Hari Dev Drashti Empire Phase 1

by SHRI HARI REALTY · Mira Bhayander, Thane 421302Also near Bhiwandi, Kamatghar, NaupadaRegistered on MahaRERA as “DEV DRASHTI EMPIRE PHASE 1”

What’s in the report? →

Possession date of Hari Dev Drashti Empire Phase 1 (MahaRERA P51700020837): 30 April 2027, moved from 30 April 2024 (32 months later). It has 209 homes, 52% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700020837, and currently active. Its completion date has moved from April 2024 to April 2027: 32 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700020837, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Hari Dev Drashti Empire Phase 1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Hari Dev Drashti Empire Phase 1 has moved

  1. 30 April 2024

    Completion date given when the project was registered

  2. 29 April 2025

    Extended at the builder's request (MahaRERA application EXT51700019552)

    Reason the builder gave MahaRERA: “Due to shortage of marital not able to complete project please grant us extension for 12 months”
  3. 31 December 2026

    Extended at the builder's request (MahaRERA application EA08072502004)

    Reason the builder gave MahaRERA:
    “We request an extension of the project's MahaRERA registration as several critical works under Interior Services and External Development are still in progress and are scheduled for phased completion up to December 2026, as per the detailed…” Read the full reason“We request an extension of the project's MahaRERA registration as several critical works under Interior Services and External Development are still in progress and are scheduled for phased completion up to December 2026, as per the detailed PERT chart submitted. While the structural and finishing works were largely completed by March 2024, the remaining work — including electrical meter room installation, rainwater harvesting system, landscaping, driveway, compound lighting, and other external service provisions — require additional time due to: Sequencing of technical and finishing stages,…”
  4. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Hari Dev Drashti Empire Phase 1’s extension records on MahaRERA (P51700020837), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Hari Dev Drashti Empire Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700020837
Status
Registered and active
Builder
SHRI HARI REALTY
Location
Mira Bhayander, Thane · 421302
Project type
Others
Registered on
15 May 2019
Completion date at registration
April 2024
Latest completion date
April 2027
Delay so far
32 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
209
Sold or booked
52%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Hari Dev Drashti Empire Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%100%
WING B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • WING A: covers 18 floors
  • WING B: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hari Dev Drashti Empire Phase 1 every 1–2 months.

Hari Dev Drashti Empire Phase 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (19 floors, 166 units) · WING B (18 floors, 69 units)
  • Land: 3,775 sq m (about 0.9 acres) · sanctioned built-up 9,851 sq m · recreational space 1,559 sq m
  • Land, as filed: 107/2, 107/2/A, 108/5, 108/6/1, 108/6/2, 177/7/B, AND 177/7/C
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Shri Hari Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Hari Dev Drashti Empire Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Hari Dev Drashti Empire Phase 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Hari Dev Drashti Empire Phase 1

What is the possession date of Hari Dev Drashti Empire Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hari Dev Drashti Empire Phase 1 in Mira Bhayander, Thane is 30 April 2027 — 32 months later than 30 April 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 32 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Hari Dev Drashti Empire Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Hari Dev Drashti Empire Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2027, already 32 months later than the 30 April 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Hari Dev Drashti Empire Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1's builder applied to MahaRERA to extend the completion date 2 times: to 29 April 2025, giving the reason "Due to shortage of marital not able to complete project please grant us extension for 12 months"; to 31 December 2026, giving the reason "We request an extension of the project's MahaRERA registration as several critical works under Interior Services and External Development are still in progress and are scheduled for phased completion up to December 2026, as per the detailed PERT chart submitted. While the structural and finishing works were largely completed by March 2024, the remaining work — including electrical meter room installation, rainwater harvesting system, landscaping, driveway, compound lighting, and other external service provisions — require additional time due to: Sequencing of technical and finishing stages,…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Hari Dev Drashti Empire Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hari Dev Drashti Empire Phase 1 in Mira Bhayander, Thane is P51700020837.

Is Hari Dev Drashti Empire Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 is registered as P51700020837 and its status is "Registered and active".

What is the current construction status of Hari Dev Drashti Empire Phase 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Hari Dev Drashti Empire Phase 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Hari Dev Drashti Empire Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 is registered on MahaRERA as P51700020837, its completion date has moved 32 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Hari Dev Drashti Empire Phase 1?

Hari Dev Drashti Empire Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Hari Dev Drashti Empire Phase 1?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Hari Dev Drashti Empire Phase 1: gharkundli.com/tools/property-cost-calculator

Has Hari Dev Drashti Empire Phase 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Hari Dev Drashti Empire Phase 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hari Dev Drashti Empire Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Hari Dev Drashti Empire Phase 1's possession date changes?

The latest dates are on Hari Dev Drashti Empire Phase 1's MahaRERA page (P51700020837). GharKundli's Kundli Watch sends a free WhatsApp update on Hari Dev Drashti Empire Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Hari Dev Drashti Empire Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 has 2 buildings filed: WING A with 19 floors and 166 units; WING B with 18 floors and 69 units.

How big is the land of Hari Dev Drashti Empire Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 stands on 3,775 sq m of land (about 0.9 acres), with 9,851 sq m of sanctioned built-up area and 1,559 sq m of recreational open space.

What is the track record of Hari Dev Drashti Empire Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shri Hari Realty (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 3 still being built, 2 past the promised date (typically 26 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Hari Dev Drashti Empire Phase 1?

Google Maps has reviews of Hari Dev Drashti Empire Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Hari Dev Drashti Empire Phase 1?

Hari Dev Drashti Empire Phase 1 by SHRI HARI REALTY is in Mira Bhayander, Thane, pincode 421302 (near Bhiwandi, Kamatghar, Naupada), Maharashtra, and is registered on MahaRERA as P51700020837, per GharKundli's check of MahaRERA records. Its land is filed as 107/2, 107/2/A, 108/5, 108/6/1, 108/6/2, 177/7/B, AND 177/7/C. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Hari Dev Drashti Empire Phase 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 has 209 homes in 2 towers registered on MahaRERA, and 52% of them are sold or booked.

When was Hari Dev Drashti Empire Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Hari Dev Drashti Empire Phase 1 was registered on MahaRERA on 15 May 2019. GharKundli did not find a title report on the land on file there.

Does Hari Dev Drashti Empire Phase 1 have any legal issues or court cases?

No court cases are listed for Hari Dev Drashti Empire Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Hari Dev Drashti Empire Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHRI HARI REALTY.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.