Sai Orchid Phase 1

by gupta builders and developers (Proviso) · Dombivali East, ThaneAlso near Shankara Nagar

Possession date of Sai Orchid Phase 1: 30 June 2024, moved from 30 June 2021 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700004806. Status: Lapsed (registration period ended). 17 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about Sai Orchid Phase 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Orchid Phase 1 has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT51700009784)

    Reason the builder gave MahaRERA:
    “Project construction was going on smoothly but due to some roadblocks like 'stay order', lockdown, etc the project execution was affected & hence causing delay. But the project is on the verge of completion & will be definitely over within…” Read the full reason“Project construction was going on smoothly but due to some roadblocks like 'stay order', lockdown, etc the project execution was affected & hence causing delay. But the project is on the verge of completion & will be definitely over within this extension of 6 Months.”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51700013637)

    Reason the builder gave MahaRERA: “project is completed but OC is not received due to certain issues. please go through the letter & annexures attached below”

Source: Sai Orchid Phase 1’s extension records on MahaRERA (P51700004806), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Orchid Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 17 complaints and 2 court cases, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700004806
Status
Lapsed (registration period ended)
Builder
gupta builders and developers
Location
Dombivali East, Thane · 421201
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
June 2024
Delay so far
36 months
Homes
239
Towers
8
Complaints on MahaRERA
17
Court cases listed
2
Appeals at the tribunal
4
Title report on file
Not found

Construction progress of Sai Orchid Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A1100%100%100%100%
A2100%100%100%100%
B1100%100%100%100%
B2100%100%100%100%
C1100%100%100%100%
C2100%100%100%100%
D1100%100%100%100%
D2100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Orchid Phase 1 every month.

Sai Orchid Phase 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: A1 (10 floors) · A2 (11 floors) · B1 (12 floors) · B2 (12 floors) · C1 (10 floors) · C2 (10 floors) · D1 (9 floors) · D2 (9 floors)
  • Land: 8,487 sq m (about 2.1 acres) · sanctioned built-up 9,500 sq m · recreational space 900 sq m
  • Boundaries filed include: 6m Wide Village Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

SAI Proviso Developers (a group of 7 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 10 months); 11 still being built, 2 past the promised date (typically 27 months late); 1 lapsed. 85 complaints on MahaRERA across 8 projects.

Read Google reviews of Sai Orchid Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Orchid Phase 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Orchid Phase 1

What is the possession date of Sai Orchid Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Orchid Phase 1 in Dombivali East, Thane is 30 June 2024 — 36 months later than 30 June 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sai Orchid Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Orchid Phase 1's builder has filed on MahaRERA, the official one, is 30 June 2024, already 36 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sai Orchid Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "Project construction was going on smoothly but due to some roadblocks like 'stay order', lockdown, etc the project execution was affected & hence causing delay. But the project is on the verge of completion & will be definitely over within this extension of 6 Months."; to 30 June 2024, giving the reason "project is completed but OC is not received due to certain issues. please go through the letter & annexures attached below".

What is the RERA number of Sai Orchid Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Orchid Phase 1 in Dombivali East, Thane is P51700004806.

Is Sai Orchid Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1 is registered as P51700004806 and its status is "Lapsed (registration period ended)".

What is the construction status of Sai Orchid Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does Sai Orchid Phase 1 have complaints on MahaRERA?

17 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sai Orchid Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1 is registered on MahaRERA as P51700004806, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 17 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Orchid Phase 1's possession date changes?

The latest dates are on Sai Orchid Phase 1's MahaRERA page (P51700004806). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Orchid Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Orchid Phase 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1 has 8 buildings filed: A1 with 10 floors; A2 with 11 floors; B1 with 12 floors; B2 with 12 floors; C1 with 10 floors; C2 with 10 floors; and 2 more.

How big is the land of Sai Orchid Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1 stands on 8,487 sq m of land (about 2.1 acres), with 9,500 sq m of sanctioned built-up area and 900 sq m of recreational open space.

What is the track record of Sai Orchid Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI Proviso Developers (a group of 7 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 10 months); 11 still being built, 2 past the promised date (typically 27 months late); 1 lapsed. 85 complaints on MahaRERA across 8 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sai Orchid Phase 1?

Google Maps has reviews of Sai Orchid Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 17 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Orchid Phase 1?

Sai Orchid Phase 1 by gupta builders and developers (Proviso) is in Dombivali East, Thane (pincode 421201), near Shankara Nagar, Maharashtra, and is registered on MahaRERA as P51700004806, per GharKundli's check of MahaRERA records. Its boundaries filed there include 6m Wide Village Road.

How many homes are in Sai Orchid Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1 has 239 homes in 8 towers registered on MahaRERA.

When was Sai Orchid Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Orchid Phase 1 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Orchid Phase 1?

2 court cases are listed for Sai Orchid Phase 1 on MahaRERA, and 4 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sai Orchid Phase 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is gupta builders and developers, the company Proviso files this project under.

Other projects in pincode 421201

All 408 projects in Tilaknagar (421201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.