by AANYA RESIDENCES · Ambivali East, Thane

Possession date of PINESHIRE: 31 December 2025, moved from 30 December 2022 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700014064. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about PINESHIRE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PINESHIRE has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700018735)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.91% allottees for purpose of extension of RERA registration period of the said project.”

Source: PINESHIRE’s extension records on MahaRERA (P51700014064), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PINESHIRE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700014064
Status
Lapsed (registration period ended)
Builder
AANYA RESIDENCES
Location
Ambivali East, Thane · 421102
Project type
Residential / Group Housing
Registered on
7 Nov 2017
Completion date at registration
December 2022
Latest completion date
December 2025
Delay so far
36 months
Homes
225
Sold or booked
51%
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of PINESHIRE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PINESHIRE100%100%15%0%

Commencement certificate (CC), as filed on MahaRERA

  • PINESHIRE: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PINESHIRE every month.

PINESHIRE: buildings, flats and land, as filed on MahaRERA

  • Buildings: PINESHIRE (20 floors, 226 units)
  • Land: 5,259 sq m (about 1.3 acres) · sanctioned built-up 4,229 sq m · recreational space 789 sq m

The builder’s record and reviews

Aanya Residences (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 30 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects.

Read Google reviews of PINESHIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PINESHIRE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PINESHIRE

What is the possession date of PINESHIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PINESHIRE in Ambivali East, Thane is 31 December 2025 — 36 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PINESHIRE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PINESHIRE's builder has filed on MahaRERA, the official one, is 31 December 2025, already 36 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PINESHIRE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE's builder applied to MahaRERA to extend the completion date once: to 31 December 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.91% allottees for purpose of extension of RERA registration period of the said project.".

What is the RERA number of PINESHIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PINESHIRE in Ambivali East, Thane is P51700014064.

Is PINESHIRE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE is registered as P51700014064 and its status is "Lapsed (registration period ended)".

What is the construction status of PINESHIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PINESHIRE is 100% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.

Does PINESHIRE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PINESHIRE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE is registered on MahaRERA as P51700014064, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PINESHIRE's possession date changes?

The latest dates are on PINESHIRE's MahaRERA page (P51700014064). GharKundli's Kundli Watch sends a free WhatsApp update on PINESHIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PINESHIRE have?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE has one building filed: PINESHIRE with 20 floors and 226 units.

How big is the land of PINESHIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE stands on 5,259 sq m of land (about 1.3 acres), with 4,229 sq m of sanctioned built-up area and 789 sq m of recreational open space.

What is the track record of PINESHIRE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aanya Residences (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 17 months); 1 still being built, 1 past the promised date (typically 30 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PINESHIRE?

Google Maps has reviews of PINESHIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PINESHIRE?

PINESHIRE by AANYA RESIDENCES is in Ambivali East, Thane (pincode 421102), Maharashtra, and is registered on MahaRERA as P51700014064, per GharKundli's check of MahaRERA records.

How many homes are in PINESHIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE has 225 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.

When was PINESHIRE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), PINESHIRE was registered on MahaRERA on 7 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PINESHIRE?

No court cases are listed for PINESHIRE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of PINESHIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AANYA RESIDENCES, which has 1 other project registered on MahaRERA.

Other projects in Kalyan

All 71 projects in Ambivali West (421102) →

Other projects by AANYA RESIDENCES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.