by SONAL DEV-CON PVT LTD · Near Agroli Pond, ThaneAlso near CBD Belapur, Vashi, Agroli Belapur

Possession date of GOPAL KRISHNA: 30 August 2027, moved from 30 April 2019 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700001570, and currently active. Its completion date has moved from April 2019 to August 2027: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about GOPAL KRISHNA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GOPAL KRISHNA has moved

  1. 30 April 2019

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51700001557)

    Reason the builder gave MahaRERA:
    “That we have received the virtual completion certificate from the Architect of our building on 25/01/2019 and also obtained various NOC's such as NOC for Property Tax, Health NOC, License for Lift, approval for drainage connection, etc. and…” Read the full reason“That we have received the virtual completion certificate from the Architect of our building on 25/01/2019 and also obtained various NOC's such as NOC for Property Tax, Health NOC, License for Lift, approval for drainage connection, etc. and after obtaining all the NOC's from the concern authorities will apply for the Occupancy Certificate which may take 3 to 4 months hence seeking extension.”
  3. 31 October 2021

    Extended at the builder's request (MahaRERA application EXT51700008497)

    Reason the builder gave MahaRERA:
    “Although we have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to prolong lockdown on account of COVID-19 and the activiti…” Read the full reason“Although we have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to prolong lockdown on account of COVID-19 and the activities of the concern department has been in slow mode for the last 8 months and the promoters are hopeful that the Occupancy Certificate would be issued sooner than later.”
  4. 30 April 2023

    Extended at the builder's request (MahaRERA application EXT51700011967)

    Reason the builder gave MahaRERA:
    “We have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to the activities of the concerned department has been in slow mode…” Read the full reason“We have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to the activities of the concerned department has been in slow mode for the last several months and we are hopeful that the Occupancy Certificate would be issued sooner than later.”
  5. 30 April 2024

    Extended at the builder's request (MahaRERA application EXT51700017219)

    Reason the builder gave MahaRERA:
    “WE HAVE COMPLETED THE 100% WORK OF THE BUILDING PROJECT AS PER THE PLANS APPROVED AND OBTAINED ALL THE CLEARANCES EXCEPT AVIATION NOC AND THEREFORE THE OCCUPANCY CERTIFICATE HAS NOT BEEN GRANTED BY THE MUNICIPAL CORPORATION AND THE SAME MAY…” Read the full reason“WE HAVE COMPLETED THE 100% WORK OF THE BUILDING PROJECT AS PER THE PLANS APPROVED AND OBTAINED ALL THE CLEARANCES EXCEPT AVIATION NOC AND THEREFORE THE OCCUPANCY CERTIFICATE HAS NOT BEEN GRANTED BY THE MUNICIPAL CORPORATION AND THE SAME MAY BE RECEIVED AT ANY POINT OF TIME. IT IS THEREFORE HUMBLE PRAYAED THAT EXTENSION MAY BE GRANTED.”
  6. 30 April 2025

    Extended at the builder's request (MahaRERA application EXT51700019797)

    Reason the builder gave MahaRERA: “We have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.”
  7. 30 April 2026

    Extended at the builder's request (MahaRERA application EA11062501471)

    Reason the builder gave MahaRERA: “We have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.”
  8. 30 April 2027

    Extended at the builder's request (MahaRERA application EA29042620766)

    Reason the builder gave MahaRERA: “We have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.”
  9. 30 August 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: GOPAL KRISHNA’s extension records on MahaRERA (P51700001570), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GOPAL KRISHNA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the August 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700001570
Status
Registered and active
Builder
SONAL DEV-CON PVT LTD
Location
Near Agroli Pond, Thane · 400614
Project type
Residential / Group Housing
Registered on
29 Jul 2017
Completion date at registration
April 2019
Latest completion date
August 2027
Delay so far
96 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
54
Sold or booked
50%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of GOPAL KRISHNA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GOPAL KRISHNA100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • GOPAL KRISHNA: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GOPAL KRISHNA every month.

GOPAL KRISHNA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sonal Dev-con has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 26 months); 1 still being built, 1 past the promised date (typically 86 months late). No complaints on MahaRERA.

