Mohan Suburbia IIB
by MOHAN LIFESPACES LLP · Ambernath, ThaneAlso near Wimco Naka, Netaji Bazar
Possession: Mohan Suburbia IIB is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700010658. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mohan Suburbia IIB?
How the possession date of Mohan Suburbia IIB has moved
31 March 2018
Completion date given when the project was registered
31 March 2019
Extended at the builder's request (MahaRERA application EXT51700000760)
Reason the builder gave MahaRERA:
“We have applied for Completion Certificate vide letter dated 04/04/2016 with Ambernath Municipal Council for our project Mohan Suburbia Phase IIB comprising of Building No K2 to T2 but due to certain technical difficulties Ambernath Municip…” Read the full reason
“We have applied for Completion Certificate vide letter dated 04/04/2016 with Ambernath Municipal Council for our project Mohan Suburbia Phase IIB comprising of Building No K2 to T2 but due to certain technical difficulties Ambernath Municipal Council has not yet issued the same. We have annexed copy of Inward application for completion certificate dated 04/04/2016 and our Architect's Letter dated 09/04/2018 in Form 4 as prescribed under RERA rules. We have already submitted letter dated 09/04/2018 in Form 4 in the month of April 2018 with your learned authority. We are continuously followin…”
Source: Mohan Suburbia IIB’s extension records on MahaRERA (P51700010658), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mohan Suburbia IIB
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700010658
- Status
- Completed
- Builder
- MOHAN LIFESPACES LLP
- Location
- Ambernath, Thane · 421501
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- March 2018
- Latest completion date
- March 2019
- Delay so far
- 12 months
- Homes
- 244
- Towers
- 10
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 23
Construction progress of Mohan Suburbia IIB, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| K2 Wing | 100% | 100% | 100% | 100% |
| L2 Wing | 100% | 100% | 100% | 100% |
| M2 Wing | 100% | 100% | 100% | 100% |
| N2 Wing | 100% | 100% | 100% | 100% |
| O2 Wing | 100% | 100% | 100% | 100% |
| P2 Wing | 100% | 100% | 100% | 100% |
| Q2 Wing | 100% | 100% | 100% | 100% |
| R2 Wing | 100% | 100% | 100% | 100% |
| S2 Wing | 100% | 100% | 100% | 100% |
| T2 Wing | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mohan Suburbia IIB every month.
Mohan Suburbia IIB: buildings, flats and land, as filed on MahaRERA
- Buildings: K2 Wing (9 floors) · L2 Wing (9 floors) · M2 Wing (9 floors) · N2 Wing (9 floors) · O2 Wing (9 floors) · P2 Wing (10 floors) · Q2 Wing (10 floors) · R2 Wing (10 floors) · and 2 more
- Land: 5,918 sq m (about 1.5 acres) · sanctioned built-up 12,242 sq m · recreational space 5,827 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Mohan Lifespaces (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 19 finished, 8 within the promised date and 11 needed more time (typically 12 months); 6 still being built, none past the promised date yet. 21 complaints on MahaRERA across 6 projects.
Read Google reviews of Mohan Suburbia IIB →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mohan Suburbia IIB: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mohan Suburbia IIB
What is the possession date of Mohan Suburbia IIB?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mohan Suburbia IIB in Ambernath, Thane is 31 March 2019 — 12 months later than 31 March 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mohan Suburbia IIB?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mohan Suburbia IIB's builder has filed on MahaRERA, the official one, is 31 March 2019, already 12 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mohan Suburbia IIB extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB's builder applied to MahaRERA to extend the completion date once: to 31 March 2019, giving the reason "We have applied for Completion Certificate vide letter dated 04/04/2016 with Ambernath Municipal Council for our project Mohan Suburbia Phase IIB comprising of Building No K2 to T2 but due to certain technical difficulties Ambernath Municipal Council has not yet issued the same. We have annexed copy of Inward application for completion certificate dated 04/04/2016 and our Architect's Letter dated 09/04/2018 in Form 4 as prescribed under RERA rules. We have already submitted letter dated 09/04/2018 in Form 4 in the month of April 2018 with your learned authority. We are continuously followin…".
What is the RERA number of Mohan Suburbia IIB?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mohan Suburbia IIB in Ambernath, Thane is P51700010658.
Is Mohan Suburbia IIB registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB is registered as P51700010658 and its status is "Completed".
What is the construction status of Mohan Suburbia IIB?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 10 towers. GharKundli's full report compares construction progress with the deadline.
Does Mohan Suburbia IIB have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Mohan Suburbia IIB safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB is registered on MahaRERA as P51700010658, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mohan Suburbia IIB's possession date changes?
The latest dates are on Mohan Suburbia IIB's MahaRERA page (P51700010658). GharKundli's Kundli Watch sends a free WhatsApp update on Mohan Suburbia IIB every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mohan Suburbia IIB have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB has 10 buildings filed: K2 Wing with 9 floors; L2 Wing with 9 floors; M2 Wing with 9 floors; N2 Wing with 9 floors; O2 Wing with 9 floors; P2 Wing with 10 floors; and 4 more.
How big is the land of Mohan Suburbia IIB?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB stands on 5,918 sq m of land (about 1.5 acres), with 12,242 sq m of sanctioned built-up area and 5,827 sq m of recreational open space.
What is the track record of Mohan Suburbia IIB's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Lifespaces (a group of 2 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 19 finished, 8 within the promised date and 11 needed more time (typically 12 months); 6 still being built, none past the promised date yet. 21 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Mohan Suburbia IIB?
Google Maps has reviews of Mohan Suburbia IIB written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mohan Suburbia IIB?
Mohan Suburbia IIB by MOHAN LIFESPACES LLP is in Ambernath, Thane (pincode 421501), near Wimco Naka, Netaji Bazar, Maharashtra, and is registered on MahaRERA as P51700010658, per GharKundli's check of MahaRERA records.
How many homes are in Mohan Suburbia IIB?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB has 244 homes in 10 towers registered on MahaRERA.
When was Mohan Suburbia IIB registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mohan Suburbia IIB was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Mohan Suburbia IIB?
No court cases are listed for Mohan Suburbia IIB on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Mohan Suburbia IIB?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MOHAN LIFESPACES LLP, which has 23 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mohan Suburbia IIB
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 421501
- NEELKANTH ROYALE PALMS - F WING PHASE II
- CHADHA RESIDENCY
- NEW NEELGAGAN CHS
- Mahadev Heights
- PARITOSH CO OPERATIVE HOUSING SOCIETY LIMITED
- NEXT CROWN LANDMARK
- ISHWAR JAY JAY SHANKARA CO-OP. HOUSING SOCIETY LTD.
- Panvelkar Daffodils-Plot No. 11,12,13
Other projects by MOHAN LIFESPACES LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.