Vedant Millenia Happiness Phase II Wing E
by MOHAN HARDASMAL THARWANI · Titwala East, ThaneAlso near Manda
Possession date of Vedant Millenia Happiness Phase II Wing E: 31 December 2029, moved from 31 December 2026 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700047571, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Vedant Millenia Happiness Phase II Wing E?
How the possession date of Vedant Millenia Happiness Phase II Wing E has moved
31 December 2026
Completion date given when the project was registered
31 December 2029
Extended at the builder's request (MahaRERA application EA06022619752)
Reason the builder gave MahaRERA: “now the construction have been started and it will take 3 to 4 years approximately to complete the same”
Source: Vedant Millenia Happiness Phase II Wing E’s extension records on MahaRERA (P51700047571), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vedant Millenia Happiness Phase II Wing E
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- VEDANT MILLENIA HAPPINESS PHASE II WING AP51700018689 · possession 28 Feb 2023
- VEDANT MILLENIA HAPPINESS PHASE II WING BP51700030699 · possession 15 Dec 2025
- Vedant Millenia happiness Phase II Wing CP51700050205 · possession 30 Apr 2028
- Vedant Millenia Happiness Phase II Wing DP51700055377 · possession 31 Jul 2028
- MahaRERA registration
- P51700047571
- Status
- Registered and active
- Builder
- MOHAN HARDASMAL THARWANI
- Location
- Titwala East, Thane · 421605
- Project type
- Residential / Group Housing
- Registered on
- 9 Nov 2022
- Completion date at registration
- December 2026
- Latest completion date
- December 2029
- Delay so far
- 36 months
- Homes
- 55
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 18
Construction progress of Vedant Millenia Happiness Phase II Wing E, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vedant Millenia Happiness Phase II Wing E | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Vedant Millenia Happiness Phase II Wing E: covers Stilt + 7 Floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vedant Millenia Happiness Phase II Wing E every month.
Vedant Millenia Happiness Phase II Wing E: buildings, flats and land, as filed on MahaRERA
- Buildings: Vedant Millenia Happiness Phase II Wing E (8 floors, 55 units)
- Land: 858 sq m (about 0.2 acres) · sanctioned built-up 791 sq m · recreational space 858 sq m
The builder’s record and reviews
Mohan Hardasmal Tharwani has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 11 finished, 7 within the promised date and 4 needed more time (typically 2 months); 8 still being built, 1 past the promised date (typically 19 months late). 8 complaints on MahaRERA across 5 projects.
Read Google reviews of Vedant Millenia Happiness Phase II Wing E →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vedant Millenia Happiness Phase II Wing E: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vedant Millenia Happiness Phase II Wing E
What is the possession date of Vedant Millenia Happiness Phase II Wing E?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vedant Millenia Happiness Phase II Wing E in Titwala East, Thane is 31 December 2029 — 36 months later than 31 December 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Vedant Millenia Happiness Phase II Wing E?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vedant Millenia Happiness Phase II Wing E's builder has filed on MahaRERA, the official one, is 31 December 2029, already 36 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vedant Millenia Happiness Phase II Wing E extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "now the construction have been started and it will take 3 to 4 years approximately to complete the same".
What is the RERA number of Vedant Millenia Happiness Phase II Wing E?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vedant Millenia Happiness Phase II Wing E in Titwala East, Thane is P51700047571.
Is Vedant Millenia Happiness Phase II Wing E registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E is registered as P51700047571 and its status is "Registered and active".
What is the construction status of Vedant Millenia Happiness Phase II Wing E?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Vedant Millenia Happiness Phase II Wing E is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Vedant Millenia Happiness Phase II Wing E have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Vedant Millenia Happiness Phase II Wing E safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E is registered on MahaRERA as P51700047571, its completion date has moved 36 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Vedant Millenia Happiness Phase II Wing E have other wings or phases?
Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: VEDANT MILLENIA HAPPINESS PHASE II WING A (P51700018689, possession 28 Feb 2023); VEDANT MILLENIA HAPPINESS PHASE II WING B (P51700030699, possession 15 Dec 2025); Vedant Millenia happiness Phase II Wing C (P51700050205, possession 30 Apr 2028); Vedant Millenia Happiness Phase II Wing D (P51700055377, possession 31 Jul 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Vedant Millenia Happiness Phase II Wing E's possession date changes?
The latest dates are on Vedant Millenia Happiness Phase II Wing E's MahaRERA page (P51700047571). GharKundli's Kundli Watch sends a free WhatsApp update on Vedant Millenia Happiness Phase II Wing E every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vedant Millenia Happiness Phase II Wing E have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E has one building filed: Vedant Millenia Happiness Phase II Wing E with 8 floors and 55 units.
How big is the land of Vedant Millenia Happiness Phase II Wing E?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E stands on 858 sq m of land (about 0.2 acres), with 791 sq m of sanctioned built-up area and 858 sq m of recreational open space.
What is the track record of Vedant Millenia Happiness Phase II Wing E's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Mohan Hardasmal Tharwani has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 11 finished, 7 within the promised date and 4 needed more time (typically 2 months); 8 still being built, 1 past the promised date (typically 19 months late). 8 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vedant Millenia Happiness Phase II Wing E?
Google Maps has reviews of Vedant Millenia Happiness Phase II Wing E written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vedant Millenia Happiness Phase II Wing E?
Vedant Millenia Happiness Phase II Wing E by MOHAN HARDASMAL THARWANI is in Titwala East, Thane (pincode 421605), near Manda, Maharashtra, and is registered on MahaRERA as P51700047571, per GharKundli's check of MahaRERA records.
How many homes are in Vedant Millenia Happiness Phase II Wing E?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E has 55 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Vedant Millenia Happiness Phase II Wing E registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vedant Millenia Happiness Phase II Wing E was registered on MahaRERA on 9 November 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Vedant Millenia Happiness Phase II Wing E?
No court cases are listed for Vedant Millenia Happiness Phase II Wing E on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Vedant Millenia Happiness Phase II Wing E?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MOHAN HARDASMAL THARWANI, which has 18 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vedant Millenia Happiness Phase II Wing E
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 421605
- CHARMS CITY PHASE II
- MARATHE TOWER
- GANPATI HEIGHTS
- SHREE GAJANAN PLAZA
- SARNOBAT RESIDENCY
- PITAMBARE TOWER
- MANGALMURTI HEIGHTS
- SAI VRINDAVAN
Other projects by MOHAN HARDASMAL THARWANI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.