Read Google reviews of GOPAL KRISHNA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GOPAL KRISHNA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GOPAL KRISHNA

What is the possession date of GOPAL KRISHNA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GOPAL KRISHNA in Near Agroli Pond, Thane is 30 August 2027 — 96 months later than 30 April 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for GOPAL KRISHNA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GOPAL KRISHNA's builder has filed on MahaRERA, the official one, is 30 August 2027, already 96 months later than the 30 April 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GOPAL KRISHNA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA's builder applied to MahaRERA to extend the completion date 7 times: to 30 April 2020, giving the reason "That we have received the virtual completion certificate from the Architect of our building on 25/01/2019 and also obtained various NOC's such as NOC for Property Tax, Health NOC, License for Lift, approval for drainage connection, etc. and after obtaining all the NOC's from the concern authorities will apply for the Occupancy Certificate which may take 3 to 4 months hence seeking extension."; to 31 October 2021, giving the reason "Although we have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to prolong lockdown on account of COVID-19 and the activities of the concern department has been in slow mode for the last 8 months and the promoters are hopeful that the Occupancy Certificate would be issued sooner than later."; to 30 April 2023, giving the reason "We have completed 100% work of the project and is in receipt of completion certificate from the Architect and applied for occupancy certificate but the same is pending due to the activities of the concerned department has been in slow mode for the last several months and we are hopeful that the Occupancy Certificate would be issued sooner than later."; to 30 April 2024, giving the reason "WE HAVE COMPLETED THE 100% WORK OF THE BUILDING PROJECT AS PER THE PLANS APPROVED AND OBTAINED ALL THE CLEARANCES EXCEPT AVIATION NOC AND THEREFORE THE OCCUPANCY CERTIFICATE HAS NOT BEEN GRANTED BY THE MUNICIPAL CORPORATION AND THE SAME MAY BE RECEIVED AT ANY POINT OF TIME. IT IS THEREFORE HUMBLE PRAYAED THAT EXTENSION MAY BE GRANTED."; to 30 April 2025, giving the reason "We have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension."; to 30 April 2026, giving the reason "We have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension."; to 30 April 2027, giving the reason "We have completed 100% work of the building project and applied for Occupancy Certificate and the same is pending due to non receipt of height NOC, which may take some more time and therefore seeking extension.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of GOPAL KRISHNA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GOPAL KRISHNA in Near Agroli Pond, Thane is P51700001570.

Is GOPAL KRISHNA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA is registered as P51700001570 and its status is "Registered and active".

What is the construction status of GOPAL KRISHNA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GOPAL KRISHNA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GOPAL KRISHNA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is GOPAL KRISHNA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA is registered on MahaRERA as P51700001570, its completion date has moved 96 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GOPAL KRISHNA's possession date changes?

The latest dates are on GOPAL KRISHNA's MahaRERA page (P51700001570). GharKundli's Kundli Watch sends a free WhatsApp update on GOPAL KRISHNA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GOPAL KRISHNA have?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA has one building filed: GOPAL KRISHNA with 22 floors and 54 units.

How big is the land of GOPAL KRISHNA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA stands on 2,349 sq m of land (about 0.6 acres), with 3,474 sq m of sanctioned built-up area.

What is the track record of GOPAL KRISHNA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Dev-con has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 26 months); 1 still being built, 1 past the promised date (typically 86 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of GOPAL KRISHNA?

Google Maps has reviews of GOPAL KRISHNA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GOPAL KRISHNA?

GOPAL KRISHNA by SONAL DEV-CON PVT LTD is in Near Agroli Pond, Thane (pincode 400614), near CBD Belapur, Vashi, Agroli Belapur, Maharashtra, and is registered on MahaRERA as P51700001570, per GharKundli's check of MahaRERA records. Its boundaries filed there include 15 MTS WIDE ROAD.

How many homes are in GOPAL KRISHNA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA has 54 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.

When was GOPAL KRISHNA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), GOPAL KRISHNA was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on GOPAL KRISHNA?

No court cases are listed for GOPAL KRISHNA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of GOPAL KRISHNA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SONAL DEV-CON PVT LTD, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Thane

All 48 projects in CBD Belapur (400614) →

Other projects by SONAL DEV-CON PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.