by FORE HOLDINGS · Dombivli, Thane 421201Also near Vishnunagar, Manpada

What’s in the report? →

Possession date of Yashraj (MahaRERA PM1330002600521): 30 April 2029. It has 58 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1330002600521, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1330002600521, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Yashraj?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Yashraj has moved

  1. 31 December 2028

    Completion date given when the project was registered

  2. 30 April 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Yashraj’s extension records on MahaRERA (PM1330002600521), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Yashraj

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1330002600521
Status
Registered and active
Builder
FORE HOLDINGS
Location
Dombivli, Thane · 421201
Project type
Mixed
Registered on
22 May 2026
Completion date at registration
December 2028
Latest completion date
April 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
58
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Yashraj, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
YASHRAJ0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • YASHRAJ: covers BASEMENT FLOOR + GRD FLOOR + 1ST TO 16TH FLOOR LOWER AND UPPER DUPLEX

Latest CC order on MahaRERA: dated 30/04/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Yashraj every 1–2 months.

Yashraj: buildings, flats and land, as filed on MahaRERA

  • Buildings: YASHRAJ (18 floors, 74 units)
  • Car parking: 42 covered
  • Land: 1,470 sq m (about 0.4 acres) · sanctioned built-up 5,023 sq m
  • Boundaries filed include: RAILWAY LAND BOUNDARY
  • Map: Get directions

The builder’s record and reviews

Fore Holdings has 5 projects on MahaRERA since 2021, this one included. Of the 5 GharKundli has checked: 3 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Yashraj →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Yashraj: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Yashraj

What is the possession date of Yashraj?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Yashraj in Dombivli, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Yashraj?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Yashraj's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Yashraj?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Yashraj in Dombivli, Thane is PM1330002600521.

Is Yashraj registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj is registered as PM1330002600521 and its status is "Registered and active".

What is the current construction status of Yashraj? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj's status on MahaRERA is "Registered and active". As filed by the builder, slab work on YASHRAJ is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Yashraj have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Yashraj safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj is registered on MahaRERA as PM1330002600521, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Yashraj?

Yashraj is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Yashraj?

For a flat in Yashraj (Kalyan-Dombivli), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Yashraj received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Yashraj a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj is a redevelopment: 57 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is KDMCC-25-55848, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Yashraj uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Yashraj was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Yashraj's possession date changes?

The latest dates are on Yashraj's MahaRERA page (PM1330002600521). GharKundli's Kundli Watch sends a free WhatsApp update on Yashraj every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Yashraj have?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj has one building filed: YASHRAJ with 18 floors and 74 units.

How much parking does Yashraj have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 42 covered car parking spaces for Yashraj.

How big is the land of Yashraj?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj stands on 1,470 sq m of land (about 0.4 acres), with 5,023 sq m of sanctioned built-up area.

What is the track record of Yashraj's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Fore Holdings has 5 projects on MahaRERA since 2021, this one included. Of the 5 GharKundli has checked: 3 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Yashraj?

Google Maps has reviews of Yashraj written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Yashraj?

Yashraj by FORE HOLDINGS is in Dombivli, Thane, pincode 421201 (near Vishnunagar, Manpada), Maharashtra, and is registered on MahaRERA as PM1330002600521, per GharKundli's check of MahaRERA records. Its boundaries filed there include RAILWAY LAND BOUNDARY. GharKundli lists all 408 MahaRERA projects in Tilaknagar (421201).

How many flats are in Yashraj, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj has 58 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Yashraj registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Yashraj was registered on MahaRERA on 22 May 2026. GharKundli did not find a title report on the land on file there.

Does Yashraj have any legal issues or court cases?

No court cases are listed for Yashraj on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Yashraj?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is FORE HOLDINGS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in Tilaknagar (421201)

All 408 projects in Tilaknagar (421201) →

Other projects by FORE HOLDINGS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.