by SANTOSH NARAYAN SINGH THAKUR · Tilaknagar S.O (Thane), ThaneAlso near Vishnunagar, Manpada

Possession date of SHREEPATI RESIDENCY: 30 January 2027, moved from 31 December 2018 (93 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700008385, and currently active. Its completion date has moved from December 2018 to January 2027: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHREEPATI RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHREEPATI RESIDENCY has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT51700001057)

    Reason the builder gave MahaRERA:
    “On account of low demand & slow down in Real Estate Sector because of Demonetization and GST , there is delay in completion of Project. It is expected that Project would get completed by Sept 2019 and Occupancy Certificate shall be obtained…” Read the full reason“On account of low demand & slow down in Real Estate Sector because of Demonetization and GST , there is delay in completion of Project. It is expected that Project would get completed by Sept 2019 and Occupancy Certificate shall be obtained before 31st December 2019. Kindly, therefore , grant extension till 31st December , 2019.”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51700011316)

    Reason the builder gave MahaRERA: “CONSTRUCTION WORK IS ALMOST COMPLETE AND ARCHITECT WILL SUBMIT APPLICATION FOR COMPLETION CERTIFICATE IN DUE COURSE. THE DELAY WAS ON ACCOUNT OF SLOW DOWN IN REAL ESTATE SECTOR ACROSS”
  4. 30 September 2026

    Extended at the builder's request (MahaRERA application EXT51700027226)

    Reason the builder gave MahaRERA:
    “Reason for Extension: The project construction work has been completed up to approximately 98%, and only minor finishing and compliance-related works remain to be completed for obtaining the Occupancy Certificate (OC) from the competent aut…” Read the full reason“Reason for Extension: The project construction work has been completed up to approximately 98%, and only minor finishing and compliance-related works remain to be completed for obtaining the Occupancy Certificate (OC) from the competent authority. Therefore, we request an extension of the project registration up to 30.09.2026, which includes buffer time required for completing statutory procedures and issuance of the OC.”
  5. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SHREEPATI RESIDENCY’s extension records on MahaRERA (P51700008385), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHREEPATI RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 1 court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700008385
Status
Registered and active
Builder
SANTOSH NARAYAN SINGH THAKUR
Location
Tilaknagar S.O (Thane), Thane · 421201
Project type
Residential / Group Housing
Registered on
18 Aug 2017
Completion date at registration
December 2018
Latest completion date
January 2027
Delay so far
93 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
129
Towers
2
Complaints on MahaRERA
7
Court cases listed
1
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of SHREEPATI RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHREEPATI RESIDENCY C100%100%100%98%
SHREEPATI RESIDENCY B2100%100%100%98%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREEPATI RESIDENCY every month.

SHREEPATI RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHREEPATI RESIDENCY C (20 floors) · SHREEPATI RESIDENCY B2 (19 floors)
  • Land: 8,070 sq m (about 2.0 acres) · sanctioned built-up 6,901 sq m
  • Boundaries filed include: JIGNYASA SOCIETY, SHIVNATH SOCIETY, DESAI KHIDKALI ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHREEPATI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHREEPATI RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHREEPATI RESIDENCY

What is the possession date of SHREEPATI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREEPATI RESIDENCY in Tilaknagar S.O (Thane), Thane is 30 January 2027 — 93 months later than 31 December 2018, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SHREEPATI RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREEPATI RESIDENCY's builder has filed on MahaRERA, the official one, is 30 January 2027, already 93 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHREEPATI RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2019, giving the reason "On account of low demand & slow down in Real Estate Sector because of Demonetization and GST , there is delay in completion of Project. It is expected that Project would get completed by Sept 2019 and Occupancy Certificate shall be obtained before 31st December 2019. Kindly, therefore , grant extension till 31st December , 2019."; to 31 December 2022, giving the reason "CONSTRUCTION WORK IS ALMOST COMPLETE AND ARCHITECT WILL SUBMIT APPLICATION FOR COMPLETION CERTIFICATE IN DUE COURSE. THE DELAY WAS ON ACCOUNT OF SLOW DOWN IN REAL ESTATE SECTOR ACROSS"; to 30 September 2026, giving the reason "Reason for Extension: The project construction work has been completed up to approximately 98%, and only minor finishing and compliance-related works remain to be completed for obtaining the Occupancy Certificate (OC) from the competent authority. Therefore, we request an extension of the project registration up to 30.09.2026, which includes buffer time required for completing statutory procedures and issuance of the OC.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SHREEPATI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREEPATI RESIDENCY in Tilaknagar S.O (Thane), Thane is P51700008385.

Is SHREEPATI RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY is registered as P51700008385 and its status is "Registered and active".

What is the construction status of SHREEPATI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does SHREEPATI RESIDENCY have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHREEPATI RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY is registered on MahaRERA as P51700008385, its completion date has moved 93 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHREEPATI RESIDENCY's possession date changes?

The latest dates are on SHREEPATI RESIDENCY's MahaRERA page (P51700008385). GharKundli's Kundli Watch sends a free WhatsApp update on SHREEPATI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHREEPATI RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY has 2 buildings filed: SHREEPATI RESIDENCY C with 20 floors; SHREEPATI RESIDENCY B2 with 19 floors.

How big is the land of SHREEPATI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY stands on 8,070 sq m of land (about 2.0 acres), with 6,901 sq m of sanctioned built-up area.

Where can I read reviews of SHREEPATI RESIDENCY?

Google Maps has reviews of SHREEPATI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHREEPATI RESIDENCY?

SHREEPATI RESIDENCY by SANTOSH NARAYAN SINGH THAKUR is in Tilaknagar S.O (Thane), Thane (pincode 421201), near Vishnunagar, Manpada, Maharashtra, and is registered on MahaRERA as P51700008385, per GharKundli's check of MahaRERA records. Its boundaries filed there include JIGNYASA SOCIETY, SHIVNATH SOCIETY, DESAI KHIDKALI ROAD.

How many homes are in SHREEPATI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY has 129 homes in 2 towers registered on MahaRERA.

When was SHREEPATI RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHREEPATI RESIDENCY was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHREEPATI RESIDENCY?

1 court case is listed for SHREEPATI RESIDENCY on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SHREEPATI RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SANTOSH NARAYAN SINGH THAKUR.

All projects with possession due in 2027 in Thane →

Other projects in pincode 421201

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.