by NAVKAR CONSTRUCTION · Andheri, Mumbai 400058Also near Vile Parle east, Vile Parle West, Lallubhai Park

What’s in the report? →

Possession date of Navkar Palace (MahaRERA PR1180002500275): 28 February 2029. It has 78 homes (2 BHK, 3 BHK and 4 BHK, 669–1513 sq ft carpet), 62% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002500275, and currently active. Its completion date is now February 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002500275, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Navkar Palace?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Navkar Palace has moved

  1. 31 October 2028

    Completion date given when the project was registered

  2. 28 February 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Navkar Palace’s extension records on MahaRERA (PR1180002500275), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Navkar Palace

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002500275
Status
Registered and active
Builder
NAVKAR CONSTRUCTION
Location
Andheri, Mumbai · 400058
Project type
Residential / Group Housing
Registered on
16 Jul 2025
Completion date at registration
October 2028
Latest completion date
February 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
78
Sold or booked
62%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Navkar Palace, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Navkar Palace / WING A80%80%55%0%
Navkar Palace / WING B80%80%55%0%

Commencement certificate (CC), as filed on MahaRERA

  • Navkar Palace: covers PLINTH
  • Navkar Palace: covers PLINTH

Latest CC order on MahaRERA: dated 20/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Navkar Palace every 1–2 months.

Navkar Palace: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK669 – 76034
3 BHK934 – 1,13732
4 BHK1,110 – 1,51312

The builder’s record and reviews

Navkar Construction (a group of 4 linked companies) has 5 projects on MahaRERA since 2023, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Navkar Palace →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Navkar Palace: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Navkar Palace

What is the possession date of Navkar Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Navkar Palace in Andheri, Mumbai is 28 February 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Navkar Palace?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Navkar Palace's builder has filed on MahaRERA, the official one, is 28 February 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Navkar Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Navkar Palace in Andheri, Mumbai is PR1180002500275.

Is Navkar Palace registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace is registered as PR1180002500275 and its status is "Registered and active".

What is the current construction status of Navkar Palace? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 80% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Navkar Palace have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Navkar Palace safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace is registered on MahaRERA as PR1180002500275, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Navkar Palace?

Navkar Palace is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Navkar Palace start at 669 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Navkar Palace?

For a flat in Navkar Palace (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Navkar Palace received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace is still under construction, with 28 February 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Navkar Palace a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace is a redevelopment: 39 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Navkar Palace uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Navkar Palace was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Navkar Palace's possession date changes?

The latest dates are on Navkar Palace's MahaRERA page (PR1180002500275). GharKundli's Kundli Watch sends a free WhatsApp update on Navkar Palace every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Navkar Palace have?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace has 2 buildings filed: Navkar Palace with 12 floors and 49 units; Navkar Palace with 12 floors and 29 units.

What are the flat sizes (carpet area) in Navkar Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Navkar Palace: 2 BHK: 669 to 760 sq ft carpet (34 homes); 3 BHK: 934 to 1137 sq ft carpet (32 homes); 4 BHK: 1110 to 1513 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Navkar Palace have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 128 covered car parking spaces for Navkar Palace.

How big is the land of Navkar Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace stands on 2,476 sq m of land (about 0.6 acres), with 7,354 sq m of sanctioned built-up area.

What is the track record of Navkar Palace's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Construction (a group of 4 linked companies) has 5 projects on MahaRERA since 2023, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Navkar Palace?

Google Maps has reviews of Navkar Palace written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Navkar Palace?

Navkar Palace by NAVKAR CONSTRUCTION is in Andheri, Mumbai, pincode 400058 (near Vile Parle east, Vile Parle West, Lallubhai Park), Maharashtra, and is registered on MahaRERA as PR1180002500275, per GharKundli's check of MahaRERA records. GharKundli lists all 148 MahaRERA projects in Andheri West (400058).

How many flats are in Navkar Palace, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace has 78 homes in 2 towers registered on MahaRERA, and 62% of them are sold or booked.

When was Navkar Palace registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Navkar Palace was registered on MahaRERA on 16 July 2025. GharKundli did not find a title report on the land on file there.

Does Navkar Palace have any legal issues or court cases?

No court cases are listed for Navkar Palace on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Navkar Palace?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NAVKAR CONSTRUCTION, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2029 in Mumbai Suburban →

Other projects in Andheri West (400058)

All 148 projects in Andheri West (400058) →

Other projects by NAVKAR CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.