Possession date of FALCO PEARLSHIRE: 30 April 2028, moved from 30 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011065, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about FALCO PEARLSHIRE?
How the possession date of FALCO PEARLSHIRE has moved
30 December 2022
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA01102517998)
Reason the builder gave MahaRERA: “Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2027 to complete the project”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: FALCO PEARLSHIRE’s extension records on MahaRERA (P51700011065), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on FALCO PEARLSHIRE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011065
- Status
- Registered and active
- Builder
- AANYA RESIDENCES
- Location
- Ambivli East, Thane · 421102
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2028
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 82
- Sold or booked
- 60%
- Towers
- 1
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of FALCO PEARLSHIRE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| FALCO PEARLSHIRE | 100% | 20% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- FALCO PEARLSHIRE: covers G+12 FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on FALCO PEARLSHIRE every month.
FALCO PEARLSHIRE: buildings, flats and land, as filed on MahaRERA
- Buildings: FALCO PEARLSHIRE (13 floors, 83 units)
- Land: 1,997 sq m (about 0.5 acres) · sanctioned built-up 1,996 sq m
The builder’s record and reviews
Aanya Residences (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 30 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects.
Read Google reviews of FALCO PEARLSHIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
FALCO PEARLSHIRE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about FALCO PEARLSHIRE
What is the possession date of FALCO PEARLSHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for FALCO PEARLSHIRE in Ambivli East, Thane is 30 April 2028 — 60 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for FALCO PEARLSHIRE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date FALCO PEARLSHIRE's builder has filed on MahaRERA, the official one, is 30 April 2028, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of FALCO PEARLSHIRE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2027 to complete the project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of FALCO PEARLSHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of FALCO PEARLSHIRE in Ambivli East, Thane is P51700011065.
Is FALCO PEARLSHIRE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE is registered as P51700011065 and its status is "Registered and active".
What is the construction status of FALCO PEARLSHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on FALCO PEARLSHIRE is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does FALCO PEARLSHIRE have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is FALCO PEARLSHIRE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE is registered on MahaRERA as P51700011065, its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if FALCO PEARLSHIRE's possession date changes?
The latest dates are on FALCO PEARLSHIRE's MahaRERA page (P51700011065). GharKundli's Kundli Watch sends a free WhatsApp update on FALCO PEARLSHIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does FALCO PEARLSHIRE have?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE has one building filed: FALCO PEARLSHIRE with 13 floors and 83 units.
How big is the land of FALCO PEARLSHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE stands on 1,997 sq m of land (about 0.5 acres), with 1,996 sq m of sanctioned built-up area.
What is the track record of FALCO PEARLSHIRE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aanya Residences (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 30 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of FALCO PEARLSHIRE?
Google Maps has reviews of FALCO PEARLSHIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is FALCO PEARLSHIRE?
FALCO PEARLSHIRE by AANYA RESIDENCES is in Ambivli East, Thane (pincode 421102), Maharashtra, and is registered on MahaRERA as P51700011065, per GharKundli's check of MahaRERA records.
How many homes are in FALCO PEARLSHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE has 82 homes in 1 tower registered on MahaRERA, and 60% of them are sold or booked.
When was FALCO PEARLSHIRE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), FALCO PEARLSHIRE was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on FALCO PEARLSHIRE?
No court cases are listed for FALCO PEARLSHIRE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of FALCO PEARLSHIRE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AANYA RESIDENCES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of FALCO PEARLSHIRE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Kalyan
- FALCO MARIGOLD
- MAJESTY HEIGHTS
- Royal Hills
- VIDHI IMPRESSION
- Mangeshi Dhara
- SWAMI ELITE
- Balaji Govind
- OM TRIMURTI DARSHAN
Other projects by AANYA RESIDENCES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.