vedantnakshatra L phase 3
by MOHAN HARDASMAL THARWANI · Badlapur, Thane 421503Also near Kulgaon
What’s in the report? →Possession date of vedantnakshatra L phase 3 (MahaRERA P51700008415): 31 December 2027, moved from 30 November 2023 (45 months later). It has 68 homes, 54% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700008415, and currently active. Its completion date has moved from November 2023 to December 2027: 45 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700008415, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about vedantnakshatra L phase 3?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of vedantnakshatra L phase 3 has moved
30 November 2023
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT51700017722)
Reason the builder gave MahaRERA: “I have registered the project in 2017 but no construction have been started till date and there is no bookings in the project”
31 August 2027
Extended at the builder's request (MahaRERA application EXT51700027111)
Reason the builder gave MahaRERA: “Now the construction have been started and it will take 2 to 3 years approximately to complete the same and there is no booking in the project”
31 December 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: vedantnakshatra L phase 3’s extension records on MahaRERA (P51700008415), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on vedantnakshatra L phase 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700008415
- Status
- Registered and active
- Builder
- MOHAN HARDASMAL THARWANI
- Location
- Badlapur, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- November 2023
- Latest completion date
- December 2027
- Delay so far
- 45 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 68
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 18
Construction progress of vedantnakshatra L phase 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING L | 100% | 72% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING L: covers Parking Floor +Seventeen Floors
Latest CC order on MahaRERA: dated 18/09/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on vedantnakshatra L phase 3 every 1–2 months.
vedantnakshatra L phase 3: buildings, flats and land, as filed on MahaRERA
- Buildings: WING L (18 floors, 68 units)
- Car parking: 25 covered
- Land: 2,705 sq m (about 0.7 acres) · sanctioned built-up 5,186 sq m · recreational space 1,558 sq m
- Land, as filed: S NO 70/1/2 AND S NO 70/5/B
- Map: Get directions
The builder’s record and reviews
Mohan Hardasmal Tharwani has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 11 finished, 7 within the promised date and 4 needed more time (typically 2 months); 8 still being built, 1 past the promised date (typically 19 months late). 8 complaints on MahaRERA across 5 projects.
Read Google reviews of vedantnakshatra L phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
vedantnakshatra L phase 3: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about vedantnakshatra L phase 3
What is the possession date of vedantnakshatra L phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for vedantnakshatra L phase 3 in Badlapur, Thane is 31 December 2027 — 45 months later than 30 November 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 45 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for vedantnakshatra L phase 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date vedantnakshatra L phase 3's builder has filed on MahaRERA, the official one, is 31 December 2027, already 45 months later than the 30 November 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of vedantnakshatra L phase 3 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2026, giving the reason "I have registered the project in 2017 but no construction have been started till date and there is no bookings in the project"; to 31 August 2027, giving the reason "Now the construction have been started and it will take 2 to 3 years approximately to complete the same and there is no booking in the project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of vedantnakshatra L phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of vedantnakshatra L phase 3 in Badlapur, Thane is P51700008415.
Is vedantnakshatra L phase 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 is registered as P51700008415 and its status is "Registered and active".
What is the current construction status of vedantnakshatra L phase 3? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING L is 72% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does vedantnakshatra L phase 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is vedantnakshatra L phase 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 is registered on MahaRERA as P51700008415, its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in vedantnakshatra L phase 3?
vedantnakshatra L phase 3 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in vedantnakshatra L phase 3?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in vedantnakshatra L phase 3: gharkundli.com/tools/property-cost-calculator
Has vedantnakshatra L phase 3 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has vedantnakshatra L phase 3 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for vedantnakshatra L phase 3 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if vedantnakshatra L phase 3's possession date changes?
The latest dates are on vedantnakshatra L phase 3's MahaRERA page (P51700008415). GharKundli's Kundli Watch sends a free WhatsApp update on vedantnakshatra L phase 3 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does vedantnakshatra L phase 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 has one building filed: WING L with 18 floors and 68 units.
How much parking does vedantnakshatra L phase 3 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 25 covered car parking spaces for vedantnakshatra L phase 3.
How big is the land of vedantnakshatra L phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 stands on 2,705 sq m of land (about 0.7 acres), with 5,186 sq m of sanctioned built-up area and 1,558 sq m of recreational open space.
What is the track record of vedantnakshatra L phase 3's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Hardasmal Tharwani has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 11 finished, 7 within the promised date and 4 needed more time (typically 2 months); 8 still being built, 1 past the promised date (typically 19 months late). 8 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of vedantnakshatra L phase 3?
Google Maps has reviews of vedantnakshatra L phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of vedantnakshatra L phase 3?
vedantnakshatra L phase 3 by MOHAN HARDASMAL THARWANI is in Badlapur, Thane, pincode 421503 (near Kulgaon), Maharashtra, and is registered on MahaRERA as P51700008415, per GharKundli's check of MahaRERA records. Its land is filed as S NO 70/1/2 AND S NO 70/5/B. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in vedantnakshatra L phase 3, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 has 68 homes in 1 tower registered on MahaRERA, and 54% of them are sold or booked.
When was vedantnakshatra L phase 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Does vedantnakshatra L phase 3 have any legal issues or court cases?
No court cases are listed for vedantnakshatra L phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of vedantnakshatra L phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOHAN HARDASMAL THARWANI, which has 18 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of vedantnakshatra L phase 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kulgaon (421503)
- Sai Universe
- Mery Villa CHSL
- Mahavir Heritage
- Infinity Meadows
- Gokul Heights
- Shiv Tirth B Wing
- Prabhu Darshan Co-operative Housing Society Limited
- Dattatray Residency
Other projects by MOHAN HARDASMAL THARWANI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.