Moonstone
by S K ENTERPRISE · Neral Mamdapur Sankul, Thane 410101
What’s in the report? →Possession date of Moonstone (MahaRERA P51700016067): 31 March 2025, moved from 30 December 2022 (27 months later), and it has already passed. It has 19 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700016067. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51700016067, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2025) has passed.
What do you want to know about Moonstone?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Moonstone has moved
30 December 2022
Completion date given when the project was registered
30 June 2024
Extended at the builder's request (MahaRERA application EXT51700018836)
Reason the builder gave MahaRERA: “WE ARE UNDER PROCESS OF GETTING OCCUPANCY CERTIFICATE SO WE NEED EXTENSION TILL 30TH JUNE 2024”
31 March 2025
Extended at the builder's request (MahaRERA application EXT51700024932)
Reason the builder gave MahaRERA: “Due to delay in bank loan process”
Source: Moonstone’s extension records on MahaRERA (P51700016067), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Moonstone
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700016067
- Status
- Lapsed (registration period ended)
- Builder
- S K ENTERPRISE
- Location
- Neral Mamdapur Sankul, Thane · 410101
- Project type
- Residential / Group Housing
- Registered on
- 16 Apr 2018
- Completion date at registration
- December 2022
- Latest completion date
- March 2025
- Delay so far
- 27 months
- Homes
- 19
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Moonstone, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Moonstone | 100% | 100% | 100% | 75% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Moonstone every 1–2 months.
Moonstone: buildings, flats and land, as filed on MahaRERA
- Buildings: Moonstone (4 floors)
- Land: 468 sq m (about 0.1 acres) · sanctioned built-up 561 sq m
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Moonstone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Moonstone: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Moonstone
What is the possession date of Moonstone?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Moonstone in Neral Mamdapur Sankul, Thane is 31 March 2025 — 27 months later than 30 December 2022, the date given at registration. That date has already passed.
The date has already moved 27 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Moonstone?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Moonstone's builder has filed on MahaRERA, the official one, is 31 March 2025, already 27 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Moonstone extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2024, giving the reason "WE ARE UNDER PROCESS OF GETTING OCCUPANCY CERTIFICATE SO WE NEED EXTENSION TILL 30TH JUNE 2024"; to 31 March 2025, giving the reason "Due to delay in bank loan process".
What is the RERA number of Moonstone?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Moonstone in Neral Mamdapur Sankul, Thane is P51700016067.
Is Moonstone registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone is registered as P51700016067 and its status is "Lapsed (registration period ended)".
What is the current construction status of Moonstone? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Moonstone is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Moonstone have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Moonstone safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone is registered on MahaRERA as P51700016067, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Moonstone?
Moonstone isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Moonstone?
For a flat in Moonstone (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Moonstone received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 March 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Moonstone?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 March 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Moonstone uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Moonstone was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Moonstone's possession date changes?
The latest dates are on Moonstone's MahaRERA page (P51700016067). GharKundli's Kundli Watch sends a free WhatsApp update on Moonstone every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Moonstone have?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone has one building filed: Moonstone with 4 floors.
How big is the land of Moonstone?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone stands on 468 sq m of land (about 0.1 acres), with 561 sq m of sanctioned built-up area.
What are the reviews of Moonstone?
Google Maps has reviews of Moonstone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Moonstone?
Moonstone by S K ENTERPRISE is in Neral Mamdapur Sankul, Thane, pincode 410101, Maharashtra, and is registered on MahaRERA as P51700016067, per GharKundli's check of MahaRERA records. GharKundli lists all 362 MahaRERA projects in Neral (410101).
How many flats are in Moonstone?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone has 19 homes in 1 tower registered on MahaRERA.
When was Moonstone registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonstone was registered on MahaRERA on 16 April 2018. GharKundli did not find a title report on the land on file there.
Does Moonstone have any legal issues or court cases?
No court cases are listed for Moonstone on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Moonstone?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S K ENTERPRISE, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Moonstone
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Neral (410101)
- Signature Phase 1
- Mira Residency
- Mecca Avenue
- Arena One
- Arya Residency P1
- A Z Landmark
- Vansh Heights
- Swami Aashray
Other projects by S K ENTERPRISE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.