NIRMAN AAKASH
by DEEPAK SHANKAR YASHWANTE · Dombivli, Thane
Possession: NIRMAN AAKASH is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011174. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about NIRMAN AAKASH?
How the possession date of NIRMAN AAKASH has moved
31 October 2018
Completion date given when the project was registered
31 October 2019
Extended at the builder's request (MahaRERA application EXT51700001921)
Reason the builder gave MahaRERA:
“As per Architect Certificate , we have completed construction and it is applied for completion certificate from competent authority for possession to be handed over to customers , we have been submitting form no 4 to the effect of completio…” Read the full reason
“As per Architect Certificate , we have completed construction and it is applied for completion certificate from competent authority for possession to be handed over to customers , we have been submitting form no 4 to the effect of completion of construction , at the same time occupancy certificate is awaited , same will be uploaded on receipt . Acknowledgment of submission for Completion to competent authority is being uploaded along with FORM No.4 Architect Certificate .”30 September 2021
Extended at the builder's request (MahaRERA application EXT51700006221)
Reason the builder gave MahaRERA:
“आमच्या प्रोजेक्ट ची मुदत 2019 ला संपली आहे आणि आमचे प्रोजेक्ट पूर्ण देखिल झाले आहे परंतु अदयाप आम्हाला महानगरपालिकेकडून अर्ज करुन देखील बांधकाम पूर्णतेचा दाखला मिळालेला नाही त्यामुले दस्त नोंदणी करता येत नाही म्हणून सदर प्रोजेक्ट ची मुदत वा…” Read the full reason
“आमच्या प्रोजेक्ट ची मुदत 2019 ला संपली आहे आणि आमचे प्रोजेक्ट पूर्ण देखिल झाले आहे परंतु अदयाप आम्हाला महानगरपालिकेकडून अर्ज करुन देखील बांधकाम पूर्णतेचा दाखला मिळालेला नाही त्यामुले दस्त नोंदणी करता येत नाही म्हणून सदर प्रोजेक्ट ची मुदत वाढवून मिळावी म्हणून विनंती शिवाय सोबत ठराव देखिल जोडत आहोत”30 March 2022
Revised completion date on MahaRERA
Source: NIRMAN AAKASH’s extension records on MahaRERA (P51700011174), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NIRMAN AAKASH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the March 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011174
- Status
- Completed
- Builder
- DEEPAK SHANKAR YASHWANTE
- Location
- Dombivli, Thane · 421306
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- October 2018
- Latest completion date
- March 2022
- Delay so far
- 41 months
- Homes
- 72
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of NIRMAN AAKASH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NIRMAN AAKASH | 100% | 83% | 65% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRMAN AAKASH every month.
NIRMAN AAKASH: buildings, flats and land, as filed on MahaRERA
- Buildings: NIRMAN AAKASH (7 floors)
- Land: 3,668 sq m (about 0.9 acres) · sanctioned built-up 2,830 sq m · recreational space 734 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NIRMAN AAKASH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NIRMAN AAKASH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NIRMAN AAKASH
What is the possession date of NIRMAN AAKASH?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRMAN AAKASH in Dombivli, Thane is 30 March 2022 — 41 months later than 31 October 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for NIRMAN AAKASH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRMAN AAKASH's builder has filed on MahaRERA, the official one, is 30 March 2022, already 41 months later than the 31 October 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NIRMAN AAKASH extended?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH's builder applied to MahaRERA to extend the completion date 2 times: to 31 October 2019, giving the reason "As per Architect Certificate , we have completed construction and it is applied for completion certificate from competent authority for possession to be handed over to customers , we have been submitting form no 4 to the effect of completion of construction , at the same time occupancy certificate is awaited , same will be uploaded on receipt . Acknowledgment of submission for Completion to competent authority is being uploaded along with FORM No.4 Architect Certificate ."; to 30 September 2021, giving the reason "आमच्या प्रोजेक्ट ची मुदत 2019 ला संपली आहे आणि आमचे प्रोजेक्ट पूर्ण देखिल झाले आहे परंतु अदयाप आम्हाला महानगरपालिकेकडून अर्ज करुन देखील बांधकाम पूर्णतेचा दाखला मिळालेला नाही त्यामुले दस्त नोंदणी करता येत नाही म्हणून सदर प्रोजेक्ट ची मुदत वाढवून मिळावी म्हणून विनंती शिवाय सोबत ठराव देखिल जोडत आहोत".
What is the RERA number of NIRMAN AAKASH?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRMAN AAKASH in Dombivli, Thane is P51700011174.
Is NIRMAN AAKASH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH is registered as P51700011174 and its status is "Completed".
What is the construction status of NIRMAN AAKASH?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH's status on MahaRERA is "Completed". As filed by the builder, slab work on NIRMAN AAKASH is 83% done and internal work 65%. GharKundli's full report compares construction progress with the deadline.
Does NIRMAN AAKASH have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is NIRMAN AAKASH safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH is registered on MahaRERA as P51700011174, its MahaRERA status is "Completed", its completion date has moved 41 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NIRMAN AAKASH's possession date changes?
The latest dates are on NIRMAN AAKASH's MahaRERA page (P51700011174). GharKundli's Kundli Watch sends a free WhatsApp update on NIRMAN AAKASH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NIRMAN AAKASH have?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH has one building filed: NIRMAN AAKASH with 7 floors.
How big is the land of NIRMAN AAKASH?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH stands on 3,668 sq m of land (about 0.9 acres), with 2,830 sq m of sanctioned built-up area and 734 sq m of recreational open space.
Where can I read reviews of NIRMAN AAKASH?
Google Maps has reviews of NIRMAN AAKASH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NIRMAN AAKASH?
NIRMAN AAKASH by DEEPAK SHANKAR YASHWANTE is in Dombivli, Thane (pincode 421306), Maharashtra, and is registered on MahaRERA as P51700011174, per GharKundli's check of MahaRERA records.
How many homes are in NIRMAN AAKASH?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH has 72 homes in 1 tower registered on MahaRERA.
When was NIRMAN AAKASH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), NIRMAN AAKASH was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on NIRMAN AAKASH?
No court cases are listed for NIRMAN AAKASH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of NIRMAN AAKASH?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is DEEPAK SHANKAR YASHWANTE.
Check it yourself on MahaRERA
- How to check the possession date of NIRMAN AAKASH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dombivli
- ARYA ARIANA
- SHIVANAND SUDAMA CO. OP. HSG. SOCIETY. LTD.
- SAI SAMRUDDHI
- RENUKA CHS
- AMALTAS
- YASHRAJ
- BHOIR JEWELS
- MILAN HEIGHTS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.