vedantnakshatra L phase 3
by MOHAN HARDASMAL THARWANI · Badlapur, Thane
Registered on MahaRERA under P51700008415, and currently active. Its completion date has moved from November 2023 to December 2027, 49 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on vedantnakshatra L phase 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700008415
- Status
- Registered and active
- Builder
- MOHAN HARDASMAL THARWANI
- Location
- Badlapur, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- November 2023
- Latest completion date
- December 2027
- Delay so far
- 49 months
- Homes
- 68
- Sold or booked
- 54%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 18
Kundli Watch
vedantnakshatra L phase 3: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about vedantnakshatra L phase 3
Is vedantnakshatra L phase 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), vedantnakshatra L phase 3 is registered as P51700008415 and its status is "Registered and active".
Where is vedantnakshatra L phase 3?
vedantnakshatra L phase 3 by MOHAN HARDASMAL THARWANI is in Badlapur, Thane (pincode 421503), Maharashtra, and is registered on MahaRERA as P51700008415, per GharKundli's check of MahaRERA records.
When is possession of vedantnakshatra L phase 3 due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for vedantnakshatra L phase 3 in Badlapur, Thane is 31 December 2027 — 49 months later than 30 November 2023, the date given at registration.
Does vedantnakshatra L phase 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of vedantnakshatra L phase 3?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOHAN HARDASMAL THARWANI, which has 18 other projects registered on MahaRERA.
Other projects in pincode 421503
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.