ATLANTA RESIDENCY PHASE II
by SRI BALAJI DEVELOPER · Naupada, ThaneAlso near bhiwandi, Kamatghar
Possession date of ATLANTA RESIDENCY PHASE II: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700010106, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ATLANTA RESIDENCY PHASE II?
How the possession date of ATLANTA RESIDENCY PHASE II has moved
31 December 2019
Completion date given when the project was registered
30 June 2021
Extended at the builder's request (MahaRERA application EXT51700008452)
Reason the builder gave MahaRERA:
“The project is situated at Bhiwandi and owing to covid 19 entire activities of Real estate are badly affected including purchasing power of the people resulting in slow down in demand and cash flow. Real Estate is amongst the worst sector t…” Read the full reason
“The project is situated at Bhiwandi and owing to covid 19 entire activities of Real estate are badly affected including purchasing power of the people resulting in slow down in demand and cash flow. Real Estate is amongst the worst sector to be affected by covid 19. We intend to complete the project at the earliest. We also request your good selves to further extend the project automatically by six month as per maharera order for covid 19 extension once the extension is allowed for one year upto 30th december , 2020. Kindly allow the extension for one year and thereafter for six month as pe…”31 December 2024
Extended at the builder's request (MahaRERA application EXT51700011216)
Reason the builder gave MahaRERA:
“The Project is situated at remote place away from Thane city in Bhiwandi. The outbreak of covid has affected the purchasing power of the people and even construction activities were halted owing to migration of labour since March 2021. We h…” Read the full reason
“The Project is situated at remote place away from Thane city in Bhiwandi. The outbreak of covid has affected the purchasing power of the people and even construction activities were halted owing to migration of labour since March 2021. We have discussed with all the customers about project extension till 31st December, 2024 and majority of them have considered our request and granted us unconditional consent for extension of time line till 31st December, 2024. We are very much sure that we shall be completing the project on or before 31st December 2024 and shall be handing over the possessi…”31 December 2026
Extended at the builder's request (MahaRERA application EXT51700028268)
Reason the builder gave MahaRERA:
“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, ca…” Read the full reason
“The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. We intend to execute an agreement with the new customer to mention the date of possession on or before 31/12/2026. Kindly process our application and grant us the extension till 31/12/…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ATLANTA RESIDENCY PHASE II’s extension records on MahaRERA (P51700010106), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ATLANTA RESIDENCY PHASE II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ATLANTA RESIDENCY PHASE IP51700007107 · possession 31 Mar 2019
- MahaRERA registration
- P51700010106
- Status
- Registered and active
- Builder
- SRI BALAJI DEVELOPER
- Location
- Naupada, Thane · 421302
- Project type
- Others
- Registered on
- 24 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2027
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 120
- Sold or booked
- 70%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of ATLANTA RESIDENCY PHASE II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 13 TYPE - 01 - WING - B | 100% | 70% | 50% | 0% |
| BUILDING NO 14 TYPE 01 - WING - B1 | 100% | 70% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 13 TYPE - 01 - WING - B: covers 17 floors
- BUILDING NO 14 TYPE 01 - WING - B1: covers 17 floors
Latest CC order on MahaRERA: dated 17/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ATLANTA RESIDENCY PHASE II every month.
