SHREE CHINTAMANI

by SHREE SHIVBALI BUILDERS PRIVATE LIMITED · Borivali West, Mumbai

Registered on MahaRERA under PM1180002601360, and currently active. Its completion date has moved from December 2029 to April 2030, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

MahaRERA registration
PM1180002601360
Status
Registered and active
Builder
SHREE SHIVBALI BUILDERS PRIVATE LIMITED
Location
Borivali West, Mumbai · 400091
Project type
Mixed
Registered on
30 Jul 2026
Completion date at registration
December 2029
Latest completion date
April 2030
Delay so far
4 months
Homes
48
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

GharKundli’s full report on SHREE CHINTAMANI

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Kundli Watch

SHREE CHINTAMANI: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SHREE CHINTAMANI

Is SHREE CHINTAMANI registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREE CHINTAMANI is registered as PM1180002601360 and its status is "Registered and active".

Where is SHREE CHINTAMANI?

SHREE CHINTAMANI by SHREE SHIVBALI BUILDERS PRIVATE LIMITED is in Borivali West, Mumbai (pincode 400091), Maharashtra, and is registered on MahaRERA as PM1180002601360, per GharKundli's check of MahaRERA records.

When is possession of SHREE CHINTAMANI due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE CHINTAMANI in Borivali West, Mumbai is 30 April 2030 — 4 months later than 31 December 2029, the date given at registration.

Does SHREE CHINTAMANI have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of SHREE CHINTAMANI?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SHIVBALI BUILDERS PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.

Other projects in pincode 400091

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.