraddha (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Shreeji Shraddha received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha is still under construction, with 30 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Shreeji Shraddha uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shreeji Shraddha was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shreeji Shraddha's possession date changes?
The latest dates are on Shreeji Shraddha's MahaRERA page (PR1180002500451). GharKundli's Kundli Watch sends a free WhatsApp update on Shreeji Shraddha every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shreeji Shraddha have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha has one building filed: C.C. issued upto Plinth level with 1 floors.
How big is the land of Shreeji Shraddha?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha stands on 807 sq m of land (about 0.2 acres).
What are the reviews of Shreeji Shraddha?
Google Maps has reviews of Shreeji Shraddha written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shreeji Shraddha?
Shreeji Shraddha by Shreeji Realtech is in Ghatkopar East, Mumbai, pincode 400075 (near Ghatkopar West, Sanghani Estate, Barve Nagar), Maharashtra, and is registered on MahaRERA as PR1180002500451, per GharKundli's check of MahaRERA records. Its boundaries filed there include Recreation Ground. GharKundli lists all 133 MahaRERA projects in Ghatkopar East (400075).
When was Shreeji Shraddha registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shreeji Shraddha was registered on MahaRERA on 1 August 2025. GharKundli did not find a title report on the land on file there.
Does Shreeji Shraddha have any legal issues or court cases?
No court cases are listed for Shreeji Shraddha on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shreeji Shraddha?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Shreeji Realtech.
Check it yourself on MahaRERA
- How to check the possession date of Shreeji Shraddha
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Ghatkopar East (400075)
- RDK Belvedere
- Poonam Celeste
- Senghani Paradise
- Alag Ananta
- Rushabh Kiran
- Vikas Ornate
- Shree Matru Krupa
- Orient Odyssey
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.