by SONAL DEV-CON PVT LTD · Nehru Nagar, Mumbai 400024Also near Kurla, Bhandup West, Chembur

What’s in the report? →

Possession date of Sonal Heights (MahaRERA P51800008992): 30 April 2025, moved from 30 October 2020 (54 months later), and it has already passed. It has 126 homes (1 BHK and 2 BHK, 222–618 sq ft carpet), 53% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800008992. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800008992, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (April 2025) has passed.

What do you want to know about Sonal Heights?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sonal Heights has moved

  1. 30 October 2020

    Completion date given when the project was registered

  2. 30 October 2021

    Extended at the builder's request (MahaRERA application EXT51800006284)

    Reason the builder gave MahaRERA:
    “Due to COVID-19 the construction activities came to be on stands still and further approvals were delayed resulting into the delay in the project. We have been granted the further approval by slum rehabilitation authority by 28/07/2020 copy…” Read the full reason“Due to COVID-19 the construction activities came to be on stands still and further approvals were delayed resulting into the delay in the project. We have been granted the further approval by slum rehabilitation authority by 28/07/2020 copy enclosed to complete the work. Since this have been a slum rehabilitation project and the members were passed in the year 2019 by the slum authority and thereafter the permission for further construction were granted only on 14/08/2020 requiring extension.”
  3. 30 April 2023

    Extended at the builder's request (MahaRERA application EXT51800011836)

    Reason the builder gave MahaRERA:
    “THIS IS THE SRA PROJECT. ON ACCOUNT OF INCREASE IN THE TENANTS AS PER THEIR ELIGIBILITY IOA & LOI IS TO BE RENEWED WHICH WAS RENEWED ONLY IN AUGUST 2020 INCREASING THE NUMBER OF FLOORS UPTO 16TH FLOOR AND WE HAVE COMPLETED. WE HAVE COMPLETE…” Read the full reason“THIS IS THE SRA PROJECT. ON ACCOUNT OF INCREASE IN THE TENANTS AS PER THEIR ELIGIBILITY IOA & LOI IS TO BE RENEWED WHICH WAS RENEWED ONLY IN AUGUST 2020 INCREASING THE NUMBER OF FLOORS UPTO 16TH FLOOR AND WE HAVE COMPLETED. WE HAVE COMPLETED THE 90 PERCENT WORK OF THE BUILDING PROJECT AND NEED TIME TO COMPLETE THE 100 PERCENT WORK AND TO OBTAIN THE OCCUPANCY CERTIFICATE. THEREFORE THIS EXTENSION.”
  4. 30 April 2024

    Extended at the builder's request (MahaRERA application EXT51800017220)

    Reason the builder gave MahaRERA:
    “Although, we have completed 100% work of the building project and have obtained the full occupancy certificate from Slum Rehabilitation Authority dated 04/07/2023 for rehab Wing-B and Part Occupancy Certificate for Wing-A comprising of Grou…” Read the full reason“Although, we have completed 100% work of the building project and have obtained the full occupancy certificate from Slum Rehabilitation Authority dated 04/07/2023 for rehab Wing-B and Part Occupancy Certificate for Wing-A comprising of Ground plus 12 Upper Floors as per the procedure including water and electricity connection and the complete and final occupancy certificate is expected to be issued in a short time. It is therefore prayed that the extension may be granted.”
  5. 30 April 2025

    Extended at the builder's request (MahaRERA application EXT51800019811)

    Reason the builder gave MahaRERA:
    “We have completed 100% construction work of both the buildings comprising A & B Wing and received Part Occupancy Certificate for A Wing upto 12th Floor and Full Occupancy Certificate for B Wing. After handing over to B Wing Rehab people, we…” Read the full reason“We have completed 100% construction work of both the buildings comprising A & B Wing and received Part Occupancy Certificate for A Wing upto 12th Floor and Full Occupancy Certificate for B Wing. After handing over to B Wing Rehab people, we are required to handover the plot area gone into the road to government authority thereafter we will get the remaining Occupancy Certificate for 13th floor to 16th floor of A Wing.”

Source: Sonal Heights’s extension records on MahaRERA (P51800008992), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sonal Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800008992
Status
Lapsed (registration period ended)
Builder
SONAL DEV-CON PVT LTD
Location
Nehru Nagar, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
October 2020
Latest completion date
April 2025
Delay so far
54 months
Homes
126
Sold or booked
53%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Sonal Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SONAL HEIGHTS-A AND B WING0%100%100%75%

Commencement certificate (CC), as filed on MahaRERA

  • SONAL HEIGHTS-A AND B WING: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sonal Heights every 1–2 months.

