PULIN CO-OP HOUSING SOCIETY LTD

by TIRUPATI DEVELOPERS · Nerul, ThaneAlso near L&T Seawoods, Ballard Estate

Possession date of PULIN CO-OP HOUSING SOCIETY LTD: 30 April 2032. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700006582, and currently active. Its completion date is now April 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about PULIN CO-OP HOUSING SOCIETY LTD?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PULIN CO-OP HOUSING SOCIETY LTD has moved

  1. 30 December 2031

    Completion date given when the project was registered

  2. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PULIN CO-OP HOUSING SOCIETY LTD’s extension records on MahaRERA (P51700006582), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PULIN CO-OP HOUSING SOCIETY LTD

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700006582
Status
Registered and active
Builder
TIRUPATI DEVELOPERS
Location
Nerul, Thane · 400706
Project type
Others
Registered on
14 Aug 2017
Completion date at registration
December 2031
Latest completion date
April 2032
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
39
Towers
2
Complaints on MahaRERA
1
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
81

Construction progress of PULIN CO-OP HOUSING SOCIETY LTD, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PULIN TOWER100%100%100%100%
PULIN TOWER100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PULIN CO-OP HOUSING SOCIETY LTD every month.

PULIN CO-OP HOUSING SOCIETY LTD: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PULIN CO-OP HOUSING SOCIETY LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PULIN CO-OP HOUSING SOCIETY LTD: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PULIN CO-OP HOUSING SOCIETY LTD

What is the possession date of PULIN CO-OP HOUSING SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PULIN CO-OP HOUSING SOCIETY LTD in Nerul, Thane is 30 April 2032, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PULIN CO-OP HOUSING SOCIETY LTD?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PULIN CO-OP HOUSING SOCIETY LTD's builder has filed on MahaRERA, the official one, is 30 April 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of PULIN CO-OP HOUSING SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PULIN CO-OP HOUSING SOCIETY LTD in Nerul, Thane is P51700006582.

Is PULIN CO-OP HOUSING SOCIETY LTD registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD is registered as P51700006582 and its status is "Registered and active".

What is the construction status of PULIN CO-OP HOUSING SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does PULIN CO-OP HOUSING SOCIETY LTD have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is PULIN CO-OP HOUSING SOCIETY LTD safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD is registered on MahaRERA as P51700006582, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PULIN CO-OP HOUSING SOCIETY LTD's possession date changes?

The latest dates are on PULIN CO-OP HOUSING SOCIETY LTD's MahaRERA page (P51700006582). GharKundli's Kundli Watch sends a free WhatsApp update on PULIN CO-OP HOUSING SOCIETY LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PULIN CO-OP HOUSING SOCIETY LTD have?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD has 2 buildings filed: PULIN TOWER with 9 floors; PULIN TOWER with 2 floors.

How big is the land of PULIN CO-OP HOUSING SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD stands on 1,445 sq m of land (about 0.4 acres), with 1,445 sq m of sanctioned built-up area.

Where can I read reviews of PULIN CO-OP HOUSING SOCIETY LTD?

Google Maps has reviews of PULIN CO-OP HOUSING SOCIETY LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PULIN CO-OP HOUSING SOCIETY LTD?

PULIN CO-OP HOUSING SOCIETY LTD by TIRUPATI DEVELOPERS is in Nerul, Thane (pincode 400706), near L&T Seawoods, Ballard Estate, Maharashtra, and is registered on MahaRERA as P51700006582, per GharKundli's check of MahaRERA records.

How many homes are in PULIN CO-OP HOUSING SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD has 39 homes in 2 towers registered on MahaRERA.

When was PULIN CO-OP HOUSING SOCIETY LTD registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PULIN CO-OP HOUSING SOCIETY LTD was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PULIN CO-OP HOUSING SOCIETY LTD?

2 court cases are listed for PULIN CO-OP HOUSING SOCIETY LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of PULIN CO-OP HOUSING SOCIETY LTD?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TIRUPATI DEVELOPERS, which has 81 other projects registered on MahaRERA.