New & under-construction projects in N.D.A. Khadakwasla (411023)
According to GharKundli's check of MahaRERA records, 36 housing projects are registered in pincode 411023 (N.D.A. Khadakwasla, Pune). 15 are still being built, 10 with possession due by the end of 2027. For 22, the completion date on MahaRERA is later than the one first promised. 4 have at least one complaint filed on MahaRERA. 2 were newly registered in the last 6 months.
Pincode 411023 also covers: Shivane, Bhugaon, Kudje, Uttamnagar, Mandvi Bk.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
Newly registered on MahaRERA in N.D.A. Khadakwasla (last 6 months)
- Green City Phase II J Building · registered 1 Oct 2026 · possession due Dec 2028
- Ved Vihar · registered 24 Jun 2026 · possession due Mar 2029
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| Natures Blessings Phase II Nagarkar Developers | De-registered | 30 Mar 2024passed | same | 0 |
| ANSHRAJ ICON VIJAY DEVELOPERS | Active | 15 Dec 2026 | 31 Dec 2025 | 0 |
| Kumar Prakruti Kumar Properties Govind Shree Realtors LLP | Active | 1 Feb 2027 | 1 Oct 2026 | 0 |
| Sai Orchid M/S RUDRA BUILDERS AND DEVELOPERS | Active | 28 Feb 2027 | 31 Mar 2025 | 0 |
| Audumbar Nest Om Chidanand Developers | Active | 30 Apr 2027 | 30 Dec 2026 | 0 |
| Dongar MAATHA M/s Starlight Projects | Active | 30 Apr 2027 | 30 Dec 2026 | 0 |
| Sajan Siddhi D Wing Nemichand Bhandari Associates | Active | 30 Apr 2027 | 31 Dec 2025 | 0 |
| ICON TOWER AYODHYA ASSOCIATES | Active | 1 Jul 2027 | 1 Mar 2027 | 0 |
| SAI NISARG SHRI SAI SHRADDHA DEVELOPERS | Active | 31 Jul 2027 | 30 Dec 2022 | 0 |
| Skyi Wild Woods Phase I Enerrgia Skyi Ventures | Active | 30 Nov 2027 | 31 Jul 2022 | 0 |
| Audumbar Nest A1 A2 and B Building Om Chidanand Developers | Active | 30 Apr 2028 | 30 Dec 2027 | 0 |
| Panama Highstreet MS PANAMA SUNARCH DEVELOPERS | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Green City Phase II J Building Ajit Girdharilal Nahar | Active | 31 Dec 2028 | same | 0 |
| Ved Vihar Damini Vastunirman | Active | 30 Mar 2029 | 30 Nov 2028 | 0 |
| Belview Tranquil Infratech LLP | Active | 1 Nov 2030 | 1 Jul 2030 | 0 |
| FUSION CITY KUMBARE ENTERPRISES | Completed | 1 Sep 2018 | same | 0 |
| LAXMI SHANTIBAN LAXMI ROPERTIES | Completed | 30 Oct 2019 | same | 0 |
| LAXMI VISHNUPURAM LAXMI DEVELOPERS | Completed | 12 Dec 2019 | same | 0 |
| ANANDTARAS HARITARA ANANDTARA PROPERTIES | Completed | 31 Dec 2019 | 31 Dec 2018 | 1 |
| Regal Residency Shamshuddin Abdul Samad Choudhary | Completed | 15 Dec 2020 | same | 0 |
| SHIVAI COMPLEX Sameer Devram Dudhane | Completed | 30 Jan 2021 | 31 Jul 2019 | 0 |
| Audumber OmChidanand | Completed | 1 Nov 2021 | same | 0 |
| Green City AJIT GIRDHARILAL NAHAR | Completed | 30 Dec 2021 | same | 0 |
| AUDUMBAR A1 A2 OM CHIDANAND DEVELOPERS | Completed | 31 May 2024 | 1 Jun 2023 | 0 |
| Aldea Annexo -C1 Puranik Builders Limited | Completed | 30 Dec 2026 | same | 0 |
| GURUMAULI VIJAY VITTHAL CHANDANE | Lapsed | 31 Mar 2019passed | same | 0 |
| WEST COAST PARK PHASE II PATE DEVELOPERS | Lapsed | 15 Feb 2022passed | 30 Jun 2019 | 3 |
| NARMADESHWAR SAHAYADRI DEVELOPERS | Lapsed | 30 Dec 2023passed | same | 0 |
| LAKE VISTA LAKE VISTA PROPERTIS LLP | Lapsed | 30 Jun 2024passed | same | 0 |
| MATOSHREE PARK DHAWADE PATIL INFRASTRUCTURE | Lapsed | 29 Sep 2024passed | 30 Sep 2023 | 0 |
| Bhargav Amantra Bhargav Homes | Lapsed | 30 Dec 2024passed | same | 0 |
| ISHANYA SRUSHTI JOGESHWARI DEVELOPERS | Lapsed | 2 Feb 2025passed | same | 0 |
| GREEN CITY PHASE II K BUILDING AJIT GIRDHARILAL NAHAR | Lapsed | 30 Jun 2025passed | 30 Jun 2024 | 0 |
| Mont Vert Kingstown Sector 1 Residential Wings Niraj Kumar Associates Pvt Ltd | Lapsed | 30 Jun 2026passed | 30 Jun 2025 | 4 |
| AVADHUT CHIDANAND BUILDERS AND DEVELOPERS | Lapsed | 31 Jul 2026passed | 31 Mar 2026 | 0 |
| RANJAI Shinde & Patil Construction | Lapsed | 31 Jul 2026passed | 30 Apr 2023 | 2 |
Questions about projects in N.D.A. Khadakwasla
How many under-construction projects are in N.D.A. Khadakwasla?
According to GharKundli's check of MahaRERA records, 15 are still being built in N.D.A. Khadakwasla (411023), 10 with possession due by the end of 2027, and 10 are marked completed. For 22, the completion date has moved since registration.
Which new projects were registered in N.D.A. Khadakwasla in 2026?
According to GharKundli's check of MahaRERA records, 2 new projects were registered on MahaRERA in N.D.A. Khadakwasla (411023) in 2026. The newest: Green City Phase II J Building (1 Oct 2026) and Ved Vihar (24 Jun 2026).
Other areas in Pune
- Alandi Devachi · 885
- Baner · 713
- Wakad · 644
- Chinchwadgaon · 613
- Ravet · 606
- Kothrud · 428
- Wagholi · 379
- Baramati · 373
- N I B M · 369
- Katraj · 355
- Armament · 332
- Kharadi · 323
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.