Possession date of Jem Mininagar (MahaRERA PR1180002502136): 9 January 2030. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1180002502136, and currently active. Its completion date is now January 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1180002502136, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Jem Mininagar?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Jem Mininagar has moved

  1. 9 September 2029

    Completion date given when the project was registered

  2. 9 January 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Jem Mininagar’s extension records on MahaRERA (PR1180002502136), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Jem Mininagar

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1180002502136
Status
Registered and active
Builder
JEM DEVELOPERS & BUILDERS
Location
Dahisar East, Mumbai · 400068
Project type
Residential / Group Housing
Registered on
21 Jan 2026
Completion date at registration
September 2029
Latest completion date
January 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
6
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Jem Mininagar, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing - A0%0%0%0%
Wing - B60%0%0%0%
Wing - C160%0%0%0%
Wing - C100%0%0%0%
Wing - D100%0%0%0%
Wing - E100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing - A: covers Up to top of plinth level only
  • Wing - B: covers Up to top of plinth level only
  • Wing - C1: covers Up to top of plinth level only
  • Wing - C: covers Up to top of plinth level only
  • Wing - D: covers Up to top of plinth level only
  • Wing - E: covers Up to top of plinth level only

Latest CC order on MahaRERA: dated 10/11/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jem Mininagar every 1–2 months.

Jem Mininagar: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

JEM Developeres AND Builderes (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 85 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of Jem Mininagar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jem Mininagar: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Jem Mininagar

What is the possession date of Jem Mininagar?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jem Mininagar in Dahisar East, Mumbai is 9 January 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Jem Mininagar?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jem Mininagar's builder has filed on MahaRERA, the official one, is 9 January 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Jem Mininagar?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jem Mininagar in Dahisar East, Mumbai is PR1180002502136.

Is Jem Mininagar registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar is registered as PR1180002502136 and its status is "Registered and active".

What is the current construction status of Jem Mininagar? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 6 towers. GharKundli's full report compares construction progress with the deadline.

Does Jem Mininagar have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Jem Mininagar safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar is registered on MahaRERA as PR1180002502136, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Jem Mininagar?

Jem Mininagar is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Jem Mininagar?

For a flat in Jem Mininagar (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Jem Mininagar received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar is still under construction, with 9 January 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Jem Mininagar a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Jem Mininagar uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Jem Mininagar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Jem Mininagar's possession date changes?

The latest dates are on Jem Mininagar's MahaRERA page (PR1180002502136). GharKundli's Kundli Watch sends a free WhatsApp update on Jem Mininagar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Jem Mininagar?

According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar stands on 4,551 sq m of land (about 1.1 acres).

What is the track record of Jem Mininagar's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), JEM Developeres AND Builderes (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, 1 past the promised date (typically 85 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Jem Mininagar?

Google Maps has reviews of Jem Mininagar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Jem Mininagar?

Jem Mininagar by JEM DEVELOPERS & BUILDERS is in Dahisar East, Mumbai, pincode 400068 (near Dahisar West, Borivali West, Mandapeshwar), Maharashtra, and is registered on MahaRERA as PR1180002502136, per GharKundli's check of MahaRERA records. Its boundaries filed there include Shyam Narayan Dubey Road, Western Express Highway. GharKundli lists all 180 MahaRERA projects in Dahisar East (400068).

When was Jem Mininagar registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Jem Mininagar was registered on MahaRERA on 21 January 2026. GharKundli did not find a title report on the land on file there.

Does Jem Mininagar have any legal issues or court cases?

No court cases are listed for Jem Mininagar on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Jem Mininagar?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JEM DEVELOPERS & BUILDERS.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Dahisar East (400068)

All 180 projects in Dahisar East (400068) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.