GAYATRI PARK
by VIKRAM BUILDERS · Opp Hanuman Mandir, ThaneAlso near Kalwa, Parsik Nagar
Possession: GAYATRI PARK is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700010528. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about GAYATRI PARK?
How the possession date of GAYATRI PARK has moved
31 December 2017
Completion date given when the project was registered
30 April 2018
Extended at the builder's request (MahaRERA application EXT51700000095)
Reason the builder gave MahaRERA: “Dear Sir, We have completed our all work only lift installation work is pending”
Source: GAYATRI PARK’s extension records on MahaRERA (P51700010528), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GAYATRI PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2018 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700010528
- Status
- Completed
- Builder
- VIKRAM BUILDERS
- Location
- Opp Hanuman Mandir, Thane · 400605
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2017
- Latest completion date
- April 2018
- Delay so far
- 4 months
- Homes
- 63
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GAYATRI PARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GAYATRI PARK | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAYATRI PARK every month.
GAYATRI PARK: buildings, flats and land, as filed on MahaRERA
- Buildings: GAYATRI PARK (10 floors)
- Land: 3,590 sq m (about 0.9 acres) · sanctioned built-up 3,044 sq m · recreational space 539 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GAYATRI PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GAYATRI PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GAYATRI PARK
What is the possession date of GAYATRI PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GAYATRI PARK in Opp Hanuman Mandir, Thane is 30 April 2018 — 4 months later than 31 December 2017, the date given at registration.
Is the builder's possession date different from the MahaRERA date for GAYATRI PARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GAYATRI PARK's builder has filed on MahaRERA, the official one, is 30 April 2018, already 4 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GAYATRI PARK extended?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK's builder applied to MahaRERA to extend the completion date once: to 30 April 2018, giving the reason "Dear Sir, We have completed our all work only lift installation work is pending".
What is the RERA number of GAYATRI PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GAYATRI PARK in Opp Hanuman Mandir, Thane is P51700010528.
Is GAYATRI PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK is registered as P51700010528 and its status is "Completed".
What is the construction status of GAYATRI PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK's status on MahaRERA is "Completed". As filed by the builder, slab work on GAYATRI PARK is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does GAYATRI PARK have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GAYATRI PARK safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK is registered on MahaRERA as P51700010528, its MahaRERA status is "Completed", its completion date has moved 4 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GAYATRI PARK's possession date changes?
The latest dates are on GAYATRI PARK's MahaRERA page (P51700010528). GharKundli's Kundli Watch sends a free WhatsApp update on GAYATRI PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GAYATRI PARK have?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK has one building filed: GAYATRI PARK with 10 floors.
How big is the land of GAYATRI PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK stands on 3,590 sq m of land (about 0.9 acres), with 3,044 sq m of sanctioned built-up area and 539 sq m of recreational open space.
Where can I read reviews of GAYATRI PARK?
Google Maps has reviews of GAYATRI PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GAYATRI PARK?
GAYATRI PARK by VIKRAM BUILDERS is in Opp Hanuman Mandir, Thane (pincode 400605), near Kalwa, Parsik Nagar, Maharashtra, and is registered on MahaRERA as P51700010528, per GharKundli's check of MahaRERA records.
How many homes are in GAYATRI PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK has 63 homes in 1 tower registered on MahaRERA.
When was GAYATRI PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GAYATRI PARK was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on GAYATRI PARK?
No court cases are listed for GAYATRI PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of GAYATRI PARK?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIKRAM BUILDERS.
Check it yourself on MahaRERA
- How to check the possession date of GAYATRI PARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- Veer Square (Thane)
- RAJ TATTVA PHASE 1 COMMERCIAL
- MAULI KRUPA
- GURUKRUPA NITYAM
- ASAVARI CO OP HSG SOC LTD
- Mahavir Breeze Phase 1
- Panache
- LOTUS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.