ATLANTA RESIDENCY PHASE II: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 13 TYPE - 01 - WING - B (18 floors, 72 units) · BUILDING NO 14 TYPE 01 - WING - B1 (18 floors, 71 units)
- Car parking: 10 covered, 92 open
- Land: 19,985 sq m (about 4.9 acres) · sanctioned built-up 15,336 sq m · recreational space 4,982 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
SRI Balaji Developer has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 2 still being built, 1 past the promised date (typically 78 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of ATLANTA RESIDENCY PHASE II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ATLANTA RESIDENCY PHASE II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ATLANTA RESIDENCY PHASE II
What is the possession date of ATLANTA RESIDENCY PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ATLANTA RESIDENCY PHASE II in Naupada, Thane is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ATLANTA RESIDENCY PHASE II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ATLANTA RESIDENCY PHASE II's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ATLANTA RESIDENCY PHASE II extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2021, giving the reason "The project is situated at Bhiwandi and owing to covid 19 entire activities of Real estate are badly affected including purchasing power of the people resulting in slow down in demand and cash flow. Real Estate is amongst the worst sector to be affected by covid 19. We intend to complete the project at the earliest. We also request your good selves to further extend the project automatically by six month as per maharera order for covid 19 extension once the extension is allowed for one year upto 30th december , 2020. Kindly allow the extension for one year and thereafter for six month as pe…"; to 31 December 2024, giving the reason "The Project is situated at remote place away from Thane city in Bhiwandi. The outbreak of covid has affected the purchasing power of the people and even construction activities were halted owing to migration of labour since March 2021. We have discussed with all the customers about project extension till 31st December, 2024 and majority of them have considered our request and granted us unconditional consent for extension of time line till 31st December, 2024. We are very much sure that we shall be completing the project on or before 31st December 2024 and shall be handing over the possessi…"; to 31 December 2026, giving the reason "The project was started prior to outbreak of COVID-19, which had an impact on real estate project for nearly 2 years, from March 2020 to February 2022 which has severely impacted the availability of labour and disrupted the supply chain, causing significant delays in the construction activities. This has resulted in slow progress in construction. However, we are trying to complete the project at the earliest. We intend to execute an agreement with the new customer to mention the date of possession on or before 31/12/2026. Kindly process our application and grant us the extension till 31/12/…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ATLANTA RESIDENCY PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ATLANTA RESIDENCY PHASE II in Naupada, Thane is P51700010106.
Is ATLANTA RESIDENCY PHASE II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II is registered as P51700010106 and its status is "Registered and active".
What is the construction status of ATLANTA RESIDENCY PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 70% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does ATLANTA RESIDENCY PHASE II have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ATLANTA RESIDENCY PHASE II safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II is registered on MahaRERA as P51700010106, its completion date has moved 84 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does ATLANTA RESIDENCY PHASE II have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ATLANTA RESIDENCY PHASE I (P51700007107, possession 31 Mar 2019). Check that your agreement names the registration of your own wing.
How can I get updates if ATLANTA RESIDENCY PHASE II's possession date changes?
The latest dates are on ATLANTA RESIDENCY PHASE II's MahaRERA page (P51700010106). GharKundli's Kundli Watch sends a free WhatsApp update on ATLANTA RESIDENCY PHASE II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ATLANTA RESIDENCY PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II has 2 buildings filed: BUILDING NO 13 TYPE - 01 - WING - B with 18 floors and 72 units; BUILDING NO 14 TYPE 01 - WING - B1 with 18 floors and 71 units.
How much parking does ATLANTA RESIDENCY PHASE II have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered and 92 open car parking spaces for ATLANTA RESIDENCY PHASE II.
How big is the land of ATLANTA RESIDENCY PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II stands on 19,985 sq m of land (about 4.9 acres), with 15,336 sq m of sanctioned built-up area and 4,982 sq m of recreational open space.
What is the track record of ATLANTA RESIDENCY PHASE II's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), SRI Balaji Developer has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 2 still being built, 1 past the promised date (typically 78 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ATLANTA RESIDENCY PHASE II?
Google Maps has reviews of ATLANTA RESIDENCY PHASE II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ATLANTA RESIDENCY PHASE II?
ATLANTA RESIDENCY PHASE II by SRI BALAJI DEVELOPER is in Naupada, Thane (pincode 421302), near bhiwandi, Kamatghar, Maharashtra, and is registered on MahaRERA as P51700010106, per GharKundli's check of MahaRERA records.
How many homes are in ATLANTA RESIDENCY PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II has 120 homes in 2 towers registered on MahaRERA, and 70% of them are sold or booked.
When was ATLANTA RESIDENCY PHASE II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ATLANTA RESIDENCY PHASE II was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ATLANTA RESIDENCY PHASE II?
No court cases are listed for ATLANTA RESIDENCY PHASE II on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ATLANTA RESIDENCY PHASE II?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SRI BALAJI DEVELOPER, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ATLANTA RESIDENCY PHASE II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Naupada
- ASAVARI CO OP HSG SOC LTD
- PRANNAV DEVELOPERS PROJECT SARODARSHAN
- HIGHLAND SKY TOWER DAMANI B BUILDING
- HIGHLAND SKY TOWERS A BUILDING
- SHRI KRISHNA GOVIND PRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED
- YASHWANT NIWAS
- SHRAM SAFAL CO-OPERATIVE HOUSING SOCIETY LTD
- Atlanta Luxuria
Other projects by SRI BALAJI DEVELOPER
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.