Pinnakle Nova
by PINNAKLE HOME SPACES LLP · Vikhroli East, Mumbai 400083Also near kanamwar Nagar, Tagore Nagar, Hariyali, Vikhroli
What’s in the report? →Possession date of Pinnakle Nova (MahaRERA PM1180002502641): 30 April 2030. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002502641, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1180002502641, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Pinnakle Nova?
Possession date khiski: ab Apr 2030. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Pinnakle Nova has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Pinnakle Nova’s extension records on MahaRERA (PM1180002502641), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pinnakle Nova
Ready · November 2026 · 4 filings read
- Risk & trust score, every point explained
- What the title report on MahaRERA says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002502641
- Status
- Registered and active
- Builder
- PINNAKLE HOME SPACES LLP
- Location
- Vikhroli East, Mumbai · 400083
- Project type
- Mixed
- Registered on
- 9 Mar 2026
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Yes
- Latest construction certificate
- 30 Jun 2026
Construction progress of Pinnakle Nova, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG NO 151 - KANNAMVAR NAGAR SAMBHAV CHS LTD | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLDG NO 151 - KANNAMVAR NAGAR SAMBHAV CHS LTD: covers 1 floors
Latest CC order on MahaRERA: dated 10/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pinnakle Nova every 1–2 months.
Pinnakle Nova: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG NO 151 - KANNAMVAR NAGAR SAMBHAV CHS LTD (1 floors)
- Land: 976 sq m (about 0.2 acres)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Pinnakle Nova →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pinnakle Nova: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Pinnakle Nova
What is the possession date of Pinnakle Nova?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Pinnakle Nova in Vikhroli East, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Pinnakle Nova?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pinnakle Nova's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Pinnakle Nova?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Pinnakle Nova in Vikhroli East, Mumbai is PM1180002502641.
Is Pinnakle Nova registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova is registered as PM1180002502641 and its status is "Registered and active".
What is the current construction status of Pinnakle Nova? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLDG NO 151 - KANNAMVAR NAGAR SAMBHAV CHS LTD is 0% done and internal work 0%. The latest construction certificate the builder filed there is dated 30 June 2026. GharKundli's full report compares construction progress with the deadline.
Does Pinnakle Nova have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Pinnakle Nova safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova is registered on MahaRERA as PM1180002502641, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Pinnakle Nova?
Pinnakle Nova is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Pinnakle Nova?
For a flat in Pinnakle Nova (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Pinnakle Nova received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Pinnakle Nova uploaded its title report on MahaRERA?
Yes. According to GharKundli's check of MahaRERA records (updated November 2026), an advocate's title report for Pinnakle Nova is uploaded on MahaRERA. It says who owns the land and whether there's any loan, case or claim on it. GharKundli's full report reads it and lists anything that needs a written answer from the builder.
A loan or claim on the land can hold up your flat or your home loan. See what the title report says →
How can I get updates if Pinnakle Nova's possession date changes?
The latest dates are on Pinnakle Nova's MahaRERA page (PM1180002502641). GharKundli's Kundli Watch sends a free WhatsApp update on Pinnakle Nova every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pinnakle Nova have?
According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova has one building filed: BLDG NO 151 - KANNAMVAR NAGAR SAMBHAV CHS LTD with 1 floors.
How big is the land of Pinnakle Nova?
According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova stands on 976 sq m of land (about 0.2 acres).
What are the reviews of Pinnakle Nova?
Google Maps has reviews of Pinnakle Nova written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Pinnakle Nova?
Pinnakle Nova by PINNAKLE HOME SPACES LLP is in Vikhroli East, Mumbai, pincode 400083 (near kanamwar Nagar, Tagore Nagar, Hariyali, Vikhroli), Maharashtra, and is registered on MahaRERA as PM1180002502641, per GharKundli's check of MahaRERA records. GharKundli lists all 176 MahaRERA projects in Vikhroli East (400083).
When was Pinnakle Nova registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Pinnakle Nova was registered on MahaRERA on 9 March 2026. A title report on the land is on file there.
Does Pinnakle Nova have any legal issues or court cases?
No court cases are listed for Pinnakle Nova on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Pinnakle Nova?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PINNAKLE HOME SPACES LLP.
Check it yourself on MahaRERA
- How to check the possession date of Pinnakle Nova
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai Suburban →
Other projects in Kurla
- Saptashringi
- Sudhanshu Heights
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Kanakdhara
- Privilon
- Heritage Lakeside
- Valentina CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.