vedantnakshatra L phase 3

by MOHAN HARDASMAL THARWANI · Badlapur, Thane

Registered on MahaRERA under P51700008415, and currently active. Its completion date has moved from November 2023 to December 2027, 49 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on vedantnakshatra L phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700008415
Status
Registered and active
Builder
MOHAN HARDASMAL THARWANI
Location
Badlapur, Thane · 421503
Project type
Residential / Group Housing
Registered on
18 Aug 2017
Completion date at registration
November 2023
Latest completion date
December 2027
Delay so far
49 months
Homes
68
Sold or booked
54%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
18

Kundli Watch

vedantnakshatra L phase 3: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about vedantnakshatra L phase 3

Is vedantnakshatra L phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 is registered as P51700008415 and its status is "Registered and active".

Where is vedantnakshatra L phase 3?

vedantnakshatra L phase 3 by MOHAN HARDASMAL THARWANI is in Badlapur, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700008415, per GharKundli's check of MahaRERA records.

When is possession of vedantnakshatra L phase 3 due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for vedantnakshatra L phase 3 in Badlapur, Thane is 31 December 2027 — 49 months later than 30 November 2023, the date given at registration.

Does vedantnakshatra L phase 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of vedantnakshatra L phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOHAN HARDASMAL THARWANI, which has 18 other projects registered on MahaRERA.

Other projects in pincode 421503

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.