Sonal Heights: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK281 – 618107
Shops42 – 23915
2 BHK61815
Other222 – 2814

The builder’s record and reviews

Sonal Dev-con has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 26 months); 1 still being built, 1 past the promised date (typically 86 months late). No complaints on MahaRERA.

Read Google reviews of Sonal Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sonal Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sonal Heights

What is the possession date of Sonal Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sonal Heights in Nehru Nagar, Mumbai is 30 April 2025 — 54 months later than 30 October 2020, the date given at registration. That date has already passed.

The date has already moved 54 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sonal Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sonal Heights's builder has filed on MahaRERA, the official one, is 30 April 2025, already 54 months later than the 30 October 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sonal Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights's builder applied to MahaRERA to extend the completion date 4 times: to 30 October 2021, giving the reason "Due to COVID-19 the construction activities came to be on stands still and further approvals were delayed resulting into the delay in the project. We have been granted the further approval by slum rehabilitation authority by 28/07/2020 copy enclosed to complete the work. Since this have been a slum rehabilitation project and the members were passed in the year 2019 by the slum authority and thereafter the permission for further construction were granted only on 14/08/2020 requiring extension."; to 30 April 2023, giving the reason "THIS IS THE SRA PROJECT. ON ACCOUNT OF INCREASE IN THE TENANTS AS PER THEIR ELIGIBILITY IOA & LOI IS TO BE RENEWED WHICH WAS RENEWED ONLY IN AUGUST 2020 INCREASING THE NUMBER OF FLOORS UPTO 16TH FLOOR AND WE HAVE COMPLETED. WE HAVE COMPLETED THE 90 PERCENT WORK OF THE BUILDING PROJECT AND NEED TIME TO COMPLETE THE 100 PERCENT WORK AND TO OBTAIN THE OCCUPANCY CERTIFICATE. THEREFORE THIS EXTENSION."; to 30 April 2024, giving the reason "Although, we have completed 100% work of the building project and have obtained the full occupancy certificate from Slum Rehabilitation Authority dated 04/07/2023 for rehab Wing-B and Part Occupancy Certificate for Wing-A comprising of Ground plus 12 Upper Floors as per the procedure including water and electricity connection and the complete and final occupancy certificate is expected to be issued in a short time. It is therefore prayed that the extension may be granted."; to 30 April 2025, giving the reason "We have completed 100% construction work of both the buildings comprising A & B Wing and received Part Occupancy Certificate for A Wing upto 12th Floor and Full Occupancy Certificate for B Wing. After handing over to B Wing Rehab people, we are required to handover the plot area gone into the road to government authority thereafter we will get the remaining Occupancy Certificate for 13th floor to 16th floor of A Wing.".

What is the RERA number of Sonal Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sonal Heights in Nehru Nagar, Mumbai is P51800008992.

Is Sonal Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights is registered as P51800008992 and its status is "Lapsed (registration period ended)".

What is the current construction status of Sonal Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SONAL HEIGHTS-A AND B WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Sonal Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sonal Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights is registered on MahaRERA as P51800008992, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sonal Heights?

Sonal Heights isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Sonal Heights are 222 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sonal Heights?

For a flat in Sonal Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Sonal Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 April 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Sonal Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 April 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Sonal Heights a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights is a redevelopment: 81 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Sonal Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sonal Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sonal Heights's possession date changes?

The latest dates are on Sonal Heights's MahaRERA page (P51800008992). GharKundli's Kundli Watch sends a free WhatsApp update on Sonal Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sonal Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights has one building filed: SONAL HEIGHTS-A AND B WING with 18 floors and 141 units.

What are the flat sizes (carpet area) in Sonal Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Sonal Heights: 1 BHK: 281 to 618 sq ft carpet (107 homes); 2 BHK: 618 sq ft carpet (15 homes); Other: 222 to 281 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Sonal Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights stands on 1,431 sq m of land (about 0.4 acres), with 5,118 sq m of sanctioned built-up area.

What is the track record of Sonal Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Dev-con has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 26 months); 1 still being built, 1 past the promised date (typically 86 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Sonal Heights?

Google Maps has reviews of Sonal Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sonal Heights?

Sonal Heights by SONAL DEV-CON PVT LTD is in Nehru Nagar, Mumbai, pincode 400024 (near Kurla, Bhandup West, Chembur), Maharashtra, and is registered on MahaRERA as P51800008992, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 6 PT. GharKundli lists all 85 MahaRERA projects in Kurla East (400024).

How many flats are in Sonal Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights has 126 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.

When was Sonal Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sonal Heights was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Does Sonal Heights have any legal issues or court cases?

No court cases are listed for Sonal Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sonal Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SONAL DEV-CON PVT LTD, which has 2 other projects registered on MahaRERA.

Other projects in Kurla East (400024)

All 85 projects in Kurla East (400024) →

Other projects by SONAL DEV-CON PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.