SANKALP SIDDHI
by SANKALP DEVELOPERS · ThaneAlso near Naupada, Majiwada, Badlapur
Possession date of SANKALP SIDDHI: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700008438, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SANKALP SIDDHI?
How the possession date of SANKALP SIDDHI has moved
30 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SANKALP SIDDHI’s extension records on MahaRERA (P51700008438), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SANKALP SIDDHI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700008438
- Status
- Registered and active
- Builder
- SANKALP DEVELOPERS
- Location
- Thane · 400601
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 46
- Sold or booked
- 90%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 16
Construction progress of SANKALP SIDDHI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SANKALP SIDDHI | 100% | 70% | 70% | 50% |
Commencement certificate (CC), as filed on MahaRERA
- SANKALP SIDDHI: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SANKALP SIDDHI every month.
SANKALP SIDDHI: buildings, flats and land, as filed on MahaRERA
- Buildings: SANKALP SIDDHI (14 floors, 53 units)
- Land: 1,750 sq m (about 0.4 acres) · sanctioned built-up 5,251 sq m · recreational space 144 sq m
- Boundaries filed include: KHOPAT ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SANKALP SIDDHI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SANKALP SIDDHI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SANKALP SIDDHI
What is the possession date of SANKALP SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SANKALP SIDDHI in Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SANKALP SIDDHI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SANKALP SIDDHI's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SANKALP SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SANKALP SIDDHI in Thane is P51700008438.
Is SANKALP SIDDHI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI is registered as P51700008438 and its status is "Registered and active".
What is the construction status of SANKALP SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SANKALP SIDDHI is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does SANKALP SIDDHI have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SANKALP SIDDHI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI is registered on MahaRERA as P51700008438, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SANKALP SIDDHI's possession date changes?
The latest dates are on SANKALP SIDDHI's MahaRERA page (P51700008438). GharKundli's Kundli Watch sends a free WhatsApp update on SANKALP SIDDHI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SANKALP SIDDHI have?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI has one building filed: SANKALP SIDDHI with 14 floors and 53 units.
How big is the land of SANKALP SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI stands on 1,750 sq m of land (about 0.4 acres), with 5,251 sq m of sanctioned built-up area and 144 sq m of recreational open space.
Where can I read reviews of SANKALP SIDDHI?
Google Maps has reviews of SANKALP SIDDHI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SANKALP SIDDHI?
SANKALP SIDDHI by SANKALP DEVELOPERS is in Thane (pincode 400601), near Naupada, Majiwada, Badlapur, Maharashtra, and is registered on MahaRERA as P51700008438, per GharKundli's check of MahaRERA records. Its boundaries filed there include KHOPAT ROAD.
How many homes are in SANKALP SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI has 46 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.
When was SANKALP SIDDHI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SANKALP SIDDHI was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SANKALP SIDDHI?
1 court case is listed for SANKALP SIDDHI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SANKALP SIDDHI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANKALP DEVELOPERS, which has 16 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SANKALP SIDDHI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 400601
- RAJ TATTVA PHASE 1 COMMERCIAL
- Phatak Wada
- URMILA CO-OPERATIVE HOUSING SOCIETY LTD
- SHRIKRISHNA RESIDENCY COOPERATIVE HOUSING SOCIETY LIMITED
- NAV SULOCHANA CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE GANGADHAR CHSL
- Panache
- Devshrushti Co-op. Hsg Soc. Ltd
Other projects by SANKALP DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.