Sunrise Sky City
by SUNRISE REALTORS · Kamatghar, Thane 421305Registered on MahaRERA as “SKY CITY”
What’s in the report? →Possession date of Sunrise Sky City (MahaRERA P51700024337): 30 October 2028, moved from 30 December 2026 (18 months later). It has 261 homes, 53% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700024337, and currently active. Its completion date has moved from December 2026 to October 2028: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700024337, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sunrise Sky City?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sunrise Sky City has moved
30 December 2026
Completion date given when the project was registered
30 June 2028
Extended at the builder's request (MahaRERA application EA12052620942)
Reason the builder gave MahaRERA:
“We've received a revised commencement certificate, which means we'll be building some additional area. To complete this updated plan, we'll need some extra time. The new projected completion date is based on the revised commencement certifi…” Read the full reason
“We've received a revised commencement certificate, which means we'll be building some additional area. To complete this updated plan, we'll need some extra time. The new projected completion date is based on the revised commencement certificate and the updated building plan.”30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sunrise Sky City’s extension records on MahaRERA (P51700024337), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sunrise Sky City
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700024337
- Status
- Registered and active
- Builder
- SUNRISE REALTORS
- Location
- Kamatghar, Thane · 421305
- Project type
- Residential / Group Housing
- Registered on
- 5 Feb 2020
- Completion date at registration
- December 2026
- Latest completion date
- October 2028
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 261
- Sold or booked
- 53%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Sunrise Sky City, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 0% | 0% | 0% | 0% |
| BUILDING B | 100% | 0% | 0% | 0% |
| BUILDING C | 100% | 100% | 45% | 0% |
| BUILDING D | 100% | 100% | 75% | 0% |
| BUILDING E | 100% | 100% | 55% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING A: covers 3 floors
- BUILDING B: covers 8 floors
- BUILDING C: covers 3 floors
- BUILDING D: covers 20 floors
- BUILDING E: covers 20 floors
Latest CC order on MahaRERA: dated 25/02/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sunrise Sky City every 1–2 months.
Sunrise Sky City: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (3 floors, 1 units) · BUILDING B (8 floors, 14 units) · BUILDING C (3 floors, 5 units) · BUILDING D (20 floors, 111 units) · BUILDING E (20 floors, 130 units)
- Car parking: 28 covered, 80 open
- Land: 7,844 sq m (about 1.9 acres) · sanctioned built-up 26,652 sq m · recreational space 1,569 sq m
- Land, as filed: 121/2, 121/3, 162/1, 120/4 PART, 120/8, 134/9/3 PART
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sunrise Sky City →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sunrise Sky City: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sunrise Sky City
What is the possession date of Sunrise Sky City?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sunrise Sky City in Kamatghar, Thane is 30 October 2028 — 18 months later than 30 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sunrise Sky City?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sunrise Sky City's builder has filed on MahaRERA, the official one, is 30 October 2028, already 18 months later than the 30 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sunrise Sky City extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City's builder applied to MahaRERA to extend the completion date once: to 30 June 2028, giving the reason "We've received a revised commencement certificate, which means we'll be building some additional area. To complete this updated plan, we'll need some extra time. The new projected completion date is based on the revised commencement certificate and the updated building plan.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sunrise Sky City?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sunrise Sky City in Kamatghar, Thane is P51700024337.
Is Sunrise Sky City registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City is registered as P51700024337 and its status is "Registered and active".
What is the current construction status of Sunrise Sky City? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Sunrise Sky City have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sunrise Sky City safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City is registered on MahaRERA as P51700024337, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sunrise Sky City?
Sunrise Sky City is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sunrise Sky City?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sunrise Sky City: gharkundli.com/tools/property-cost-calculator
Has Sunrise Sky City received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City is still under construction, with 30 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sunrise Sky City uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sunrise Sky City was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sunrise Sky City's possession date changes?
The latest dates are on Sunrise Sky City's MahaRERA page (P51700024337). GharKundli's Kundli Watch sends a free WhatsApp update on Sunrise Sky City every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sunrise Sky City have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City has 5 buildings filed: BUILDING A with 3 floors and 1 units; BUILDING B with 8 floors and 14 units; BUILDING C with 3 floors and 5 units; BUILDING D with 20 floors and 111 units; BUILDING E with 20 floors and 130 units.
How much parking does Sunrise Sky City have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 covered and 80 open car parking spaces for Sunrise Sky City.
How big is the land of Sunrise Sky City?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City stands on 7,844 sq m of land (about 1.9 acres), with 26,652 sq m of sanctioned built-up area and 1,569 sq m of recreational open space.
What are the reviews of Sunrise Sky City?
Google Maps has reviews of Sunrise Sky City written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sunrise Sky City?
Sunrise Sky City by SUNRISE REALTORS is in Kamatghar, Thane, pincode 421305, Maharashtra, and is registered on MahaRERA as P51700024337, per GharKundli's check of MahaRERA records. Its land is filed as 121/2, 121/3, 162/1, 120/4 PART, 120/8, 134/9/3 PART. GharKundli lists all 13 MahaRERA projects in Bhiwandi (421305).
How many flats are in Sunrise Sky City, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City has 261 homes in 5 towers registered on MahaRERA, and 53% of them are sold or booked.
When was Sunrise Sky City registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunrise Sky City was registered on MahaRERA on 5 February 2020. GharKundli did not find a title report on the land on file there.
Does Sunrise Sky City have any legal issues or court cases?
No court cases are listed for Sunrise Sky City on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sunrise Sky City?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUNRISE REALTORS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sunrise Sky City
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Bhiwandi (421305)
- Shatrunjay Heights
- Vardhaman Vatika
- Sai Vatika Residency
- Siyara Signature
- Siyara Viva
- One Silver Avenue
- Vighnaharta Apartment
- Jangid Empire
Other projects by SUNRISE REALTORS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.