Possession date of SANJANA HEIGHTS: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900046485, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SANJANA HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SANJANA HEIGHTS has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SANJANA HEIGHTS’s extension records on MahaRERA (P51900046485), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SANJANA HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 3 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900046485
Status
Registered and active
Builder
SAFEWAY PROJECTS PVT LTD
Location
Grant Road West, Mumbai · 400036
Project type
Residential / Group Housing
Registered on
5 Aug 2022
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
12
Sold or booked
0%
Towers
1
Complaints on MahaRERA
1
Court cases listed
3
Title report on file
Not found

Construction progress of SANJANA HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SANJANA HEIGHTS100%32.13%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SANJANA HEIGHTS: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SANJANA HEIGHTS every month.

SANJANA HEIGHTS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK822 – 91211
2 BHK8221
  • Buildings: SANJANA HEIGHTS (28 floors, 12 units)
  • Land: 772 sq m (about 0.2 acres) · sanctioned built-up 2,752 sq m · recreational space 376 sq m
  • Boundaries filed include: PLAY GROUND, FORJETT HILL ROAD, NAVYUG NAGAR BUILDING
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SANJANA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SANJANA HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SANJANA HEIGHTS

What is the possession date of SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SANJANA HEIGHTS in Grant Road West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SANJANA HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SANJANA HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SANJANA HEIGHTS in Grant Road West, Mumbai is P51900046485.

Is SANJANA HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS is registered as P51900046485 and its status is "Registered and active".

What is the construction status of SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SANJANA HEIGHTS is 32.13% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does SANJANA HEIGHTS have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SANJANA HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS is registered on MahaRERA as P51900046485, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SANJANA HEIGHTS's possession date changes?

The latest dates are on SANJANA HEIGHTS's MahaRERA page (P51900046485). GharKundli's Kundli Watch sends a free WhatsApp update on SANJANA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SANJANA HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS has one building filed: SANJANA HEIGHTS with 28 floors and 12 units.

What are the flat sizes (carpet area) in SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SANJANA HEIGHTS: 3 BHK: 822 to 912 sq ft carpet (11 homes); 2 BHK: 822 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS stands on 772 sq m of land (about 0.2 acres), with 2,752 sq m of sanctioned built-up area and 376 sq m of recreational open space.

Where can I read reviews of SANJANA HEIGHTS?

Google Maps has reviews of SANJANA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SANJANA HEIGHTS?

SANJANA HEIGHTS by SAFEWAY PROJECTS PVT LTD is in Grant Road West, Mumbai (pincode 400036), near Kurla West, Parel, Byculla, Maharashtra, and is registered on MahaRERA as P51900046485, per GharKundli's check of MahaRERA records. Its boundaries filed there include PLAY GROUND, FORJETT HILL ROAD, NAVYUG NAGAR BUILDING.

How many homes are in SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS has 12 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was SANJANA HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SANJANA HEIGHTS was registered on MahaRERA on 5 August 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SANJANA HEIGHTS?

3 court cases are listed for SANJANA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SANJANA HEIGHTS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAFEWAY PROJECTS PVT LTD.